| Inspection | Outcome | Requested | Scheduled | Date Inspected | 
            
                
                    | Mechanical Rough In Inspection | In Progress |  | 12/10/2009 | 12/10/2009 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Plumbing Below Slab Inspection | Approved | 12/16/2009 | 12/16/2009 | 12/16/2009 | 
 
                
                    
                        |  | rfore | 
                
                
                    | Footing/Setback Inspection | In Progress | 12/16/2009 | 12/16/2009 | 12/16/2009 | 
 
                
                    
                        |  | rfore | 
                
                
                    | Slab/Insulation Inspection | In Progress |  | 12/17/2009 | 12/17/2009 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Footing/Setback Inspection | In Progress |  | 12/23/2009 | 12/23/2009 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Mechanical Rough In Inspection | In Progress |  | 12/24/2009 | 12/24/2009 | 
 
                
                    
                        |  | rfore | 
                
                
                    | Plumbing Rough In Inspection | In Progress |  | 12/31/2009 | 01/04/2010 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Footing/Setback Inspection | In Progress |  | 1/13/2010 | 01/13/2010 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Wallboard / Drywall Inspection | In Progress |  | 1/13/2010 | 01/13/2010 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Frame Inspection | In Progress |  | 1/14/2010 | 01/13/2010 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Wallboard / Drywall Inspection | In Progress |  | 1/20/2010 | 01/20/2010 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Foundation/Rebar Inspection | In Progress | 1/22/2010 | 1/22/2010 | 01/22/2010 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Slab/Insulation Inspection | In Progress | 1/22/2010 | 1/22/2010 | 01/22/2010 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Frame Inspection | In Progress | 1/22/2010 | 1/23/2010 | 01/25/2010 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Foundation/Rebar Inspection | In Progress |  |  | 01/29/2010 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Frame Inspection | In Progress |  | 2/2/2010 | 02/02/2010 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Wallboard / Drywall Inspection | In Progress |  | 2/2/2010 | 02/02/2010 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Wallboard / Drywall Inspection | In Progress |  | 2/3/2010 | 02/03/2010 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Wallboard / Drywall Inspection | In Progress |  | 2/4/2010 | 02/04/2010 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Energy (Insulation) Inspection | In Progress |  | 2/4/2010 | 02/04/2010 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Mechanical Rough In Inspection | In Progress |  | 12/31/2009 | 02/08/2010 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Mechanical Rough In Inspection | In Progress |  | 2/9/2010 | 02/09/2010 | 
 
                
                    
                        |  | rfore | 
                
                
                    | Wallboard / Drywall Inspection | In Progress |  |  | 02/11/2010 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Gas Test Inspection | Approved |  |  | 02/11/2010 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Frame Inspection | In Progress |  |  | 02/11/2010 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Energy (Insulation) Inspection | In Progress |  | 2/12/2010 | 02/11/2010 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Energy (Insulation) Inspection | In Progress |  |  | 02/12/2010 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Frame Inspection | In Progress |  | 2/16/2010 | 02/16/2010 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Wallboard / Drywall Inspection | In Progress |  | 2/16/2010 | 02/16/2010 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Energy (Insulation) Inspection | In Progress |  | 2/17/2010 | 02/16/2010 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Energy (Insulation) Inspection | In Progress |  |  | 02/18/2010 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Frame Inspection | In Progress | 2/19/2010 | 2/20/2010 | 02/22/2010 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Frame Inspection | In Progress |  | 2/23/2010 | 02/23/2010 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Frame Inspection | In Progress |  | 2/24/2010 | 02/24/2010 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Wallboard / Drywall Inspection | In Progress |  | 2/25/2010 | 02/25/2010 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Wallboard / Drywall Inspection | In Progress |  | 2/26/2010 | 02/26/2010 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Frame Inspection | In Progress |  | 3/2/2010 | 03/02/2010 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Energy (Insulation) Inspection | In Progress |  | 3/3/2010 | 03/03/2010 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Frame Inspection | In Progress |  | 3/3/2010 | 03/03/2010 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Wallboard / Drywall Inspection | In Progress |  | 3/3/2010 | 03/03/2010 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Wallboard / Drywall Inspection | In Progress |  | 3/5/2010 | 03/05/2010 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Frame Inspection | In Progress |  | 3/5/2010 | 03/05/2010 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Frame Inspection | In Progress |  | 3/8/2010 | 03/08/2010 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Wallboard / Drywall Inspection | In Progress |  | 3/8/2010 | 03/08/2010 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Energy (Insulation) Inspection | In Progress |  | 3/10/2010 | 03/10/2010 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Frame Inspection | In Progress |  | 3/10/2010 | 03/10/2010 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Wallboard / Drywall Inspection | In Progress |  |  | 03/11/2010 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Energy (Insulation) Inspection | In Progress | 3/11/2010 | 3/11/2010 | 03/11/2010 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Comment Building Div Inspection | In Progress |  | 3/12/2010 | 03/12/2010 | 
 
