CITY OF PUYALLUP PERMITTING PORTAL

Permit Application Status

B-18-1096


In order to request inspections, you need to be signed in.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

B-18-1096
Commercial - New Construction
Closed
PUYALLUP MEMORY CARE, LLC
Other
DEER RIDGE MEMORY CARE FACILITY BLDG/MECH/PLUMB
12/10/2018
11/21/2019
10/18/2021
04/21/2021

Locations

Reviews

Review Type Outcome Est. Completion Date Completed
Building Review VOID 12/09/2021
Building Review VOID 12/09/2021
Planning Review Approved 11/20/2019
Engineering Review Approved 11/08/2019
Building Review Approved 10/17/2019
Fire Review Approved 01/16/2019

Fees

Paid Fees Amount Paid Owing Date Paid
Legacy Fee $260.00 $260.00 Paid 02/24/2021
No
Fire Watch Inspection Fee $650.00 $650.00 Paid 02/24/2021
No
WA State Building Code Council Fee (Residential) $127.00 $127.00 Paid 11/21/2019
No
Fire Review Fee (Commercial Building) $265.00 $265.00 Paid 11/21/2019
No
Plumbing Plan Review Fee $1,751.43 $1,751.43 Paid 11/21/2019
No
Mechanical Plan Review Fee $1,464.32 $1,464.32 Paid 11/21/2019
No
Mechanical Permit Fee $2,252.80 $2,252.80 Paid 11/21/2019
No
Building Permit Fee $22,362.25 $22,362.25 Paid 11/21/2019
No
Sewer System Development Charge $41,115.24 $41,115.24 Paid 11/21/2019
No
Sewer System Development Charge $64,596.00 $64,596.00 Paid 11/21/2019
No
Building Division Fee (Hourly) $130.00 $130.00 Paid 11/21/2019
No
Plumbing Permit Fee $2,694.50 $2,694.50 Paid 11/21/2019
No
Building Plan Review Fee $14,535.46 $14,535.46 Paid 12/11/2018
No
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


Permit(s) will not be issued until outstanding fees have been paid in full. Fee details shown above only include currently payable fees, there might be addtional fees to be paid before issuance.

