Summary

B-16-0559
Commercial - New Construction
Closed
CAFARO NORTHWEST PARTNERSHIP
Other
TI ~ VICTORIA SECRET #300 BUILD/MECH/PLUMB
06/27/2016
08/18/2016
05/09/2017
11/10/2016

Locations

Property
6021010051

Property
6021590070

Property
6021590090

* Address
3500 S MERIDIAN

Reviews

Review Type Outcome Est. Completion Date Completed
Building Review VOID 12/09/2021
Building Review Approved 08/11/2016
Engineering Review Approved 07/26/2016
Planning Review Approved 07/14/2016
Engineering Traffic Review Approved 06/27/2016

Fees

Paid Fees Amount Paid Owing Date Paid
Planning Landscape Review Fee $90.00 $90.00 Paid 08/18/2016
No
Mechanical Plan Review Fee $74.13 $74.13 Paid 08/18/2016
No
WA State Building Code Council Fee (Residential) $4.50 $4.50 Paid 08/18/2016
No
Planning Building Permit Fee $30.00 $30.00 Paid 08/18/2016
No
Mechanical Permit Fee $114.05 $114.05 Paid 08/18/2016
No
Plumbing Permit Fee $131.00 $131.00 Paid 08/18/2016
No
Building Division Fee (Hourly) $260.00 $260.00 Paid 08/18/2016
No
Building Permit Fee $3,542.50 $3,542.50 Paid 08/18/2016
No
Fire Review Fee (Commercial Building) $265.00 $265.00 Paid 08/18/2016
No
Plumbing Plan Review Fee $85.15 $85.15 Paid 08/18/2016
No
Sewer System Development Charge $653.92 $653.92 Paid 08/18/2016
No
Building Plan Review Fee $2,302.63 $2,302.63 Paid 06/27/2016
No
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


Permit(s) will not be issued until outstanding fees have been paid in full. Fee details shown above only include currently payable fees, there might be addtional fees to be paid before issuance.

$0.00

Inspections

Inspection Outcome Requested Scheduled Date Inspected
Plumbing Below Slab Inspection Approved 9/2/2016 09/02/2016
Shannon King ((253) 840-6684)
Mechanical Rough In Inspection In Progress 9/9/2016 09/09/2016
Shannon King ((253) 840-6684)
Plumbing Rough In Inspection In Progress 9/12/2016 09/12/2016
Shannon King ((253) 840-6684)
Frame Inspection In Progress 9/13/2016 09/13/2016
Shannon King ((253) 840-6684)
Plumbing Rough In Inspection Approved 9/13/2016 09/13/2016
Shannon King ((253) 840-6684)
Mechanical Rough In Inspection Approved 9/16/2016 09/16/2016
Monty Johnson ((253) 770-3326)
Wallboard / Drywall Inspection In Progress 9/21/2016 09/21/2016
Shannon King ((253) 840-6684)
Ceiling Grid/T-Bar Inspection In Progress 9/22/2016 09/22/2016
Monty Johnson ((253) 770-3326)
Wallboard / Drywall Inspection In Progress 9/26/2016 09/26/2016
Shannon King ((253) 840-6684)
Frame Inspection In Progress 9/28/2016 09/28/2016
Monty Johnson ((253) 770-3326)
Wallboard / Drywall Inspection In Progress 10/3/2016 10/03/2016
rfore
Wallboard / Drywall Inspection Approved 10/5/2016 10/06/2016
Monty Johnson ((253) 770-3326)
Ceiling Grid/T-Bar Inspection Approved 10/28/2016 10/28/2016
Monty Johnson ((253) 770-3326)
Fire Final Inspection In Progress 11/3/2016 11/03/2016
rfore
Mechanical Final Inspection Approved 11/10/2016 11/10/2016
rfore
Exit Lighting Test Inspection Approved 11/10/2016 11/10/2016
rfore
Plumbing Final Inspection Approved 11/10/2016 11/10/2016
rfore
Building Final Inspection Approved 11/10/2016 11/10/2016
rfore
Fire Final Inspection Approved 11/10/2016 11/10/2016
rfore
Plumbing Below Slab Inspection VOID 12/09/2021
Shannon King ((253) 840-6684)
Frame Inspection VOID 8/30/2016 12/09/2021
Shannon King ((253) 840-6684)
Plumbing Rough In Inspection VOID 8/31/2016 12/09/2021
Shannon King ((253) 840-6684)
Plumbing Rough In Inspection VOID 9/1/2016 12/09/2021
Shannon King ((253) 840-6684)
Mechanical Rough In Inspection VOID 9/1/2016 12/09/2021
Shannon King ((253) 840-6684)
Frame Inspection VOID 9/12/2016 12/09/2021
Shannon King ((253) 840-6684)
Ceiling Grid/T-Bar Inspection VOID 9/16/2016 12/09/2021
Monty Johnson ((253) 770-3326)
Frame Inspection VOID 9/16/2016 12/09/2021
Monty Johnson ((253) 770-3326)
Wallboard / Drywall Inspection VOID 9/20/2016 12/09/2021
Shannon King ((253) 840-6684)
Ceiling Grid/T-Bar Inspection VOID 9/20/2016 12/09/2021
Shannon King ((253) 840-6684)
Plumbing Rough In Inspection VOID 9/20/2016 12/09/2021
Shannon King ((253) 840-6684)
Ceiling Grid/T-Bar Inspection VOID 9/21/2016 12/09/2021
Shannon King ((253) 840-6684)
Frame Inspection VOID 9/26/2016 12/09/2021
Shannon King ((253) 840-6684)
Ceiling Grid/T-Bar Inspection VOID 10/19/2016 12/09/2021
Shannon King ((253) 840-6684)
Ceiling Grid/T-Bar Inspection VOID 10/24/2016 12/09/2021
Shannon King ((253) 840-6684)
Mechanical Final Inspection VOID 11/3/2016 12/09/2021
Shannon King ((253) 840-6684)
Plumbing Final Inspection VOID 11/3/2016 12/09/2021
Shannon King ((253) 840-6684)
Fire Final Inspection VOID 11/9/2016 12/09/2021
rfore
Building Final Inspection VOID 11/9/2016 12/09/2021
Shannon King ((253) 840-6684)
Mechanical Final Inspection VOID 11/9/2016 12/09/2021
Shannon King ((253) 840-6684)

