Inspection |
Outcome |
Requested |
Scheduled |
Date Inspected |
Footing/Setback Inspection
|
In Progress
|
|
6/11/2019
|
06/11/2019
|
|
Gary Webster
((253) 841-5590)
|
Foundation/Rebar Inspection
|
In Progress
|
|
6/17/2019
|
06/17/2019
|
|
Shannon King
((253) 840-6684)
|
Plumbing Rough In Inspection
|
In Progress
|
|
7/3/2019
|
07/03/2019
|
|
Gary Webster
((253) 841-5590)
|
Comment Building Div Inspection
|
Approved
|
|
7/9/2019
|
07/09/2019
|
|
Gary Webster
((253) 841-5590)
|
Shear Wall Inspection
|
Approved
|
|
7/25/2019
|
07/25/2019
|
|
Gary Webster
((253) 841-5590)
|
Frame Inspection
|
In Progress
|
|
8/1/2019
|
08/01/2019
|
|
Gary Webster
((253) 841-5590)
|
Foundation/Rebar Inspection
|
In Progress
|
|
8/14/2019
|
08/14/2019
|
|
Gary Webster
((253) 841-5590)
|
Plumbing Rough In Inspection
|
In Progress
|
|
8/15/2019
|
08/15/2019
|
|
Gary Webster
((253) 841-5590)
|
Foundation/Rebar Inspection
|
In Progress
|
|
|
08/21/2019
|
|
Gary Webster
((253) 841-5590)
|
Energy (Insulation) Inspection
|
Approved
|
|
8/21/2019
|
08/21/2019
|
|
Gary Webster
((253) 841-5590)
|
Wallboard / Drywall Inspection
|
In Progress
|
|
8/26/2019
|
08/26/2019
|
|
Gary Webster
((253) 841-5590)
|
Block Wall Rebar Inspection
|
In Progress
|
|
8/26/2019
|
08/26/2019
|
|
Gary Webster
((253) 841-5590)
|
Frame Inspection
|
In Progress
|
|
8/27/2019
|
08/27/2019
|
|
Gary Webster
((253) 841-5590)
|
Mechanical Rough In Inspection
|
In Progress
|
|
9/4/2019
|
09/04/2019
|
|
Shannon King
((253) 840-6684)
|
Mechanical Rough In Inspection
|
Approved
|
|
9/23/2019
|
09/23/2019
|
|
Shannon King
((253) 840-6684)
|
Ceiling Grid/T-Bar Inspection
|
Approved
|
|
10/10/2019
|
10/10/2019
|
|
Monty Johnson
((253) 770-3326)
|
Fire Final Inspection
|
Approved
|
|
10/23/2019
|
10/22/2019
|
|
David Drake
((253) 864-4171)
|
Planning Final Inspection
|
Approved
|
|
|
10/24/2019
|
|
Ken Davies
((253) 841-5507)
|
Building Final Inspection
|
Approved
|
|
|
10/25/2019
|
|
Gary Webster
((253) 841-5590)
|
Engineering Final Inspection
|
Approved
|
|
|
10/25/2019
|
|
Gary Webster
((253) 841-5590)
|
Comment Building Div Inspection
|
Approved
|
|
10/25/2019
|
10/25/2019
|
|
Gary Webster
((253) 841-5590)
|
Frame Inspection
|
VOID
|
|
8/19/2019
|
12/09/2021
|
|
Gary Webster
((253) 841-5590)
|
Ceiling Grid/T-Bar Inspection
|
VOID
|
|
9/23/2019
|
12/09/2021
|
|
Shannon King
((253) 840-6684)
|
Plumbing Final Inspection
|
VOID
|
|
10/18/2019
|
12/09/2021
|
|
Shannon King
((253) 840-6684)
|
Mechanical Final Inspection
|
VOID
|
|
10/18/2019
|
12/09/2021
|
|
Shannon King
((253) 840-6684)
|
Fire Final Inspection
|
VOID
|
|
10/21/2019
|
12/09/2021
|
|
counter1
|
Building Final Inspection
|
VOID
|
|
10/24/2019
|
12/09/2021
|
|
Shannon King
((253) 840-6684)
|