Inspection |
Outcome |
Requested |
Scheduled |
Date Inspected |
Footing/Setback Inspection
|
In Progress
|
7/17/2008
|
7/18/2008
|
07/21/2008
|
|
counter1
|
Footing/Setback Inspection
|
In Progress
|
|
|
07/23/2008
|
|
Monty Johnson
((253) 770-3326)
|
Wallboard / Drywall Inspection
|
In Progress
|
8/18/2008
|
8/18/2008
|
08/18/2008
|
|
Monty Johnson
((253) 770-3326)
|
Footing/Setback Inspection
|
In Progress
|
8/25/2008
|
8/26/2008
|
08/26/2008
|
|
Monty Johnson
((253) 770-3326)
|
Footing/Setback Inspection
|
Approved
|
|
|
09/03/2008
|
|
Monty Johnson
((253) 770-3326)
|
Plumbing Below Slab Inspection
|
In Progress
|
9/12/2008
|
9/15/2008
|
09/16/2008
|
|
Ray Cockerham
((253) 841-5585)
|
Plumbing Below Slab Inspection
|
In Progress
|
9/17/2008
|
9/18/2008
|
09/18/2008
|
|
Monty Johnson
((253) 770-3326)
|
Foundation/Rebar Inspection
|
In Progress
|
9/19/2008
|
9/22/2008
|
09/22/2008
|
|
Monty Johnson
((253) 770-3326)
|
Plumbing Below Slab Inspection
|
In Progress
|
9/29/2008
|
9/30/2008
|
09/30/2008
|
|
Monty Johnson
((253) 770-3326)
|
Slab/Insulation Inspection
|
In Progress
|
10/2/2008
|
10/3/2008
|
10/06/2008
|
|
Ray Cockerham
((253) 841-5585)
|
Foundation/Rebar Inspection
|
Approved
|
11/12/2008
|
11/13/2008
|
11/13/2008
|
|
Monty Johnson
((253) 770-3326)
|
Block Wall Rebar Inspection
|
In Progress
|
11/13/2008
|
11/14/2008
|
11/14/2008
|
|
Monty Johnson
((253) 770-3326)
|
Energy (Insulation) Inspection
|
In Progress
|
12/30/2008
|
12/30/2008
|
12/30/2008
|
|
Monty Johnson
((253) 770-3326)
|
Energy (Insulation) Inspection
|
In Progress
|
1/5/2009
|
1/5/2009
|
01/05/2009
|
|
Monty Johnson
((253) 770-3326)
|
Frame Inspection
|
In Progress
|
1/5/2009
|
1/5/2009
|
01/05/2009
|
|
Monty Johnson
((253) 770-3326)
|
Frame Inspection
|
In Progress
|
1/20/2009
|
1/20/2009
|
01/20/2009
|
|
Shannon King
((253) 840-6684)
|
Frame Inspection
|
Approved
|
|
|
01/21/2009
|
|
rfore
|
Comment Building Div Inspection
|
Approved
|
1/20/2009
|
1/20/2009
|
01/21/2009
|
|
rfore
|
Frame Inspection
|
In Progress
|
1/21/2009
|
1/22/2009
|
01/22/2009
|
|
rfore
|
Mechanical Rough In Inspection
|
In Progress
|
1/21/2009
|
1/22/2009
|
01/22/2009
|
|
rfore
|
Plumbing Rough In Inspection
|
In Progress
|
|
|
01/26/2009
|
|
Monty Johnson
((253) 770-3326)
|
Mechanical Rough In Inspection
|
In Progress
|
1/29/2009
|
1/30/2009
|
01/30/2009
|
|
Monty Johnson
((253) 770-3326)
|
Comment Building Div Inspection
|
Approved
|
2/2/2009
|
|
02/05/2009
|
|
Ray Cockerham
((253) 841-5585)
|
Plumbing Rough In Inspection
|
In Progress
|
2/10/2009
|
2/10/2009
|
