CITY OF PUYALLUP PERMITTING PORTAL

Permit Application Status

B-15-0336


In order to request inspections, you need to be signed in.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

B-15-0336
Commercial - New Construction
Closed
IAC VABP LLC
Other
TI ~ CABELA'S BLDG ONLY
04/14/2015
07/21/2015
03/16/2016
10/16/2015

Locations

Reviews

Review Type Outcome Est. Completion Date Completed
Engineering Traffic Review VOID 12/09/2021
Building Review Approved 04/30/2015
Engineering Review Approved 04/16/2015

Fees

Paid Fees Amount Paid Owing Date Paid
WA State Building Code Council Fee (Residential) $4.50 $4.50 Paid 07/21/2015
No
Fire Review Fee (Commercial Building) $265.00 $265.00 Paid 07/21/2015
No
Building Permit Fee $2,393.75 $2,393.75 Paid 07/21/2015
No
Traffic Impact Fee $86,400.00 $86,400.00 Paid 07/21/2015
No
Building Plan Review Fee $1,555.94 $1,555.94 Paid 04/14/2015
No
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


Permit(s) will not be issued until outstanding fees have been paid in full. Fee details shown above only include currently payable fees, there might be addtional fees to be paid before issuance.

$0.00

Inspections

Inspection Outcome Requested Scheduled Date Inspected
Frame Inspection In Progress 8/20/2015 08/20/2015
rfore
Comment Building Div Inspection In Progress 8/24/2015 08/24/2015
rfore
Frame Inspection In Progress 8/26/2015 08/26/2015
rfore
Wallboard / Drywall Inspection Approved 8/27/2015 08/27/2015
rfore
Frame Inspection In Progress 9/1/2015 09/01/2015
rfore
Comment Building Div Inspection Approved 9/1/2015 09/01/2015
rfore
Gas Test Inspection Approved 09/10/2015
Shannon King ((253) 840-6684)
Frame Inspection In Progress 9/10/2015 09/10/2015
rfore
Ceiling Grid/T-Bar Inspection Approved 9/14/2015 09/14/2015
Shannon King ((253) 840-6684)
Frame Inspection In Progress 9/15/2015 09/15/2015
rfore
Frame Inspection Approved 9/18/2015 09/18/2015
rfore
Wallboard / Drywall Inspection In Progress 9/18/2015 09/18/2015
rfore
Wallboard / Drywall Inspection Approved 9/22/2015 09/22/2015
Shannon King ((253) 840-6684)
Fire Final Inspection In Progress 9/23/2015 09/22/2015
rfore
Fire Final Inspection Approved 9/23/2015 9/24/2015 09/24/2015
rfore
Building Final Inspection In Progress 9/25/2015 09/25/2015
Shannon King ((253) 840-6684)
Foundation/Rebar Inspection Approved 10/12/2015
Monty Johnson ((253) 770-3326)
Building Final Inspection Approved 10/16/2015 10/16/2015
Shannon King ((253) 840-6684)
Comment Building Div Inspection VOID 8/26/2015 12/09/2021
rfore
Ceiling Grid/T-Bar Inspection VOID 9/10/2015 12/09/2021
rfore
Ceiling Grid/T-Bar Inspection VOID 9/11/2015 12/09/2021
Shannon King ((253) 840-6684)
Building Final Inspection VOID 10/12/2015 12/09/2021
Monty Johnson ((253) 770-3326)

Conditions

Condition Status Category
General Permit Conditions Resolved Standard Conditions
Building Division
* Final approval by the Building Official is required prior to occupancy. *Work shall not proceed until the inspector has approved the stages of construction. *Surface storm water shall be diverted from the building site and shall not drain onto adjacent properties. * I hereby acknowledge that I have read this Permit/Application, that the information given is correct: that I am the owner or the duly authorized agent of the owner; that plans submitted herewith are in compliance with all applicable city, county and state laws and that all construction will proceed in accordance with said laws. This permit shall expire if work is not commenced with 180 days or if the work is suspended for a period of 180 days. Once work has started (passed a required inspection) one inspection per year must be completed to keep active or it will formally expire and become null and void. * By leaving the contractor information section blank, I hereby certify further that contractors (general or subcontractors) will not be hired to perform any work in association with this permit. I also certify that if I do choose to hire a contractor (general or subcontractor) I will only hire those contractors that are licensed by the state of Washington.
Building Permit Standard Conditions Resolved Standard Conditions
Building Division
PERMIT CONDITIONS: FIRE: 1 ANY MODIFICATION TO THE EXISTING FIRE SPRINKLER OR FIRE ALARM SYSTEMS SHALL REQUIRE SEPERATE PERMITS. 2 CITY OF PUYALLUP MUNICIPAL CODE REQUIRES "TOTAL COVERAGE" PER NFPA 72. 3 FIRE ALARM CONTRACTOR SHALL BE UL CERTIFIED. 4 COMPLY WITH IFC 2012 EDITION SECTION 510 EMERGENCY RESPONDER RADIO COVERAGE. QUESTIONS REGARDING ACCEPTANCE TESTING CAN BE DIRECTED TO, RAY COCKERHAM, THE BUILDING AND FIRE CODE OFFICIAL. (253-841-5585) 5 FIRE EXTINGUISHERS SHALL BE INSTALLED PER IFC 2012 EDITION SECTION 906. 6 A HMIS SHALL BE REQUIRED PRIOR TO STOCKING THE WAREHOUSE. 7 IVR-9200 FIRE FINAL BUILDING PERMIT INSPECTION REQUIRED.
Pipeline Notfication Rcw 19.122.033 Resolved Standard Conditions
Engineering Division
Effective January 1, 2013 RCW 19.122 Before conducting any construction or excavation within 100 feet of a right-of-way or utility easement containing a transmission pipeline a person must notify the pipeline companies of the scheduled excavation through the one-number locator service 811. Notification must occur in a window of not less than 2 business days but not more than 10 business days before beginning the excavation. If a transmission pipeline company is notified that excavation work will occur near a pipeline, a representative of the company must consult with the excavator on-site prior to excavation.

Related Permit & Planning Applications

There are no related items for this permit application.