Summary

B-14-0547
Commercial - New Construction
Closed
GOOD SAMARITAN COMM HEALTHCARE
Other
TI ~ GSH/MULTICARE - 2ND FLOOR, UROLOGY SUITE
07/18/2014
09/15/2014
06/15/2015
12/17/2014

Locations

Reviews

Review Type Outcome Est. Completion Date Completed
Building Review VOID 12/09/2021
Building Review Approved 08/20/2014
Planning Review Approved 07/29/2014
Engineering Review Approved 07/21/2014

Fees

Paid Fees Amount Paid Owing Date Paid
WA State Building Code Council Fee (Residential) $4.50 $4.50 Paid 09/15/2014
No
Plumbing Plan Review Fee $203.45 $203.45 Paid 09/15/2014
No
Plumbing Permit Fee $313.00 $313.00 Paid 09/15/2014
No
Mechanical Plan Review Fee $41.60 $41.60 Paid 09/15/2014
No
Building Permit Fee $3,590.00 $3,590.00 Paid 09/15/2014
No
Mechanical Permit Fee $64.00 $64.00 Paid 09/15/2014
No
Fire Review Fee (Commercial Building) $265.00 $265.00 Paid 09/15/2014
No
Building Plan Review Fee $2,333.50 $2,333.50 Paid 09/15/2014
No
Sewer System Development Charge $12,113.60 $12,113.60 Paid 09/15/2014
No
Water System Development Charge $7,339.85 $7,339.85 Paid 09/15/2014
No
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


Permit(s) will not be issued until outstanding fees have been paid in full. Fee details shown above only include currently payable fees, there might be addtional fees to be paid before issuance.

$0.00

Inspections

Inspection Outcome Requested Scheduled Date Inspected
Plumbing Rough In Inspection Approved 10/8/2014 10/08/2014
Monty Johnson ((253) 770-3326)
Combination Frame And Rough In Inspection In Progress 10/10/2014 10/10/2014
Shannon King ((253) 840-6684)
Mechanical Rough In Inspection In Progress 10/10/2014 10/10/2014
Shannon King ((253) 840-6684)
Wallboard / Drywall Inspection Approved 10/21/2014 10/21/2014
Shannon King ((253) 840-6684)
Ceiling Grid/T-Bar Inspection Approved 11/26/2014
Monty Johnson ((253) 770-3326)
Plumbing Final Inspection Approved 12/9/2014 12/09/2014
Shannon King ((253) 840-6684)
Fire Final Inspection Approved 12/17/2014
Ray Cockerham ((253) 841-5585)
Mechanical Final Inspection Approved 12/17/2014
Ray Cockerham ((253) 841-5585)
Building Final Inspection Approved 12/17/2014 12/17/2014
Ray Cockerham ((253) 841-5585)
Frame Inspection VOID 12/09/2021
Monty Johnson ((253) 770-3326)
Comment Building Div Inspection VOID 12/09/2021
Ray Cockerham ((253) 841-5585)
Ceiling Grid/T-Bar Inspection VOID 11/26/2014 12/09/2021
Monty Johnson ((253) 770-3326)

Conditions

Condition Status Department Category Expiration Date Due Date
General Permit Conditions Resolved Building Division Standard Conditions
: * Final approval by the Building Official is required prior to occupancy. *Work shall not proceed until the inspector has approved the stages of construction. *Surface storm water shall be diverted from the building site and shall not drain onto adjacent properties. * I hereby acknowledge that I have read this Permit/Application, that the information given is correct: that I am the owner or the duly authorized agent of the owner; that plans submitted herewith are in compliance with all applicable city, county and state laws and that all construction will proceed in accordance with said laws. This permit shall expire if work is not commenced with 180 days or if the work is suspended for a period of 180 days. Once work has started (passed a required inspection) one inspection per year must be completed to keep active or it will formally expire and become null and void. * By leaving the contractor information section blank, I hereby certify further that contractors (general or subcontractors) will not be hired to perform any work in association with this permit. I also certify that if I do choose to hire a contractor (general or subcontractor) I will only hire those contractors that are licensed by the state of Washington.
Building Permit Standard Conditions Resolved Building Division Standard Conditions
: PERMIT CONDITIONS: FIRE REVIEW NOTES: 1 MOUNT 2A-10BC FIRE EXTINGUISHERS PER CODE 2 CHANGES IN FIRE ALARM OR SPRINKLER LAYOUT WILL REQUIRE SEPERATE PERMITS. 3 ALL AREAS SHALL BE COVERED BY FIRE SPRINKLER AND ALARM DEVICES. "TOTAL COVERAGE" PER NFPA 72 4 FIRE ALARM DEVICE MAPS AND UL CERTIFICATION SHALL BE UPDATED WITH THIS NEW TENANT SPACE. 5 CONSTRUCITON PER THE 2012 IBC AND IFC 6 IRV-9200 FIRE FINAL BUILDING PERMIT INSPECTION REQUIRED
Pipeline Notfication Rcw 19.122.033 Resolved Engineering Division Standard Conditions
: Effective January 1, 2013 RCW 19.122 Before conducting any construction or excavation within 100 feet of a right-of-way or utility easement containing a transmission pipeline a person must notify the pipeline companies of the scheduled excavation through the one-number locator service 811. Notification must occur in a window of not less than 2 business days but not more than 10 business days before beginning the excavation. If a transmission pipeline company is notified that excavation work will occur near a pipeline, a representative of the company must consult with the excavator on-site prior to excavation.

Related Permit & Planning Applications

There are no related items for this permit application.

Documents & Images

No documents are currently available for viewing.


Should you need assistance, please contact the Permit Center at (253) 864-4165 option 1.