| Inspection |
Outcome |
Requested |
Scheduled |
Date Inspected |
|
Plumbing Below Slab Inspection
|
Approved
|
|
|
10/08/2013
|
|
|
Shannon King
((253) 840-6684)
|
|
Slab/Insulation Inspection
|
Approved
|
|
|
10/09/2013
|
|
|
Shannon King
((253) 840-6684)
|
|
Combination Frame And Rough In Inspection
|
In Progress
|
|
10/16/2013
|
10/16/2013
|
|
|
Shannon King
((253) 840-6684)
|
|
Plumbing Rough In Inspection
|
Approved
|
|
10/16/2013
|
10/16/2013
|
|
|
Shannon King
((253) 840-6684)
|
|
Mechanical Rough In Inspection
|
In Progress
|
|
10/18/2013
|
10/18/2013
|
|
|
Shannon King
((253) 840-6684)
|
|
Wallboard / Drywall Inspection
|
Approved
|
|
10/18/2013
|
10/18/2013
|
|
|
Shannon King
((253) 840-6684)
|
|
Mechanical Rough In Inspection
|
In Progress
|
|
10/21/2013
|
10/21/2013
|
|
|
Shannon King
((253) 840-6684)
|
|
Ceiling Grid/T-Bar Inspection
|
Approved
|
|
11/1/2013
|
11/01/2013
|
|
|
Shannon King
((253) 840-6684)
|
|
Mechanical Final Inspection
|
Approved
|
|
12/2/2013
|
12/02/2013
|
|
|
Shannon King
((253) 840-6684)
|
|
Plumbing Final Inspection
|
Approved
|
|
12/2/2013
|
12/02/2013
|
|
|
Shannon King
((253) 840-6684)
|
|
Fire Final Inspection
|
Resubmittal Required
|
|
12/5/2013
|
12/05/2013
|
|
|
rfore
|
|
Building Final Inspection
|
Approved
|
|
12/5/2013
|
12/05/2013
|
|
|
Shannon King
((253) 840-6684)
|
|
Plumbing Rough In Inspection
|
VOID
|
|
10/8/2013
|
12/09/2021
|
|
|
Shannon King
((253) 840-6684)
|
|
Foundation/Rebar Inspection
|
VOID
|
|
10/9/2013
|
12/09/2021
|
|
|
Shannon King
((253) 840-6684)
|
|
Plumbing Final Inspection
|
VOID
|
|
11/26/2013
|
12/09/2021
|
|
|
Monty Johnson
((253) 770-3326)
|
|
Mechanical Final Inspection
|
VOID
|
|
11/26/2013
|
12/09/2021
|
|
|
Monty Johnson
((253) 770-3326)
|
|
Building Final Inspection
|
VOID
|
|
12/4/2013
|
12/09/2021
|
|
|
Shannon King
((253) 840-6684)
|