Summary

B-11-0588
Demolition
Expired
BCC PUYALLUP LLC
Demolition
DEMO (3) STEEL WATER TANKS AND A 11,456 SF CONCRETE BLDG ~ SOUTH HILL DATA CENTER
09/19/2011
10/13/2011
03/17/2012

Locations

Property
0419034038

* Address
1111 39TH AVE SE

Reviews

Review Type Outcome Est. Completion Date Completed
Fire Review Approved 10/12/2011
Building Review Approved 09/23/2011
Planning Review Approved 09/22/2011
Engineering Review Approved 09/20/2011

Fees

Paid Fees Amount Paid Owing Date Paid
WA State Building Code Council Fee (Residential) $4.50 $4.50 Paid 10/13/2011
No
Building Permit Fee $462.45 $462.45 Paid 10/13/2011
No
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


Permit(s) will not be issued until outstanding fees have been paid in full. Fee details shown above only include currently payable fees, there might be addtional fees to be paid before issuance.

$0.00

Inspections

Inspection Outcome Requested Scheduled Date Inspected
Comment Building Div Inspection VOID 12/09/2021
Legacy user
Building Final Inspection VOID 12/09/2021
Legacy user
Engineering Final Inspection VOID 12/09/2021
Legacy user

Conditions

Condition Status Department Category Expiration Date Due Date
General Permit Conditions Resolved Building Division Standard Conditions
: * Final approval by the Building Official is required prior to occupancy. *Work shall not proceed until the inspector has approved the stages of construction. *Surface storm water shall be diverted from the building site and shall not drain onto adjacent properties. * I hereby acknowledge that I have read this Permit/Application, that the information given is correct: that I am the owner or the duly authorized agent of the owner; that plans submitted herewith are in compliance with all applicable city, county and state laws and that all construction will proceed in accordance with said laws. This permit shall expire if work is not commenced with 180 days or if the work is suspended for a period of 180 days. Once work has started (passed a required inspection) one inspection per year must be completed to keep active or it will formally expire and become null and void. * By leaving the contractor information section blank, I hereby certify further that contractors (general or subcontractors) will not be hired to perform any work in association with this permit. I also certify that if I do choose to hire a contractor (general or subcontractor) I will only hire those contractors that are licensed by the state of Washington. 1) DEMOLITION TO BE COMPLETED PER INDICATED REGULATIONS IN ASBESTOS REPORT AND ASSOCIATED DEMOLITION REQUIREMENTS. 2) STRUCTURAL INSPECTIONS OR CHANGES MAY BE NECESSARY AS THE TWO BUILDINGS ARE ADJOINING AND MAY SHARE STRUCTURAL ELEMENTS.
Demolition Standard Conditions Resolved Engineering Division Standard Conditions
: 1. I agree to call the Engineering inspector at 253-405-1707 to inspect the cut and cap of the sanitary sidesewer at property line. The existing sidesewer shall not be re-used. 2. I agree to call the inspection line at 253-445-4795 or 253-445-5092 to schedule a building final inspection. Enter action code 9800 when prompted for Builidng Inspection Final. 3. I agree to call the Utility Notification Center at 1-800-424-5555 before beginning any excavation. Call before you dig, it's the law. 5. The applicant is responsible to decommision the existing septic system per P.C.H.D requirements. A decommissioning certificate is required to be filed with P.C.H.D. and a copy submitted to the City of Puyallup. 6. The applicant is responsible to decommision the existing private well per P.C.H.D. requirements. A decommissioning certificate is required to be filed with P.C.H.D. and a copy submitted to the City of Puyallup. 7. The City water division shall perform the water service removal. Contact Perry Baird at 253-841-5512 to schedule. 8. I hereby acknowledge that I have read and understand the contents of this permit and I hereby state that the information I have supplied is true and correct. The Applicant shall defend, indemnify, and hold the City, its officers, employees and volunteers harmless from any and all claims, injuries, damages, losses or suits including attorney fees, arising out of or in connection with activities or operations performed by the Applicant or on the Applicant's behalf out of issuance of this permit.

Related Permit & Planning Applications

There are no related items for this permit application.

Documents & Images

No documents are currently available for viewing.


Should you need assistance, please contact the Permit Center at (253) 864-4165 option 1.