02/10/2009
|
|
Ray Cockerham
((253) 841-5585)
|
Plumbing Rough In Inspection
|
In Progress
|
2/19/2009
|
2/20/2009
|
02/20/2009
|
|
rfore
|
Frame Inspection
|
In Progress
|
2/19/2009
|
2/20/2009
|
02/20/2009
|
|
rfore
|
Frame Inspection
|
In Progress
|
3/24/2009
|
3/24/2009
|
03/24/2009
|
|
Monty Johnson
((253) 770-3326)
|
Wallboard / Drywall Inspection
|
In Progress
|
4/1/2009
|
4/1/2009
|
04/01/2009
|
|
rfore
|
Wallboard / Drywall Inspection
|
In Progress
|
4/9/2009
|
4/9/2009
|
04/09/2009
|
|
Monty Johnson
((253) 770-3326)
|
Wallboard / Drywall Inspection
|
In Progress
|
4/13/2009
|
4/14/2009
|
04/14/2009
|
|
Monty Johnson
((253) 770-3326)
|
Mechanical Final Inspection
|
Approved
|
4/23/2009
|
4/24/2009
|
04/24/2009
|
|
Shannon King
((253) 840-6684)
|
Building Final Inspection
|
In Progress
|
4/28/2009
|
4/29/2009
|
04/29/2009
|
|
Monty Johnson
((253) 770-3326)
|
Frame Inspection
|
Approved
|
7/22/2009
|
7/22/2009
|
07/28/2009
|
|
Eric Tague
((253) 864-4192)
|
Shear Wall Inspection
|
In Progress
|
8/3/2009
|
8/3/2009
|
08/03/2009
|
|
Monty Johnson
((253) 770-3326)
|
Comment Building Div Inspection
|
Approved
|
|
|
09/02/2009
|
|
Ray Cockerham
((253) 841-5585)
|
Wallboard / Drywall Inspection
|
In Progress
|
|
|
11/16/2010
|
|
Monty Johnson
((253) 770-3326)
|
Building Final Inspection
|
Approved
|
|
|
02/07/2011
|
|
Monty Johnson
((253) 770-3326)
|
Plumbing Final Inspection
|
Approved
|
|
|
02/07/2011
|
|
Monty Johnson
((253) 770-3326)
|
Planning Final Inspection
|
VOID
|
|
|
12/09/2021
|
|
Legacy user
|
Footing/Setback Inspection
|
VOID
|
7/21/2008
|
7/21/2008
|
12/09/2021
|
|
Monty Johnson
((253) 770-3326)
|
Footing/Setback Inspection
|
VOID
|
7/23/2008
|
7/23/2008
|
12/09/2021
|
|
Shannon King
((253) 840-6684)
|
Foundation/Rebar Inspection
|
VOID
|
8/8/2008
|
8/11/2008
|
12/09/2021
|
|
Monty Johnson
((253) 770-3326)
|
Mechanical Final Inspection
|
VOID
|
9/11/2008
|
9/12/2008
|
12/09/2021
|
|
Monty Johnson
((253) 770-3326)
|
Plumbing Below Slab Inspection
|
VOID
|
9/24/2008
|
9/25/2008
|
12/09/2021
|
|
Monty Johnson
((253) 770-3326)
|
Frame Inspection
|
VOID
|
12/17/2008
|
12/18/2008
|
12/09/2021
|
|
Monty Johnson
((253) 770-3326)
|
Mechanical Rough In Inspection
|
VOID
|
4/22/2009
|
4/23/2009
|
12/09/2021
|
|
Monty Johnson
((253) 770-3326)
|
Building Final Inspection
|
VOID
|
4/24/2009
|
4/27/2009
|
12/09/2021
|
|
rfore
|
Building Final Inspection
|
VOID
|
|
11/16/2010
|
12/09/2021
|
|
Monty Johnson
((253) 770-3326)
|
Building Final Inspection
|
VOID
|
|
1/28/2011
|
12/09/2021
|
|
Monty Johnson
((253) 770-3326)
|