$0.00

Inspections

Inspection Outcome Requested Scheduled Date Inspected
Foundation/Rebar Inspection In Progress 2/14/2020 02/14/2020
Gary Webster ((253) 841-5590)
Foundation/Rebar Inspection In Progress 2/25/2020 02/25/2020
Monty Johnson ((253) 770-3326)
Foundation/Rebar Inspection In Progress 3/2/2020 03/02/2020
Gary Webster ((253) 841-5590)
Foundation/Rebar Inspection In Progress 3/5/2020 03/05/2020
Gary Webster ((253) 841-5590)
Foundation/Rebar Inspection In Progress 3/13/2020 03/13/2020
Monty Johnson ((253) 770-3326)
Foundation/Rebar Inspection In Progress 3/19/2020 03/19/2020
Gary Webster ((253) 841-5590)
Foundation/Rebar Inspection In Progress 3/25/2020 03/25/2020
Gary Webster ((253) 841-5590)
Plumbing Below Slab Inspection In Progress 04/09/2020
Gary Webster ((253) 841-5590)
Plumbing Below Slab Inspection In Progress 04/23/2020
Gary Webster ((253) 841-5590)
Plumbing Below Slab Inspection In Progress 4/27/2020 04/27/2020
Gary Webster ((253) 841-5590)
Plumbing Below Slab Inspection In Progress 4/28/2020 04/28/2020
Gary Webster ((253) 841-5590)
Plumbing Rough In Inspection In Progress 4/30/2020 04/30/2020
Gary Webster ((253) 841-5590)
Foundation/Rebar Inspection In Progress 5/6/2020 05/06/2020
Shannon King ((253) 840-6684)
Foundation/Rebar Inspection In Progress 5/11/2020 05/11/2020
Gary Webster ((253) 841-5590)
Foundation/Rebar Inspection In Progress 5/28/2020 05/28/2020
Gary Webster ((253) 841-5590)
Shear Wall Inspection In Progress 6/1/2020 06/01/2020
Gary Webster ((253) 841-5590)
Foundation/Rebar Inspection In Progress 6/3/2020 06/03/2020
Gary Webster ((253) 841-5590)
Frame Inspection In Progress 6/9/2020 06/09/2020
Gary Webster ((253) 841-5590)
Footing/Setback Inspection In Progress 6/23/2020 06/23/2020
Gary Webster ((253) 841-5590)
Foundation/Rebar Inspection In Progress 6/26/2020 06/26/2020
Gary Webster ((253) 841-5590)
Plumbing Below Slab Inspection Approved 7/8/2020 07/08/2020
Gary Webster ((253) 841-5590)
Foundation/Rebar Inspection In Progress 7/14/2020 07/14/2020
Gary Webster ((253) 841-5590)
Shear Wall Inspection Approved 7/28/2020 07/28/2020
Gary Webster ((253) 841-5590)
Frame Inspection In Progress 8/24/2020 08/24/2020
Gary Webster ((253) 841-5590)
Foundation/Rebar Inspection In Progress 9/2/2020 09/02/2020
Gary Webster ((253) 841-5590)
Wallboard / Drywall Inspection In Progress 9/24/2020 09/22/2020
Gary Webster ((253) 841-5590)
Wallboard / Drywall Inspection In Progress 09/23/2020
Gary Webster ((253) 841-5590)
Wallboard / Drywall Inspection In Progress 9/25/2020 09/25/2020
Gary Webster ((253) 841-5590)
Wallboard / Drywall Inspection In Progress 9/29/2020 09/29/2020
Gary Webster ((253) 841-5590)
Wallboard / Drywall Inspection In Progress 10/1/2020 10/01/2020
Shannon King ((253) 840-6684)
Wallboard / Drywall Inspection In Progress 10/2/2020 10/02/2020
Gary Webster ((253) 841-5590)
Wallboard / Drywall Inspection In Progress 10/5/2020 10/05/2020
Gary Webster ((253) 841-5590)
Wallboard / Drywall Inspection In Progress 10/08/2020
Monty Johnson ((253) 770-3326)
Mechanical Rough In Inspection In Progress 10/9/2020 10/09/2020
Shannon King ((253) 840-6684)
Plumbing Rough In Inspection In Progress 10/22/2020 10/22/2020
Gary Webster ((253) 841-5590)
Plumbing Rough In Inspection In Progress 10/27/2020 10/27/2020
Gary Webster ((253) 841-5590)
Mechanical Rough In Inspection In Progress 10/27/2020 10/27/2020
Gary Webster ((253) 841-5590)
Plumbing Rough In Inspection In Progress 10/28/2020 10/28/2020
Gary Webster ((253) 841-5590)
Frame Inspection In Progress 10/29/2020 10/29/2020
Gary Webster ((253) 841-5590)
Plumbing Rough In Inspection Approved 10/29/2020 10/29/2020
Gary Webster ((253) 841-5590)
Frame Inspection In Progress 10/30/2020 10/30/2020
Gary Webster ((253) 841-5590)
Frame Inspection In Progress 11/3/2020 11/03/2020
Gary Webster ((253) 841-5590)
Combination Frame And Rough In Inspection In Progress 11/5/2020 11/05/2020
Gary Webster ((253) 841-5590)
Wallboard / Drywall Inspection In Progress 11/5/2020 11/05/2020
Gary Webster ((253) 841-5590)
Frame Inspection In Progress 11/12/2020 11/12/2020
Gary Webster ((253) 841-5590)
Energy (Insulation) Inspection In Progress 11/12/2020 11/12/2020
Gary Webster ((253) 841-5590)
Mechanical Rough In Inspection In Progress 11/12/2020 11/12/2020
Gary Webster ((253) 841-5590)
Mechanical Rough In Inspection In Progress 11/13/2020 11/13/2020
Gary Webster ((253) 841-5590)
Wallboard / Drywall Inspection In Progress 11/13/2020 11/13/2020
Gary Webster ((253) 841-5590)
Wallboard / Drywall Inspection In Progress 11/16/2020 11/16/2020
Gary Webster ((253) 841-5590)
Mechanical Rough In Inspection In Progress 11/17/2020 11/17/2020
Gary Webster ((253) 841-5590)
Wallboard / Drywall Inspection In Progress 11/18/2020 11/18/2020
Gary Webster ((253) 841-5590)
Wallboard / Drywall Inspection In Progress 11/19/2020 11/19/2020
Gary Webster ((253) 841-5590)
Frame Inspection In Progress 11/24/2020 11/24/2020
