Summary

B-11-0030
Commercial - New Construction
Closed
RJ 1526 LLC
Other
REPAIR EXISTING BUILDING DAMAGED BY FIRE - HAGEN BUILD BLDG/PLUMB C OF O 9/19/12
01/18/2011
05/26/2011
02/01/2012
09/19/2012

Locations

Reviews

Review Type Outcome Est. Completion Date Completed
Building Review VOID 12/09/2021
Building Review VOID 12/09/2021
Fire Review Approved 05/25/2011
Building Review Approved 05/20/2011
Engineering Review Approved 02/02/2011
Planning Review Approved 01/24/2011

Fees

Paid Fees Amount Paid Owing Date Paid
Plumbing Permit Fee $52.00 $52.00 Paid 12/16/2011
No
Exhaust Vent Fan (Bath) Fee $13.00 $13.00 Paid 12/16/2011
No
Plumbing Plan Review Fee $59.80 $59.80 Paid 05/26/2011
No
WA State Building Code Council Fee (Residential) $4.50 $4.50 Paid 05/26/2011
No
Plumbing Permit Fee $92.00 $92.00 Paid 05/26/2011
No
Fire Review Fee (Commercial Building) $265.00 $265.00 Paid 05/26/2011
No
Sewer System Development Charge $2,119.88 $2,119.88 Paid 05/26/2011
No
Building Permit Fee $2,393.75 $2,393.75 Paid 05/26/2011
No
Water System Development Charge $838.84 $838.84 Paid 05/26/2011
No
Building Plan Review Fee $1,555.94 $1,555.94 Paid 01/18/2011
No
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


Permit(s) will not be issued until outstanding fees have been paid in full. Fee details shown above only include currently payable fees, there might be addtional fees to be paid before issuance.

$0.00

Inspections

Inspection Outcome Requested Scheduled Date Inspected
Foundation/Rebar Inspection Approved 8/5/2011 08/05/2011
Monty Johnson ((253) 770-3326)
Frame Inspection In Progress 9/16/2011 09/16/2011
Monty Johnson ((253) 770-3326)
Shear Wall Inspection In Progress 9/23/2011 09/23/2011
Monty Johnson ((253) 770-3326)
Frame Inspection In Progress 10/4/2011 10/04/2011
Monty Johnson ((253) 770-3326)
Frame Inspection In Progress 11/02/2011
Monty Johnson ((253) 770-3326)
Plumbing Rough In Inspection Approved 11/2/2011 11/02/2011
Monty Johnson ((253) 770-3326)
Frame Inspection Approved 12/14/2011 12/14/2011
Monty Johnson ((253) 770-3326)
Energy (Insulation) Inspection Approved 12/19/2011 12/19/2011
Monty Johnson ((253) 770-3326)
Wallboard / Drywall Inspection Approved 12/23/2011 12/23/2011
Monty Johnson ((253) 770-3326)
Engineering Final Inspection Approved 05/15/2012
charris
Plumbing Final Inspection Approved 6/4/2012 06/04/2012
Monty Johnson ((253) 770-3326)
Fire Final Inspection Approved 7/25/2012 07/25/2012
rfore
Building Final Inspection Approved 9/19/2012 09/19/2012
Monty Johnson ((253) 770-3326)
Comment Building Div Inspection VOID 7/19/2011 12/09/2021
Monty Johnson ((253) 770-3326)
Building Final Inspection VOID 7/25/2011 12/09/2021
Monty Johnson ((253) 770-3326)
Frame Inspection VOID 12/7/2011 12/09/2021
Monty Johnson ((253) 770-3326)
Building Final Inspection VOID 8/1/2012 12/09/2021
Monty Johnson ((253) 770-3326)

Conditions

Condition Status Category
General Permit Conditions Resolved Standard Conditions
Building Division
* Final approval by the Building Official is required prior to occupancy. *Work shall not proceed until the inspector has approved the stages of construction. *Surface storm water shall be diverted from the building site and shall not drain onto adjacent properties. Rain drains shall connect to the storm sewer or discharge at the street. * I hereby acknowledge that I have read this Permit/Application, that the information given is correct: that I am the owner or the duly authorized agent of the owner; that plans submitted herewith are in compliance with all applicable city, county and state laws and that all construction will proceed in accordance with said laws. This permit shall expire if work is not commenced with 180 days or if the work is suspended for a period of 180 days. Once work has started (passed a required inspection) one inspection per year must be completed to keep active or it will formally expire and become null and void. * By leaving the contractor information section blank, I hereby certify further that contractors (general or subcontractors) will not be hired to perform any work in association with this permit. I also certify that if I do choose to hire a contractor (general or subcontractor) I will only hire those contractors that are licensed by the state of Washington.
Building Permit Standard Conditions Resolved Standard Conditions
Building Division
PERMIT CONDITIONS: 1. THE APPLICANT IS RESPONSIBLE TO CALL THE INSPECTION LINE AT 253-445-4795 OR 253-445-5092 TO SCHEDULE INSPECTIONS. UTILITY INSPECTIONS ARE REQUIRED PRIOR TO BACKFILLING. 2. For Engineering questions arising in the field, please contact the Engineering Inspector at 253-405-1707. 3. No work shall be done in or on the public right of way without a licensed and bonded contractor first obtaining a right of way permit. FIRE CODE OFFICIAL CONDITONS: 1. FIRE SEPARATIONS MAY BE REQUIRED FOR THE FOLLOWING CONDITIONS: A. FURNACE THAT IS OVER 400,000BTU B. BOILER IS OVER 15PSI AND 10HP C. STORAGE UNDER STAIRS 2. FIRE EXTINGUISHERS ARE REQUIRED PER IFC. CONTACT FIRE INSPECTOR DURING CONSTRUCTION TO HELP LAYOUT EXTINGUISHERS ONSITE. 3. EGRESS LIGHTING WILL BE TESTED TO DETERMINE IF ADEQUATE. 4. SIX INCH ADDRESS NUMBER IS REQUIRED ON BUILDING 5. KNOX KEY BOX IS REQUIRED FOR BUILDING. 6. COMPLY WITH ALL REDLINES ON APPROVED PLANS

Related Permit & Planning Applications

There are no related items for this permit application.

Documents & Images

No documents are currently available for viewing.


Should you need assistance, please contact the Permit Center at (253) 864-4165 option 1.