CITY OF PUYALLUP PERMITTING PORTAL

Permit Application Status

B-10-0527


In order to request inspections, you need to be signed in.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

B-10-0527
Sign/Awning
Closed
SOUTHLAND CORP TAX DEPT
Other
FREESTANDING SIGN - (1) 80 SQ FT 7-ELEVEN
08/12/2010
09/01/2010
02/08/2011
03/04/2011

Locations

Reviews

Review Type Outcome Est. Completion Date Completed
Building Review Approved 08/16/2010
Planning Review Approved 08/16/2010

Fees

Paid Fees Amount Paid Owing Date Paid
WA State Building Code Council Fee (Residential) $4.50 $4.50 Paid 09/01/2010
No
Legacy Fee $37.50 $37.50 Paid 09/01/2010
No
Building Permit Fee $125.25 $125.25 Paid 09/01/2010
No
Building Plan Review Fee $81.41 $81.41 Paid 08/12/2010
No
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


Permit(s) will not be issued until outstanding fees have been paid in full. Fee details shown above only include currently payable fees, there might be addtional fees to be paid before issuance.

$0.00

Inspections

Inspection Outcome Requested Scheduled Date Inspected
Sign Footing Inspection Approved 9/28/2010 09/28/2010
Monty Johnson ((253) 770-3326)
Sign Final Inspection Approved 9/30/2010 09/30/2010
Monty Johnson ((253) 770-3326)

Conditions

Condition Status Department Category Expiration Date Due Date
General Permit Conditions Resolved Building Division Standard Conditions
: Final approval by the Building Official is required prior to occupancy. WORK SHALL NOT PROCEED UNTIL THE INSPECTOR HAS APPROVED THE STAGES OF CONSTRUCTION SURFACE STORM WATER SHALL BE DIVERTED FROM THE BUILDING SITE AND SHALL NOT DRAIN ONTO ADJACENT PROPERTIES. Rain drains shall connect to the storm sewer or discharge at the street. I hereby acknowledge that I have read this Permit/Application, that the information given is correct: that I am the owner or the duly authorized agent of the owner; that plans submitted herewith are in compliance with all applicable city, county and state laws and that all construction will proceed in accordance with said laws. This permit shall expire if work is not commenced with 180 days or if the work is suspended for a period of 180 days. Once work has started (passed a required inspection) one inspection per year must be completed to keep active or it will formally expire and become null and void. BY LEAVING THE CONTRACTOR INFORMATION SECTION BLANK, I HEREBY CERTIFY FURTHER THAT CONTRACTORS (GENERAL OR SUBCONTRACTORS) WILL NOT BE HIRED TO PERFORM ANY WORK IN ASSOCIATION WITH THIS PERMIT. I ALSO CERTIFY THAT IF I DO CHOOSE TO HIRE A CONTRACTOR (GENERAL OR SUBCONTRACTOR) I WILL ONLY HIRE THOSE CONTRACTORS THAT ARE LICENSED BY THE STATE OF WASHINGTON.
Right Of Way Permit Conditions Resolved Engineering Division Standard Conditions
: * THE APPLICANT IS RESPONSIBLE TO CALL THE INSPECTION LINE AT 253-445-4795 OR 253-445-5092 TO SCHEDULE INSPECTIONS. Enter action code 6910 when prompted. * UTILITY INSPECTIONS ARE REQUIRED PRIOR TO BACKFILLING. * For Engineering questions arising in the field, please contact the Engineering Inspector at 253-405-1707. * No work shall be done in or on the public right of way without a licensed and bonded contractor first obtaining a right of way permit. * The applicant is responsible to call the Utility Notification Center at 1-800-424-5555 before beginning any excavation. Call before you dig, it's the law. * Adhere to approved Traffic Control Plan. * Any curb, gutter or sidewalk broken now or during construction shall be removed and replaced per City Standards. * The applicant is responsible for keeping the existing right of way free of debris and dirt. Sediment control and erosion procedures shall be implemented to prevent off site damage. * The applicant is required to have the approved permit on site at all times.

Related Permit & Planning Applications

There are no related items for this permit application.

Documents & Images

No documents are currently available for viewing.