Gary Webster ((253) 841-5590)
Wallboard / Drywall Inspection Approved 11/25/2020 11/25/2020
Gary Webster ((253) 841-5590)
Energy (Insulation) Inspection In Progress 11/30/2020 11/30/2020
Gary Webster ((253) 841-5590)
Frame Inspection In Progress 12/4/2020 12/04/2020
Gary Webster ((253) 841-5590)
Wallboard / Drywall Inspection In Progress 12/4/2020 12/04/2020
Gary Webster ((253) 841-5590)
Frame Inspection In Progress 12/7/2020 12/07/2020
Gary Webster ((253) 841-5590)
Wallboard / Drywall Inspection In Progress 12/9/2020 12/09/2020
Gary Webster ((253) 841-5590)
Frame Inspection In Progress 12/14/2020 12/14/2020
Gary Webster ((253) 841-5590)
Energy (Insulation) Inspection Approved 12/16/2020 12/16/2020
Monty Johnson ((253) 770-3326)
Ceiling Grid/T-Bar Inspection In Progress 12/16/2020 12/16/2020
Monty Johnson ((253) 770-3326)
Wallboard / Drywall Inspection In Progress 12/17/2020 12/17/2020
Gary Webster ((253) 841-5590)
Wallboard / Drywall Inspection In Progress 12/18/2020 12/18/2020
Gary Webster ((253) 841-5590)
Wallboard / Drywall Inspection In Progress 12/21/2020 12/21/2020
Gary Webster ((253) 841-5590)
Frame Inspection In Progress 12/22/2020 12/22/2020
Gary Webster ((253) 841-5590)
Wallboard / Drywall Inspection In Progress 12/22/2020 12/22/2020
Gary Webster ((253) 841-5590)
Wallboard / Drywall Inspection In Progress 12/24/2020 12/24/2020
Shannon King ((253) 840-6684)
Wallboard / Drywall Inspection Approved 12/31/2020 12/31/2020
Gary Webster ((253) 841-5590)
Mechanical Rough In Inspection In Progress 1/7/2021 01/07/2021
Gary Webster ((253) 841-5590)
Ceiling Grid/T-Bar Inspection In Progress 02/05/2021
Gary Webster ((253) 841-5590)
Ceiling Grid/T-Bar Inspection Approved 2/18/2021 02/18/2021
Gary Webster ((253) 841-5590)
Fire Final Inspection Approved 4/7/2021 04/08/2021
David Drake ((253) 864-4171)
Emergency Radio Test Review Inspection Approved 4/7/2021 04/08/2021
David Drake ((253) 864-4171)
Exit Lighting Test Inspection Approved 4/13/2021 04/13/2021
David Drake ((253) 864-4171)
Planning Final Inspection Approved 4/13/2021 04/14/2021
Chris Beale ((253) 841-5418)
Engineering Final Inspection Approved 04/21/2021
Kenneth Cook ((253) 864-4177)
Mechanical Final Inspection Approved 4/21/2021 04/21/2021
Gary Webster ((253) 841-5590)
Plumbing Final Inspection Approved 4/21/2021 04/21/2021
Gary Webster ((253) 841-5590)
Building Final Inspection Approved 4/21/2021 04/21/2021
Gary Webster ((253) 841-5590)
Comment Building Div Inspection VOID 12/09/2021
Gary Webster ((253) 841-5590)
Plumbing Rough In Inspection VOID 4/9/2020 12/09/2021
Gary Webster ((253) 841-5590)
Plumbing Below Slab Inspection VOID 4/15/2020 12/09/2021
Shannon King ((253) 840-6684)
Plumbing Rough In Inspection VOID 4/23/2020 12/09/2021
Gary Webster ((253) 841-5590)
Foundation/Rebar Inspection VOID 5/8/2020 12/09/2021
Monty Johnson ((253) 770-3326)
Shear Wall Inspection VOID 6/19/2020 12/09/2021
Gary Webster ((253) 841-5590)
Combination Frame And Rough In Inspection VOID 9/9/2020 12/09/2021
Gary Webster ((253) 841-5590)
Energy (Insulation) Inspection VOID 9/22/2020 12/09/2021
Gary Webster ((253) 841-5590)
Frame Inspection VOID 9/23/2020 12/09/2021
Gary Webster ((253) 841-5590)
Wallboard / Drywall Inspection VOID 10/9/2020 12/09/2021
Shannon King ((253) 840-6684)
Energy (Insulation) Inspection VOID 11/10/2020 12/09/2021
Gary Webster ((253) 841-5590)
Frame Inspection VOID 11/18/2020 12/09/2021
Gary Webster ((253) 841-5590)
Energy (Insulation) Inspection VOID 12/15/2020 12/09/2021
Monty Johnson ((253) 770-3326)
Comment Building Div Inspection VOID 12/15/2020 12/09/2021
Monty Johnson ((253) 770-3326)
Wallboard / Drywall Inspection VOID 12/23/2020 12/09/2021
Gary Webster ((253) 841-5590)
Comment Building Div Inspection VOID 1/7/2021 12/09/2021
Gary Webster ((253) 841-5590)
Comment Building Div Inspection VOID 2/1/2021 12/09/2021
Gary Webster ((253) 841-5590)
Comment Building Div Inspection VOID 2/5/2021 12/09/2021
Gary Webster ((253) 841-5590)
Comment Building Div Inspection VOID 2/24/2021 12/09/2021
Gary Webster ((253) 841-5590)
Mechanical Final Inspection VOID 3/11/2021 12/09/2021
Gary Webster ((253) 841-5590)
Mechanical Final Inspection VOID 3/12/2021 12/09/2021
Gary Webster ((253) 841-5590)
Plumbing Final Inspection VOID 3/12/2021 12/09/2021
Gary Webster ((253) 841-5590)
Building Final Inspection VOID 3/18/2021 12/09/2021
Gary Webster ((253) 841-5590)
Building Final Inspection VOID 3/19/2021 12/09/2021
Gary Webster ((253) 841-5590)
Building Final Inspection VOID 3/31/2021 12/09/2021
Gary Webster ((253) 841-5590)
Exit Lighting Test Inspection VOID 4/7/2021 12/09/2021
David Drake ((253) 864-4171)
Plumbing Final Inspection VOID 4/13/2021 12/09/2021
Gary Webster ((253) 841-5590)
Mechanical Final Inspection VOID 4/13/2021 12/09/2021
Gary Webster ((253) 841-5590)
Building Final Inspection VOID 4/13/2021 12/09/2021
Gary Webster ((253) 841-5590)

