Summary

B-09-0052
Commercial - New Construction
Closed
CAFARO NORTHWEST PARTNERSHIP
Other
2009 SOUTH HILL MALL RENOVATION - COMBO PERMIT
01/16/2009
03/20/2009
09/13/2010
05/10/2011

Locations

Property
6021010051

Property
6021590070

Property
6021590090

* Address
3500 S MERIDIAN

Reviews

Review Type Outcome Est. Completion Date Completed
Building Review Approved 02/18/2009
Planning Review Approved 02/09/2009
Fire Review Approved 02/09/2009
Building Review Approved 02/09/2009 02/09/2009
Engineering Review Approved 02/04/2009
Engineering Traffic Review Approved 02/04/2009

Fees

Paid Fees Amount Paid Owing Date Paid
Building Re-Inspection Fee $660.00 $660.00 Paid 01/22/2010
No
Mechanical Permit Fee $661.40 $661.40 Paid 03/20/2009
No
Plumbing Permit Fee $445.50 $445.50 Paid 03/20/2009
No
Plumbing Plan Review Fee $289.58 $289.58 Paid 03/20/2009
No
WA State Building Code Council Fee (Residential) $4.50 $4.50 Paid 03/20/2009
No
Fire Review Fee (Commercial Building) $265.00 $265.00 Paid 03/20/2009
No
Sewer System Development Charge $10,883.00 $10,883.00 Paid 03/20/2009
No
Building Permit Fee $26,778.75 $26,778.75 Paid 03/20/2009
No
Mechanical Plan Review Fee $429.91 $429.91 Paid 03/20/2009
No
Building Plan Review Fee $17,406.19 $17,406.19 Paid 01/30/2009
No
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


Permit(s) will not be issued until outstanding fees have been paid in full. Fee details shown above only include currently payable fees, there might be addtional fees to be paid before issuance.

$0.00

Inspections

Inspection Outcome Requested Scheduled Date Inspected
Fire Final Inspection In Progress 10/1/2009 10/01/2009
rfore
Ceiling Grid/T-Bar Inspection In Progress 10/1/2009 10/01/2009
Shannon King ((253) 840-6684)
Frame Inspection In Progress 10/5/2009 10/05/2009
Shannon King ((253) 840-6684)
Wallboard / Drywall Inspection In Progress 10/5/2009 10/05/2009
Shannon King ((253) 840-6684)
Wallboard / Drywall Inspection In Progress 10/07/2009
Shannon King ((253) 840-6684)
Ceiling Grid/T-Bar Inspection In Progress 10/7/2009 10/07/2009
Shannon King ((253) 840-6684)
Frame Inspection In Progress 10/09/2009
Shannon King ((253) 840-6684)
Plumbing Below Slab Inspection In Progress 10/09/2009
Shannon King ((253) 840-6684)
Gas Test Inspection Approved 10/9/2009 10/09/2009
Shannon King ((253) 840-6684)
Wallboard / Drywall Inspection In Progress 10/12/2009 10/12/2009
Shannon King ((253) 840-6684)
Wallboard / Drywall Inspection In Progress 10/14/2009
Shannon King ((253) 840-6684)
Frame Inspection In Progress 10/13/2009 10/14/2009
Shannon King ((253) 840-6684)
Wallboard / Drywall Inspection In Progress 10/14/2009 10/14/2009
Shannon King ((253) 840-6684)
Wallboard / Drywall Inspection Approved 10/16/2009 10/16/2009
rfore
Ceiling Grid/T-Bar Inspection In Progress 10/20/2009 10/20/2009
Shannon King ((253) 840-6684)
Frame Inspection In Progress 10/20/2009 10/20/2009
Shannon King ((253) 840-6684)
Ceiling Grid/T-Bar Inspection Approved 10/20/2009 10/21/2009 10/21/2009
Shannon King ((253) 840-6684)
Frame Inspection In Progress 10/22/2009 10/22/2009
Shannon King ((253) 840-6684)
Wallboard / Drywall Inspection In Progress 10/22/2009 10/22/2009
Shannon King ((253) 840-6684)
Energy (Insulation) Inspection In Progress 10/22/2009 10/22/2009
Shannon King ((253) 840-6684)
Wallboard / Drywall Inspection In Progress 10/23/2009 10/23/2009
Shannon King ((253) 840-6684)
Mechanical Rough In Inspection In Progress 10/26/2009 10/26/2009
Shannon King ((253) 840-6684)
Ceiling Grid/T-Bar Inspection In Progress 10/26/2009 10/26/2009
Shannon King ((253) 840-6684)
Wallboard / Drywall Inspection In Progress 10/26/2009 10/26/2009
Shannon King ((253) 840-6684)
Ceiling Grid/T-Bar Inspection In Progress 10/27/2009 10/27/2009
rfore
Wallboard / Drywall Inspection In Progress 10/27/2009 10/27/2009
rfore
Ceiling Grid/T-Bar Inspection In Progress 10/26/2009 10/28/2009 10/28/2009
Shannon King ((253) 840-6684)
Wallboard / Drywall Inspection In Progress 10/29/2009 10/29/2009
Shannon King ((253) 840-6684)
Ceiling Grid/T-Bar Inspection In Progress 10/29/2009 10/29/2009
Shannon King ((253) 840-6684)
Frame Inspection In Progress 2/18/2010 02/18/2010
Shannon King ((253) 840-6684)
Plumbing Final Inspection Approved 03/17/2010
rfore
Fire Final Inspection Approved 5/27/2010 06/04/2010
rfore
Building Final Inspection In Progress 8/2/2010 08/02/2010
rfore
Comment Building Div Inspection VOID 12/09/2021
Shannon King ((253) 840-6684)
Mechanical Rough In Inspection VOID 12/09/2021
Shannon King ((253) 840-6684)
Comment Building Div Inspection VOID 12/09/2021
Shannon King ((253) 840-6684)
Plumbing Final Inspection VOID 10/1/2009 12/09/2021
Shannon King ((253) 840-6684)
Mechanical Final Inspection VOID 10/1/2009 12/09/2021
Shannon King ((253) 840-6684)
Building Final Inspection VOID 4/24/2009 10/1/2009 12/09/2021
Shannon King ((253) 840-6684)
Frame Inspection VOID 10/2/2009 12/09/2021
Shannon King ((253) 840-6684)
Wallboard / Drywall Inspection VOID 10/6/2009 12/09/2021
Shannon King ((253) 840-6684)
Mechanical Rough In Inspection VOID 10/6/2009 12/09/2021
Shannon King ((253) 840-6684)
Frame Inspection VOID 10/6/2009 12/09/2021
Shannon King ((253) 840-6684)
Frame Inspection VOID 10/7/2009 12/09/2021
Shannon King ((253) 840-6684)
Mechanical Rough In Inspection VOID 10/7/2009 12/09/2021
Shannon King ((253) 840-6684)
Plumbing Rough In Inspection VOID 10/9/2009 12/09/2021
Shannon King ((253) 840-6684)
Frame Inspection VOID 10/8/2009 10/9/2009 12/09/2021
Shannon King ((253) 840-6684)
Ceiling Grid/T-Bar Inspection VOID 10/14/2009 12/09/2021
Shannon King ((253) 840-6684)
Mechanical Final Inspection VOID 2/18/2010 12/09/2021
Shannon King ((253) 840-6684)
Comment Building Div Inspection VOID 2/18/2010 12/09/2021
Shannon King ((253) 840-6684)
Comment Building Div Inspection VOID 2/22/2010 12/09/2021
rfore
Plumbing Final Inspection VOID 2/23/2010 12/09/2021
Shannon King ((253) 840-6684)
Plumbing Rough In Inspection VOID 3/15/2010 12/09/2021
rfore
Comment Building Div Inspection VOID 5/24/2010 12/09/2021
Shannon King ((253) 840-6684)
Comment Building Div Inspection VOID 6/11/2010 6/11/2010 12/09/2021
Shannon King ((253) 840-6684)

