CITY OF PUYALLUP PERMITTING PORTAL

Permit Application Status

B-16-0334


In order to request inspections, you need to be signed in.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

B-16-0334
Commercial - New Construction
Closed
PUYALLUP SCHOOL DIST NO 3
Other
INSTALL NEW 988SF OFFICE PORTABLE WITH RESTROOM~ PSD/MODULAR TRAINING ROOM
04/20/2016
06/02/2016
11/29/2016
07/19/2016

Locations

Reviews

Review Type Outcome Est. Completion Date Completed
Engineering Traffic Review VOID 12/09/2021
Building Review VOID 12/09/2021
Building Review Approved 05/18/2016
Engineering Review Approved 05/03/2016
Planning Review Approved 05/02/2016

Fees

Paid Fees Amount Paid Owing Date Paid
WA State Building Code Council Fee (Residential) $4.50 $4.50 Paid 06/01/2016
No
Sewer System Development Charge $2,119.88 $2,119.88 Paid 06/01/2016
No
Planning Building Permit Fee $30.00 $30.00 Paid 06/01/2016
No
Plumbing Plan Review Fee $51.35 $51.35 Paid 06/01/2016
No
Plumbing Permit Fee $79.00 $79.00 Paid 06/01/2016
No
Planning Landscape Review Fee $90.00 $90.00 Paid 06/01/2016
No
Mechanical Plan Review Fee $60.48 $60.48 Paid 06/01/2016
No
Fire Review Fee (Commercial Building) $265.00 $265.00 Paid 06/01/2016
No
Building Plan Review Fee $532.19 $532.19 Paid 06/01/2016
No
Storm System Development Charge $622.44 $622.44 Paid 06/01/2016
No
Building Permit Fee $818.75 $818.75 Paid 06/01/2016
No
Mechanical Permit Fee $93.05 $93.05 Paid 06/01/2016
No
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


Permit(s) will not be issued until outstanding fees have been paid in full. Fee details shown above only include currently payable fees, there might be addtional fees to be paid before issuance.

$0.00

Inspections

Inspection Outcome Requested Scheduled Date Inspected
Foundation/Rebar Inspection In Progress 6/14/2016 06/14/2016
rfore
Building Final Inspection Approved 7/12/2016 07/12/2016
rfore
Planning Final Inspection Approved 07/19/2016
Chris Beale ((253) 841-5418)
Comment Building Div Inspection VOID 6/17/2016 12/09/2021
Shannon King ((253) 840-6684)
Comment Building Div Inspection VOID 6/22/2016 12/09/2021
Shannon King ((253) 840-6684)
Plumbing Final Inspection VOID 6/24/2016 12/09/2021
rfore

Conditions

Condition Status Department Category Expiration Date Due Date
General Permit Conditions Resolved Building Division Standard Conditions
: * Final approval by the Building Official is required prior to occupancy. *Work shall not proceed until the inspector has approved the stages of construction. *Surface storm water shall be diverted from the building site and shall not drain onto adjacent properties. * I hereby acknowledge that I have read this Permit/Application, that the information given is correct: that I am the owner or the duly authorized agent of the owner; that plans submitted herewith are in compliance with all applicable city, county and state laws and that all construction will proceed in accordance with said laws. This permit shall expire if work is not commenced with 180 days or if the work is suspended for a period of 180 days. Once work has started (passed a required inspection) one inspection per year must be completed to keep active or it will formally expire and become null and void. Permits expire 2 years from issuance. **PUYALLUP SCHOOL DISTRICT HAS ACKNOWLEDGED THAT THIS FACILITY WILL ONLY BE USED FROM 9:30 AM TO 3:30 PM AND IS THEREFORE EXEMPT FROM PAYING TRAFFIC IMPACT FEES. * By leaving the contractor information section blank, I hereby certify further that contractors (general or subcontractors) will not be hired to perform any work in association with this permit. I also certify that if I do choose to hire a contractor (general or subcontractor) I will only hire those contractors that are licensed by the state of Washington.
Engineering Commercial Standard Conditions Resolved Engineering Division Standard Conditions
: * THE APPLICANT IS RESPONSIBLE TO CALL THE INSPECTION LINE AT 253-445-4795 OR 253-445-5092 TO SCHEDULE INSPECTIONS. UTILITY INSPECTIONS ARE REQUIRED PRIOR TO BACKFILLING. * The builder/owner shall be responsible for keeping the existing right-of-way free of debris and dirt. Any violation of PMC Chapter 21.14 pertaining to clearing, filling and grading, erosion and sediment control, and storm water discharges shall be prosecuted to the fullest extent of the law. * Any addition/expansion to the foot print of the building including decks and porches not originally shown on the approved set of plans must obtain proper permits prior to construction. * Sediment control and erosion procedures shall be practiced to eliminate and prevent off site damage. Storm water runoff originating upgrade of exposed areas shall be controlled to reduce erosion and sediment loss during the period of exposure. * The applicant is responsible to call the Utility Notification Center at 1-800-424-5555 before beginning any excavation. Call before you dig, it's the law. * No work shall be done in or on the public right of way without a licensed and bonded contractor first obtaining a right of way permit. * Any code requirement that may have been overlooked in this plan review does not imply that the requirements have been waived.
Building Permit Standard Conditions Resolved Building Division Standard Conditions
: PERMIT CONDITIONS: FIRE: 1. A SEPARATE ADDRESS SHALL BE MADE TO DISTINGUISH FROM THE MAIN BUILDINGS. 2. IF INSTALLED, A SEPARATE PERMIT SHALL BE REQUIRED FOR A NON-REQUIRED FIRE ALARM SYSTEM. 3. IVR-9200 FIRE FINAL BUILDING PERMIT INSPECTION REQUIRED.
Pipeline Notfication Rcw 19.122.033 Resolved Engineering Division Standard Conditions
: Effective January 1, 2013 RCW 19.122 Before conducting any construction or excavation within 100 feet of a right-of-way or utility easement containing a transmission pipeline a person must notify the pipeline companies of the scheduled excavation through the one-number locator service 811. Notification must occur in a window of not less than 2 business days but not more than 10 business days before beginning the excavation. If a transmission pipeline company is notified that excavation work will occur near a pipeline, a representative of the company must consult with the excavator on-site prior to excavation.

Related Permit & Planning Applications

There are no related items for this permit application.

Documents & Images

No documents are currently available for viewing.


Should you need assistance, please contact the Permit Center at (253) 864-4165 option 1.