CITY OF PUYALLUP PERMITTING PORTAL

Permit Application Status

B-10-0046


In order to request inspections, you need to be signed in.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

B-10-0046
Building
Closed
PUYALLUP SCHOOL DIST NO 3
Other
CONST ITC FOR PUYALLUP SCHOOL DISTRICT ADDITION
01/27/2010
01/27/2010
07/26/2010
01/29/2010

Locations

Property
0419043117

* Address
1501 39TH AVE SW

Reviews

There are no reviews for this permit application, or you are not authorized to view them.

Fees

There are no fees for this permit application, or you are not authorized to view them.

Inspections

Inspection Outcome Requested Scheduled Date Inspected
Building Final Inspection Approved 1/27/2010 1/28/2010 01/29/2010
Shannon King ((253) 840-6684)

Conditions

Condition Status Department Category Expiration Date Due Date
General Permit Conditions Resolved Building Division Standard Conditions
: Final approval by the Building Official is required prior to occupancy. WORK SHALL NOT PROCEED UNTIL THE INSPECTOR HAS APPROVED THE STAGES OF CONSTRUCTION SURFACE STORM WATER SHALL BE DIVERTED FROM THE BUILDING SITE AND SHALL NOT DRAIN ONTO ADJACENT PROPERTIES. Rain drains shall connect to the storm sewer or discharge at the street. I hereby acknowledge that I have read this Permit/Application, that the information given is correct: that I am the owner or the duly authorized agent of the owner; that plans submitted herewith are in compliance with all applicable city, county and state laws and that all construction will proceed in accordance with said laws. This permit shall expire if work is not commenced with 180 days or if the work is suspended for a period of 180 days. Once work has started (passed a required inspection) one inspection per year must be completed to keep active or it will formally expire and become null and void. BY LEAVING THE CONTRACTOR INFORMATION SECTION BLANK, I HEREBY CERTIFY FURTHER THAT CONTRACTORS (GENERAL OR SUBCONTRACTORS) WILL NOT BE HIRED TO PERFORM ANY WORK IN ASSOCIATION WITH THIS PERMIT. I ALSO CERTIFY THAT IF I DO CHOOSE TO HIRE A CONTRACTOR (GENERAL OR SUBCONTRACTOR) I WILL ONLY HIRE THOSE CONTRACTORS THAT ARE LICENSED BY THE STATE OF WASHINGTON.
Building Permit Standard Conditions Resolved Building Division Standard Conditions
: PERMIT CONDITIONS:

Related Permit & Planning Applications

There are no related items for this permit application.

Documents & Images

No documents are currently available for viewing.


Should you need assistance, please contact the Permit Center at (253) 864-4165 option 1.