Conditions

Condition Status Department Category Expiration Date Due Date
General Permit Conditions Resolved Building Division Standard Conditions
: Final approval by the Building Official is required prior to occupancy. WORK SHALL NOT PROCEED UNTIL THE INSPECTOR HAS APPROVED THE STAGES OF CONSTRUCTION SURFACE STORM WATER SHALL BE DIVERTED FROM THE BUILDING SITE AND SHALL NOT DRAIN ONTO ADJACENT PROPERTIES. Rain drains shall connect to the storm sewer or discharge at the street. I hereby acknowledge that I have read this Permit/Application, that the information given is correct: that I am the owner or the duly authorized agent of the owner; that plans submitted herewith are in compliance with all applicable city, county and state laws and that all construction will proceed in accordance with said laws. This permit shall expire if work is not commenced with 180 days or if the work is suspended for a period of 180 days. Once work has started (passed a required inspection) one inspection per year must be completed to keep active or it will formally expire and become null and void. BY LEAVING THE CONTRACTOR INFORMATION SECTION BLANK, I HEREBY CERTIFY FURTHER THAT CONTRACTORS (GENERAL OR SUBCONTRACTORS) WILL NOT BE HIRED TO PERFORM ANY WORK IN ASSOCIATION WITH THIS PERMIT. I ALSO CERTIFY THAT IF I DO CHOOSE TO HIRE A CONTRACTOR (GENERAL OR SUBCONTRACTOR) I WILL ONLY HIRE THOSE CONTRACTORS THAT ARE LICENSED BY THE STATE OF WASHINGTON.
Building Permit Standard Conditions Resolved Building Division Standard Conditions
: PERMIT CONDITIONS: FIRE REVIEW: 1. The electrical plans submitted with fire alarm device locations are not approved. A separate permit is required for fire alarm work. 2. A separate permit is required for any relocation of fire sprinkler heads. 3. Fire final is required for this permit. PLANNING CONDITIONS: Mechanical equipment shall be screened from public rights-of-way per PMC 20.30.045(1). BUILDING REVIEW: 1) FR wood use is allowed in accordance with section 603 IBC (where generally concealed in construction). Other use of combustible construction is limited by 603, please reference for other proposed uses of combustibles. 2) Special Inspection Due to the phasing and sequencing of the project; a special inspection program that tracks the project sequencing is requested (1704.1.1 and 1705 IBC). Summary approval inspection (reports) will be required by the special inspector in conjunction with the project sequencing. PAY AFTER HOURS INSPECTION FEES PRIOR TO BUILDING FINAL

Related Permit & Planning Applications

There are no related items for this permit application.