Summary

B-10-0509
Commercial - New Construction
Expired
BCC PUYALLUP LLC
Other
RENEVATIONS - SOUTH HILL BUSINESS & TECHNOLOGY CENTER- BLDG B NO PLUMB/MECH
08/06/2010
12/09/2010
01/01/2012

Locations

Property
0419034038

* Address
1111 39TH AVE SE

Reviews

Review Type Outcome Est. Completion Date Completed
Fire Review VOID 12/09/2021
Building Review Approved 09/15/2010
Fire Review Approved 09/14/2010
Planning Review Approved 08/20/2010
Engineering Review Approved 08/20/2010

Fees

Paid Fees Amount Paid Owing Date Paid
Building Plan Review Fee $1,737.94 $1,737.94 Paid 12/09/2010
No
Building Permit Fee $2,673.75 $2,673.75 Paid 12/09/2010
No
WA State Building Code Council Fee (Residential) $4.50 $4.50 Paid 12/09/2010
No
Fire Review Fee (Commercial Building) $265.00 $265.00 Paid 12/09/2010
No
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


Permit(s) will not be issued until outstanding fees have been paid in full. Fee details shown above only include currently payable fees, there might be addtional fees to be paid before issuance.

$0.00

Inspections

Inspection Outcome Requested Scheduled Date Inspected
Frame Inspection In Progress 12/30/2010 12/30/2010
rfore
Frame Inspection In Progress 1/20/2011 01/20/2011
Monty Johnson ((253) 770-3326)
Energy (Insulation) Inspection Approved 05/10/2011
Monty Johnson ((253) 770-3326)
Frame Inspection Approved 5/10/2011 05/10/2011
Monty Johnson ((253) 770-3326)
Ceiling Grid/T-Bar Inspection Approved 5/23/2011 05/23/2011
Monty Johnson ((253) 770-3326)
Mechanical Rough In Inspection VOID 12/09/2021
Legacy user
Foundation/Rebar Inspection VOID 12/09/2021
Legacy user
Plumbing Rough In Inspection VOID 12/09/2021
Legacy user
Mechanical Final Inspection VOID 12/09/2021
Legacy user
Footing/Setback Inspection VOID 12/09/2021
Legacy user
Shear Wall Inspection VOID 12/09/2021
Legacy user
Planning Final Inspection VOID 12/09/2021
Legacy user
Frame Inspection VOID 12/09/2021
Legacy user
Carbon Monoxide Detectors Inspection VOID 12/09/2021
Legacy user
Building Final Inspection VOID 12/09/2021
Legacy user
Ceiling Grid/T-Bar Inspection VOID 12/09/2021
Legacy user
Plumbing Final Inspection VOID 12/09/2021
Legacy user
Energy (Insulation) Inspection VOID 12/09/2021
Legacy user
Fire Final Inspection VOID 12/09/2021
Legacy user
Combination Frame And Rough In Inspection VOID 12/09/2021
Legacy user
Comment Building Div Inspection VOID 5/10/2011 12/09/2021
Monty Johnson ((253) 770-3326)
Comment Building Div Inspection VOID 7/5/2011 12/09/2021
jonw

Conditions

Condition Status Department Category Expiration Date Due Date
General Permit Conditions Resolved Building Division Standard Conditions
: Final approval by the Building Official is required prior to occupancy. WORK SHALL NOT PROCEED UNTIL THE INSPECTOR HAS APPROVED THE STAGES OF CONSTRUCTION SURFACE STORM WATER SHALL BE DIVERTED FROM THE BUILDING SITE AND SHALL NOT DRAIN ONTO ADJACENT PROPERTIES. Rain drains shall connect to the storm sewer or discharge at the street. I hereby acknowledge that I have read this Permit/Application, that the information given is correct: that I am the owner or the duly authorized agent of the owner; that plans submitted herewith are in compliance with all applicable city, county and state laws and that all construction will proceed in accordance with said laws. This permit shall expire if work is not commenced with 180 days or if the work is suspended for a period of 180 days. Once work has started (passed a required inspection) one inspection per year must be completed to keep active or it will formally expire and become null and void. BY LEAVING THE CONTRACTOR INFORMATION SECTION BLANK, I HEREBY CERTIFY FURTHER THAT CONTRACTORS (GENERAL OR SUBCONTRACTORS) WILL NOT BE HIRED TO PERFORM ANY WORK IN ASSOCIATION WITH THIS PERMIT. I ALSO CERTIFY THAT IF I DO CHOOSE TO HIRE A CONTRACTOR (GENERAL OR SUBCONTRACTOR) I WILL ONLY HIRE THOSE CONTRACTORS THAT ARE LICENSED BY THE STATE OF WASHINGTON.
Building Permit Standard Conditions Resolved Building Division Standard Conditions
: PERMIT CONDITIONS: Building Review Maintain fire ratings in existing building elements. FIRE MARSHAL REVIEW: 1. FIRE SPRINKLER SYSTEMS SHALL BE INTER-TIED TO CREAT ONE SYSTEM WITH ONE FDC. 2. FIRE MARSHAL FINAL INSPECTION IS REQUIRED 3. UNDERGROUND PLANS WILL BE REQUIRED FOR ANY CHANGES

Related Permit & Planning Applications

There are no related items for this permit application.

Documents & Images

No documents are currently available for viewing.


Should you need assistance, please contact the Permit Center at (253) 864-4165 option 1.