Summary

B-14-0496
Commercial - New Construction
Closed
IAC VABP LLC
Other
TI ~ LJ SMITH BLDG B ~ PORT 167 LOGISTIC CENTER
06/30/2014
07/31/2014
03/16/2015
12/01/2014

Locations

Reviews

Review Type Outcome Est. Completion Date Completed
Building Review VOID 12/09/2021
Building Review Approved 07/23/2014
Planning Review Approved 07/15/2014
Engineering Review Approved 07/07/2014

Fees

Paid Fees Amount Paid Owing Date Paid
WA State Building Code Council Fee (Residential) $4.50 $4.50 Paid 07/31/2014
No
Fire Review Fee (Commercial Building) $265.00 $265.00 Paid 07/31/2014
No
Traffic Impact Fee $73,035.00 $73,035.00 Paid 07/31/2014
No
Building Permit Fee $2,533.75 $2,533.75 Paid 07/31/2014
No
Building Plan Review Fee $1,646.94 $1,646.94 Paid 07/01/2014
No
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


Permit(s) will not be issued until outstanding fees have been paid in full. Fee details shown above only include currently payable fees, there might be addtional fees to be paid before issuance.

$0.00

Inspections

Inspection Outcome Requested Scheduled Date Inspected
Wallboard / Drywall Inspection In Progress 8/27/2014 08/27/2014
Shannon King ((253) 840-6684)
Frame Inspection In Progress 8/27/2014 08/27/2014
Shannon King ((253) 840-6684)
Frame Inspection Approved 8/28/2014 08/28/2014
Shannon King ((253) 840-6684)
Wallboard / Drywall Inspection In Progress 9/5/2014 09/05/2014
Shannon King ((253) 840-6684)
Energy (Insulation) Inspection Approved 09/08/2014
Shannon King ((253) 840-6684)
Wallboard / Drywall Inspection In Progress 9/9/2014 09/09/2014
Shannon King ((253) 840-6684)
Wallboard / Drywall Inspection Approved 9/11/2014 09/11/2014
Shannon King ((253) 840-6684)
Foundation/Rebar Inspection In Progress 9/18/2014 09/18/2014
Shannon King ((253) 840-6684)
Ceiling Grid/T-Bar Inspection Approved 9/23/2014 09/23/2014
Shannon King ((253) 840-6684)
Building Final Inspection In Progress 9/29/2014 09/29/2014
Shannon King ((253) 840-6684)
Fire Final Inspection Approved 9/29/2014 09/29/2014
rfore
Emergency Radio Test Review Inspection Approved 12/01/2014
Ray Cockerham ((253) 841-5585)
Building Final Inspection Approved 11/13/2014 12/01/2014
Ray Cockerham ((253) 841-5585)
Foundation/Rebar Inspection VOID 12/09/2021
Shannon King ((253) 840-6684)
Frame Inspection VOID 8/14/2014 12/09/2021
Shannon King ((253) 840-6684)
Frame Inspection VOID 8/22/2014 12/09/2021
Shannon King ((253) 840-6684)
Wallboard / Drywall Inspection VOID 9/3/2014 12/09/2021
Shannon King ((253) 840-6684)
Wallboard / Drywall Inspection VOID 9/8/2014 12/09/2021
Shannon King ((253) 840-6684)
Frame Inspection VOID 9/15/2014 12/09/2021
Shannon King ((253) 840-6684)
Foundation/Rebar Inspection VOID 9/17/2014 12/09/2021
Shannon King ((253) 840-6684)

Conditions

Condition Status Category
General Permit Conditions Resolved Standard Conditions
Building Division
* Final approval by the Building Official is required prior to occupancy. *Work shall not proceed until the inspector has approved the stages of construction. *Surface storm water shall be diverted from the building site and shall not drain onto adjacent properties. * I hereby acknowledge that I have read this Permit/Application, that the information given is correct: that I am the owner or the duly authorized agent of the owner; that plans submitted herewith are in compliance with all applicable city, county and state laws and that all construction will proceed in accordance with said laws. This permit shall expire if work is not commenced with 180 days or if the work is suspended for a period of 180 days. Once work has started (passed a required inspection) one inspection per year must be completed to keep active or it will formally expire and become null and void. * By leaving the contractor information section blank, I hereby certify further that contractors (general or subcontractors) will not be hired to perform any work in association with this permit. I also certify that if I do choose to hire a contractor (general or subcontractor) I will only hire those contractors that are licensed by the state of Washington. PLANNING CONDITIONS: * ANY DISPLACED LANDSCAPING SHALL BE REPLACED IN-KIND
Building Permit Standard Conditions Resolved Standard Conditions
Building Division
PERMIT CONDITIONS: FIRE: 1 ANY MODIFICATION TO THE FIRE SPRINKLER OR FIRE ALARM SYSTEMS SHALL REQUIRE A SEPERATE PERMIT. 2 CITY OF PUYALLUP MUNICIPAL CODE REQUIRES "TOTAL COVERAGE" PER NFPA 72. 3 FIRE ALARM CONTRACTOR SHALL BE UL CERTIFIED. 4 COMPLY WITH IFC 2012 EDITION SECTION 510 EMERGENCY RESPONDER RADIO COVERAGE. QUESTIONS REGARDING ACCEPTANCE TESTING CAN BE DIRECTED TO, RAY COCKERHAM, THE BUILDING AND FIRE CODE OFFICIAL. (253-841-5585) 5 FIRE EXTINGUISHERS SHALL BE INSTALLED PER IFC 2012 EDITION SECTION 906. 6 IVR-9200 FIRE FINAL BUILDING PERMIT INSPECTION REQUIRED
Pipeline Notfication Rcw 19.122.033 Resolved Standard Conditions
Engineering Division
Effective January 1, 2013 RCW 19.122 Before conducting any construction or excavation within 100 feet of a right-of-way or utility easement containing a transmission pipeline a person must notify the pipeline companies of the scheduled excavation through the one-number locator service 811. Notification must occur in a window of not less than 2 business days but not more than 10 business days before beginning the excavation. If a transmission pipeline company is notified that excavation work will occur near a pipeline, a representative of the company must consult with the excavator on-site prior to excavation.

Related Permit & Planning Applications

There are no related items for this permit application.

Documents & Images

No documents are currently available for viewing.


Should you need assistance, please contact the Permit Center at (253) 864-4165 option 1.