Summary

B-11-0116
Commercial - New Construction
Closed
CAFARO NORTHWEST PARTNERSHIP
Other
COMM BUILD INSTALLATION OF WALK-IN FREEZER/COOLERS IN STOCK AREA, NEW ROOF UNITS & NEW DRY LABELING ROOM. SALES FLOOR DECORE TO MATCH NEW LAYOUT - TARGET
03/09/2011
06/14/2011
09/05/2011
10/11/2011

Locations

Reviews

Review Type Outcome Est. Completion Date Completed
Building Review Approved 04/27/2011
Fire Review Approved 03/29/2011
Planning Review Approved 03/14/2011
Engineering Review Approved 03/14/2011

Fees

Paid Fees Amount Paid Owing Date Paid
Building Division Fee (Hourly) $165.00 $165.00 Paid 07/25/2011
No
Mechanical Permit Fee $64.00 $64.00 Paid 06/14/2011
No
Building Permit Fee $5,133.75 $5,133.75 Paid 06/14/2011
No
WA State Building Code Council Fee (Residential) $4.50 $4.50 Paid 06/14/2011
No
Plumbing Permit Fee $211.00 $211.00 Paid 06/14/2011
No
Mechanical Plan Review Fee $41.60 $41.60 Paid 03/09/2011
No
Plumbing Plan Review Fee $137.15 $137.15 Paid 03/09/2011
No
Fire Review Fee (Commercial Building) $265.00 $265.00 Paid 03/09/2011
No
Building Plan Review Fee $3,336.94 $3,336.94 Paid 03/09/2011
No
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


Permit(s) will not be issued until outstanding fees have been paid in full. Fee details shown above only include currently payable fees, there might be addtional fees to be paid before issuance.

$0.00

Inspections

Inspection Outcome Requested Scheduled Date Inspected
Slab/Insulation Inspection In Progress 07/19/2011
Shannon King ((253) 840-6684)
Plumbing Below Slab Inspection In Progress 08/10/2011
Shannon King ((253) 840-6684)
Mechanical Rough In Inspection In Progress 8/11/2011 08/11/2011
Monty Johnson ((253) 770-3326)
Ceiling Grid/T-Bar Inspection In Progress 8/16/2011 08/16/2011
Monty Johnson ((253) 770-3326)
Frame Inspection In Progress 8/24/2011 08/24/2011
Monty Johnson ((253) 770-3326)
Plumbing Below Slab Inspection In Progress 8/25/2011 08/25/2011
Monty Johnson ((253) 770-3326)
Plumbing Rough In Inspection In Progress 8/26/2011 08/26/2011
Monty Johnson ((253) 770-3326)
Mechanical Rough In Inspection In Progress 9/15/2011 09/15/2011
Shannon King ((253) 840-6684)
Plumbing Final Inspection In Progress 9/26/2011 09/26/2011
Monty Johnson ((253) 770-3326)
Ceiling Grid/T-Bar Inspection In Progress 09/28/2011
Monty Johnson ((253) 770-3326)
Mechanical Final Inspection In Progress 9/30/2011 09/30/2011
Monty Johnson ((253) 770-3326)
Fire Final Inspection Approved 10/5/2011 10/05/2011
kenb
Building Final Inspection Approved 10/6/2011 10/06/2011
Monty Johnson ((253) 770-3326)
Engineering Final Inspection Approved 10/10/2011
charris
Comment Building Div Inspection VOID 12/09/2021
Shannon King ((253) 840-6684)
Pre-Construction Building Inspection VOID 7/18/2011 7/19/2011 12/09/2021
Shannon King ((253) 840-6684)
Slab/Insulation Inspection VOID 7/20/2011 12/09/2021
Shannon King ((253) 840-6684)
Frame Inspection VOID 7/25/2011 12/09/2021
Monty Johnson ((253) 770-3326)
Frame Inspection VOID 8/5/2011 12/09/2021
Shannon King ((253) 840-6684)
Comment Building Div Inspection VOID 8/8/2011 12/09/2021
Monty Johnson ((253) 770-3326)
Frame Inspection VOID 8/8/2011 12/09/2021
Monty Johnson ((253) 770-3326)
Plumbing Rough In Inspection VOID 8/10/2011 12/09/2021
Shannon King ((253) 840-6684)
Ceiling Grid/T-Bar Inspection VOID 9/7/2011 12/09/2021
Shannon King ((253) 840-6684)
Mechanical Rough In Inspection VOID 9/14/2011 12/09/2021
Shannon King ((253) 840-6684)
Mechanical Rough In Inspection VOID 9/28/2011 12/09/2021
Monty Johnson ((253) 770-3326)
Mechanical Final Inspection VOID 10/4/2011 12/09/2021
Monty Johnson ((253) 770-3326)
Mechanical Rough In Inspection VOID 10/5/2011 12/09/2021
Monty Johnson ((253) 770-3326)
Building Final Inspection VOID 10/5/2011 12/09/2021
Monty Johnson ((253) 770-3326)

Conditions

Condition Status Department Category Expiration Date Due Date
General Permit Conditions Resolved Building Division Standard Conditions
: * Final approval by the Building Official is required prior to occupancy. *Work shall not proceed until the inspector has approved the stages of construction. *Surface storm water shall be diverted from the building site and shall not drain onto adjacent properties. Rain drains shall connect to the storm sewer or discharge at the street. * I hereby acknowledge that I have read this Permit/Application, that the information given is correct: that I am the owner or the duly authorized agent of the owner; that plans submitted herewith are in compliance with all applicable city, county and state laws and that all construction will proceed in accordance with said laws. This permit shall expire if work is not commenced with 180 days or if the work is suspended for a period of 180 days. Once work has started (passed a required inspection) one inspection per year must be completed to keep active or it will formally expire and become null and void. * By leaving the contractor information section blank, I hereby certify further that contractors (general or subcontractors) will not be hired to perform any work in association with this permit. I also certify that if I do choose to hire a contractor (general or subcontractor) I will only hire those contractors that are licensed by the state of Washington. FIRE CODE OFFICIAL REVIEW: 1. PERMITS ARE REQUIRED FOR ANY FIRE SPRINKLER OR FIRE ALARM WORK. 2. FIRE FINAL INSPECTION IS REQUIRED FOR THIS PERMIT(IVR 9200) BUILDING PERMIT REVIEW: AFFADAVIT OF TESTING AND REFERIGERATION QUANTITIES REQUIRED FROM THE INSTALLER (2009 IMC SECTION 1108.4).

Related Permit & Planning Applications

There are no related items for this permit application.

Documents & Images

No documents are currently available for viewing.


Should you need assistance, please contact the Permit Center at (253) 864-4165 option 1.