                
                    
                        |  | rfore | 
                
                
                    | Wallboard / Drywall Inspection | In Progress | 3/11/2010 | 3/12/2010 | 03/12/2010 | 
 
                
                    
                        |  | rfore | 
                
                
                    | Mechanical Rough In Inspection | Approved |  | 3/16/2010 | 03/16/2010 | 
 
                
                    
                        |  | rfore | 
                
                
                    | Wallboard / Drywall Inspection | In Progress |  | 3/16/2010 | 03/16/2010 | 
 
                
                    
                        |  | rfore | 
                
                
                    | Comment Building Div Inspection | In Progress |  | 3/17/2010 | 03/17/2010 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Frame Inspection | Approved |  |  | 03/23/2010 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Ceiling Grid/T-Bar Inspection | Approved |  | 3/23/2010 | 03/23/2010 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Energy (Insulation) Inspection | Approved |  | 3/23/2010 | 03/23/2010 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Plumbing Final Inspection | Approved |  |  | 03/26/2010 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Mechanical Final Inspection | Approved |  | 3/26/2010 | 03/26/2010 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Fire Final Inspection | In Progress |  | 3/26/2010 | 03/26/2010 | 
 
                
                    
                        |  | rfore | 
                
                
                    | Fire Final Inspection | Approved |  |  | 04/07/2010 | 
 
                
                    
                        |  | kenb | 
                
                
                    | Building Final Inspection | Approved |  | 4/15/2010 | 04/15/2010 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Plumbing Below Slab Inspection | VOID |  |  | 12/09/2021 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Engineering Final Inspection | VOID |  |  | 12/09/2021 | 
 
                
                    
                        |  | Marcus Sedlickas
                              
                                ((253) 405-1707) | 
                
                
                    | Gas Test Inspection | VOID |  |  | 12/09/2021 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Comment Building Div Inspection | VOID |  |  | 12/09/2021 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Plumbing Rough In Inspection | VOID |  | 12/15/2009 | 12/09/2021 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Comment Building Div Inspection | VOID |  | 1/13/2010 | 12/09/2021 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Gas Test Inspection | VOID |  | 1/20/2010 | 12/09/2021 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Frame Inspection | VOID | 1/22/2010 | 1/22/2010 | 12/09/2021 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Frame Inspection | VOID |  | 1/26/2010 | 12/09/2021 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Shear Wall Inspection | VOID | 1/29/2010 | 1/29/2010 | 12/09/2021 | 
 
                
                    
                        |  | rfore | 
                
                
                    | Frame Inspection | VOID | 1/29/2010 | 1/30/2010 | 12/09/2021 | 
 
                
                    
                        |  | Eric Tague
                              
                                ((253) 864-4192) | 
                
                
                    | Compliance Inspection Building Inspection | VOID | 1/29/2010 | 1/30/2010 | 12/09/2021 | 
 
                
                    
                        |  | Eric Tague
                              
                                ((253) 864-4192) | 
                
                
                    | Frame Inspection | VOID |  | 2/3/2010 | 12/09/2021 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Gas Test Inspection | VOID |  | 2/3/2010 | 12/09/2021 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Frame Inspection | VOID |  | 2/4/2010 | 12/09/2021 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Wallboard / Drywall Inspection | VOID |  | 2/8/2010 | 12/09/2021 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Energy (Insulation) Inspection | VOID |  | 2/8/2010 | 12/09/2021 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Comment Building Div Inspection | VOID |  | 2/11/2010 | 12/09/2021 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Frame Inspection | VOID |  | 2/12/2010 | 12/09/2021 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Energy (Insulation) Inspection | VOID |  | 2/18/2010 | 12/09/2021 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Wallboard / Drywall Inspection | VOID |  | 2/18/2010 | 12/09/2021 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Energy (Insulation) Inspection | VOID |  | 3/9/2010 | 12/09/2021 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Frame Inspection | VOID |  | 3/9/2010 | 12/09/2021 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Wallboard / Drywall Inspection | VOID |  | 3/9/2010 | 12/09/2021 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Comment Building Div Inspection | VOID |  | 3/10/2010 | 12/09/2021 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Ceiling Grid/T-Bar Inspection | VOID |  | 3/22/2010 | 12/09/2021 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Mechanical Final Inspection | VOID |  | 3/24/2010 | 12/09/2021 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Plumbing Final Inspection | VOID |  | 3/25/2010 | 12/09/2021 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Comment Building Div Inspection | VOID |  | 3/26/2010 | 12/09/2021 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Building Final Inspection | VOID |  | 3/26/2010 | 12/09/2021 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Comment Building Div Inspection | VOID |  | 4/6/2010 | 12/09/2021 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) | 
                
                
                    | Building Final Inspection | VOID |  | 4/13/2010 | 12/09/2021 | 
 
                
                    
                        |  | Shannon King
                              
                                ((253) 840-6684) |