Conditions

Condition Status Department Category Expiration Date Due Date
General Permit Conditions Resolved Building Division Standard Conditions
: * Final approval by the Building Official is required prior to occupancy. *Work shall not proceed until the inspector has approved the stages of construction. *Surface storm water shall be diverted from the building site and shall not drain onto adjacent properties. * I hereby acknowledge that I have read this Permit/Application, that the information given is correct: that I am the owner or the duly authorized agent of the owner; that plans submitted herewith are in compliance with all applicable city, county and state laws and that all construction will proceed in accordance with said laws. This permit shall expire if work is not commenced with 180 days or if the work is suspended for a period of 180 days. Once work has started (passed a required inspection) one inspection per year must be completed to keep active or it will formally expire and become null and void. Permits expire 2 years from issuance. * By leaving the contractor information section blank, I hereby certify further that contractors (general or subcontractors) will not be hired to perform any work in association with this permit. I also certify that if I do choose to hire a contractor (general or subcontractor) I will only hire those contractors that are licensed by the state of Washington.
Engineering Commercial Standard Conditions Resolved Engineering Division Standard Conditions
: *** Three wheelchair ramps, as documented on the exhibit drawing provided to the applicant, shall be upgraded to current ADA standadrds prior to final approval/occupancy. *** Frontage improvement requirement waived by City Engineer - See AMR E-16-0578 * Any addition/expansion to the foot print of the building including decks and porches not originally shown on the approved set of plans must obtain proper permits prior to construction. * Any code requirement that may have been overlooked in this plan review does not imply that the requirements have been waived.
Building Permit Standard Conditions Resolved Building Division Standard Conditions
: PERMIT CONDITIONS: FIRE: 1. ANY MODIFICATION TO THE FIRE ALARM OR SPRINKLER SYSTEMS SHALL REQUIRE A SEPERATE PERMIT 2. CITY OF PUYALLUP MUNICIPAL CODE REQUIRES "TOTAL COVERAGE" PER NFPA 72, 2010 EDITION 3. IVR-2252 EMERGENCY EGRESS LIGHTING TEST REQUIRED. 4. IVR-9200 FIRE FINAL BUILDING PERMIT INSPECTION REQUIRED
Pipeline Notfication Rcw 19.122.033 Resolved Engineering Division Standard Conditions
: Effective January 1, 2013 RCW 19.122 Before conducting any construction or excavation within 100 feet of a right-of-way or utility easement containing a transmission pipeline a person must notify the pipeline companies of the scheduled excavation through the one-number locator service 811. Notification must occur in a window of not less than 2 business days but not more than 10 business days before beginning the excavation. If a transmission pipeline company is notified that excavation work will occur near a pipeline, a representative of the company must consult with the excavator on-site prior to excavation.

Related Permit & Planning Applications

There are no related items for this permit application.

Documents & Images

No documents are currently available for viewing.


Should you need assistance, please contact the Permit Center at (253) 864-4165 option 1.