Footing/Setback Inspection
|
Approved
|
|
8/25/2016
|
08/25/2016
|
|
Monty Johnson
((253) 770-3326)
|
Slab/Insulation Inspection
|
Approved
|
|
9/28/2016
|
09/28/2016
|
|
Shannon King
((253) 840-6684)
|
Shear Wall Inspection
|
Approved
|
|
1/6/2017
|
01/09/2017
|
|
Monty Johnson
((253) 770-3326)
|
Sidesewer Inspection
|
Approved
|
|
|
01/12/2017
|
|
Marcus Sedlickas
((253) 405-1707)
|
Water Inspection
|
Approved
|
|
1/17/2017
|
01/16/2017
|
|
Marcus Sedlickas
((253) 405-1707)
|
Plumbing Rough In Inspection
|
Approved
|
|
1/23/2017
|
01/24/2017
|
|
Shannon King
((253) 840-6684)
|
Frame Inspection
|
In Progress
|
|
1/31/2017
|
01/31/2017
|
|
Shannon King
((253) 840-6684)
|
Energy (Insulation) Inspection
|
Approved
|
|
2/9/2017
|
02/09/2017
|
|
Shannon King
((253) 840-6684)
|
Shower Pan Inspection
|
Approved
|
|
|
02/15/2017
|
|
Monty Johnson
((253) 770-3326)
|
Wallboard / Drywall Inspection
|
Approved
|
|
2/15/2017
|
02/15/2017
|
|
Monty Johnson
((253) 770-3326)
|
Comment Building Div Inspection
|
Approved
|
|
12/14/2017
|
12/15/2017
|
|
Gary Webster
((253) 841-5590)
|
Engineering Final Inspection
|
Approved
|
|
|
02/06/2018
|
|
Michael Rosenau
((253) 344-6753)
|
Carbon Monoxide Detectors Inspection
|
Approved
|
|
|
02/14/2018
|
|
Gary Webster
((253) 841-5590)
|
Building Final Inspection
|
Approved
|
|
2/14/2018
|
02/14/2018
|
|
Gary Webster
((253) 841-5590)
|
Foundation/Rebar Inspection
|
VOID
|
|
9/6/2016
|
12/09/2021
|
|
Shannon King
((253) 840-6684)
|
Foundation/Rebar Inspection
|
VOID
|
|
9/8/2016
|
12/09/2021
|
|
Julie Johnson
((253) 841-5482)
|
Foundation/Rebar Inspection
|
VOID
|
|
9/9/2016
|
12/09/2021
|
|
Shannon King
((253) 840-6684)
|
Foundation/Rebar Inspection
|
VOID
|
|
9/12/2016
|
12/09/2021
|
|
Shannon King
((253) 840-6684)
|
Underfloor Inspection
|
VOID
|
|
10/12/2016
|
12/09/2021
|
|
Shannon King
((253) 840-6684)
|
Shear Wall Inspection
|
VOID
|
|
1/5/2017
|
12/09/2021
|
|
Monty Johnson
((253) 770-3326)
|
Mechanical Rough In Inspection
|
VOID
|
|
1/23/2017
|
12/09/2021
|
|
Shannon King
((253) 840-6684)
|
Frame Inspection
|
VOID
|
|
1/23/2017
|
12/09/2021
|
|
Shannon King
((253) 840-6684)
|
Combination Frame And Rough In Inspection
|
VOID
|
|
1/30/2017
|
12/09/2021
|
|
Shannon King
((253) 840-6684)
|
Underfloor Inspection
|
VOID
|
|
1/31/2017
|
12/09/2021
|
|
Shannon King
((253) 840-6684)
|
Energy (Insulation) Inspection
|
VOID
|
|
2/3/2017
|
12/09/2021
|
|
Eric Tague
((253) 864-4192)
|
Energy (Insulation) Inspection
|
VOID
|
|
2/6/2017
|
12/09/2021
|
|
Shannon King
((253) 840-6684)
|
Energy (Insulation) Inspection
|
VOID
|
|
2/8/2017
|
12/09/2021
|
|
Shannon King
((253) 840-6684)
|
Combination Frame And Rough In Inspection
|
VOID
|
|
10/30/2017
|
12/09/2021
|
|
Monty Johnson
((253) 770-3326)
|
Comment Building Div Inspection
|
VOID
|
|
11/29/2017
|
12/09/2021
|
|
Shannon King
((253) 840-6684)
|
Comment Building Div Inspection
|
VOID
|
|
12/1/2017
|
12/09/2021
|
|
Gary Webster
((253) 841-5590)
|
Comment Building Div Inspection
|
VOID
|
|
12/7/2017
|
12/09/2021
|
|
Gary Webster
((253) 841-5590)
|
Building Final Inspection
|
VOID
|
|
1/12/2018
|
12/09/2021
|
|
Gary Webster
((253) 841-5590)
|
Engineering Final Inspection
|
VOID
|
|
1/12/2018
|
12/09/2021
|
|
Michael Rosenau
((253) 344-6753)
|
Engineering Final Inspection
|
VOID
|
|
2/5/2018
|
12/09/2021
|
|
Michael Rosenau
((253) 344-6753)
|
Building Final Inspection
|
VOID
|
|
2/7/2018
|
12/09/2021
|
|
Gary Webster
((253) 841-5590)
|
Building Final Inspection
|
VOID
|
|
2/9/2018
|
12/09/2021
|
|
Shannon King
((253) 840-6684)
|