Summary

B-13-0602
Demolition
Expired
WASHINGTON COLD STORAGE INC
Demolition
DEMO 6231 SQ FT OF (2) FREEZER ROOMS ~ WASHINGTON COLD STORAGE
07/23/2013
03/02/2014

Locations

Reviews

Review Type Outcome Est. Completion Date Completed
Building Review VOID 12/09/2021
Building Review Approved 08/27/2013
Planning Review Approved 07/24/2013

Fees

Paid Fees Amount Paid Owing Date Paid
WA State Building Code Council Fee (Residential) $4.50 $4.50 Paid 09/03/2013
No
Building Permit Fee $888.75 $888.75 Paid 09/03/2013
No
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


Permit(s) will not be issued until outstanding fees have been paid in full. Fee details shown above only include currently payable fees, there might be addtional fees to be paid before issuance.

$0.00

Inspections

Inspection Outcome Requested Scheduled Date Inspected
Building Final Inspection VOID 12/09/2021
Legacy user
Comment Building Div Inspection VOID 12/09/2021
Legacy user
Engineering Final Inspection VOID 12/09/2021
Legacy user

Conditions

Condition Status Department Category Expiration Date Due Date
General Permit Conditions Resolved Building Division Standard Conditions
: * Final approval by the Building Official is required prior to occupancy. *Work shall not proceed until the inspector has approved the stages of construction. *Surface storm water shall be diverted from the building site and shall not drain onto adjacent properties. * I hereby acknowledge that I have read this Permit/Application, that the information given is correct: that I am the owner or the duly authorized agent of the owner; that plans submitted herewith are in compliance with all applicable city, county and state laws and that all construction will proceed in accordance with said laws. This permit shall expire if work is not commenced with 180 days or if the work is suspended for a period of 180 days. Once work has started (passed a required inspection) one inspection per year must be completed to keep active or it will formally expire and become null and void. * By leaving the contractor information section blank, I hereby certify further that contractors (general or subcontractors) will not be hired to perform any work in association with this permit. I also certify that if I do choose to hire a contractor (general or subcontractor) I will only hire those contractors that are licensed by the state of Washington. FIRE: 1 REMOVE DEMOLISHED DEVICE DESCRIPTIONS FROM THE FIRE ALARM CONTROL PANEL 2 IVR-9200 FIRE FINAL BUILDING PERMIT INSPECTION REQUIRED BUILDING: 1) ASBESTOS REMOVAL SHALL MEET WASHINGTON STATE AND PUGET SOUND CLEAN AIR AGENCY REQUIREMENTS. 2) ENGINEER SHALL PROVIDE DETAILS FOR ENCLOSING BUILDING WHEN DEMOLITION IS COMPLETED AND PRIOR TO CONSTRUCTION OF THAT ENCLOSURE. 3) SCOPE OF DEMOLITION AS APPLIED FOR ARE ROOMS #1, 5 AND 6.
Demolition Standard Conditions Resolved Engineering Division Standard Conditions
: 1. I agree to call the Engineering inspector at 253-405-1707 to inspect the cut and cap of the sanitary sidesewer at property line. The existing sidesewer shall not be re-used. 2. I agree to call the inspection line at 253-445-4795 or 253-445-5092 to schedule a building final inspection. Enter action code 9800 when prompted for Building Inspection Final. 3. I agree to call the Utility Notification Center at 1-800-424-5555 before beginning any excavation. Call before you dig, it's the law. 5. The applicant is responsible to decommission the existing septic system per P.C.H.D requirements. A decommissioning certificate is required to be filed with P.C.H.D. and a copy submitted to the City of Puyallup. 6. The applicant is responsible to decommission the existing private well per P.C.H.D. requirements. A decommissioning certificate is required to be filed with P.C.H.D. and a copy submitted to the City of Puyallup. If the existing private well is to be retained it will be necessary to install a RPBA on the domestic connection to the City’s system. 7. The City water division shall perform the water service removal. Contact Perry Baird at 253-841-5512 to schedule. I hereby acknowledge that I have read and understand the contents of this permit and I hereby state that the information I have supplied is true and correct. The Applicant shall defend, indemnify, and hold the City, its officers, employees and volunteers harmless from any and all claims, injuries, damages, losses or suits including attorney fees, arising out of or in connection with activities or operations performed by the Applicant or on the Applicant's behalf out of issuance of this permit.
Pipeline Notfication Rcw 19.122.033 Resolved Engineering Division Standard Conditions
: Effective January 1, 2013 RCW 19.122 Before conducting any construction or excavation within 100 feet of a right-of-way or utility easement containing a transmission pipeline a person must notify the pipeline companies of the scheduled excavation through the one-number locator service 811. Notification must occur in a window of not less than 2 business days but not more than 10 business days before beginning the excavation. If a transmission pipeline company is notified that excavation work will occur near a pipeline, a representative of the company must consult with the excavator on-site prior to excavation.

Related Permit & Planning Applications

There are no related items for this permit application.