Conditions

Condition Status Department Category Expiration Date Due Date
General Permit Conditions Resolved Building Division Standard Conditions
: * Final approval by the Building Official is required prior to use or occupancy. * Work shall not proceed until the inspector has approved the stages of construction. * Surface storm water shall be diverted from the building site and shall not drain onto adjacent properties. * I hereby acknowledge that I have read this Permit/Application, that the information given is correct; that I am the owner or the duly authorized agent of the owner; that plans submitted herewith are in compliance with all applicable city, county and state laws and that all construction will proceed in accordance with said laws. This permit shall expire if work is not commenced with 180 days or if the work is suspended for a period of 180 days. Permits expire two years from issuance. * By leaving the contractor information section blank, I hereby certify further that contractors (general or subcontractors) will not be hired to perform any work in association with this permit. I also certify that if I do choose to hire a contractor (general or subcontractor) I will only hire those contractors that are licensed by the State of Washington. * TO SCHEDULE INSPECTIONS, CHECK PERMIT STATUS OR TO MAKE PAYMENTS ON THE CITY WEB SITE VISIT https://secure.cityofpuyallup.org/ PLANNING FINAL CONDITIONS: APPROVAL MUST BE CONSISTENT WITH DESIGN REVIEW BOARD APPROVALS, INCLUDING: 1. The applicant shall use decorative/ornate stamped concrete at all pedestrian crossings and entries. 2. Per PMC 20.52.025 (6), Building Materials; the applicant shall omit completely the use of hardie board siding materials on the building elevations facing the public way (north and west elevations). The applicant may use approved materials including; metal paneling, brick, decorative faux stone, masonry, and masonry veneer in place of hardie board on these elevations. The applicant is encouraged to minimize the use of hardie board on other areas of the building.
Engineering Commercial Standard Conditions Resolved Engineering Division Standard Conditions
: ** PRIOR TO OCCUPANCY ALL ASSOCIATED CIVIL WORK MUST BE COMPLETED AND RECIEVED A FINAL INSPECTION ** * THE APPLICANT IS RESPONSIBLE TO CALL THE INSPECTION LINE AT 877-232-6456 TO SCHEDULE INSPECTIONS. UTILITY INSPECTIONS ARE REQUIRED PRIOR TO BACKFILLING. ** STORMWATER CONTROL OF ROOF DOWNSPOUTS MUST BE CONTROLLED. ATTACHED TO THE SITE PLAN IS A TYPICAL INFILTRATION SYSTEM YOU MAY CHOOSE TO FOLLOW. FOR ANY QUESTIONS CALL MARCUS SEDLICKAS, ENGINEERING INSPECTOR, AT 253-405-1707 ** SEDIMENT CONTROL AND EROSION PROCEDURES SHALL BE PRACTICE TO ELIMINATE AND PREVENT OFF SITE DAMAGE. STORMWATER RUNOFF ORIGINATING UPGRADE OF EXPOSED AREAS SHALL BE CONTROLLED TO REDUCE EROSION AND SEDIMENT LOSS DURING THE PERIOD OF EXPOSURE. * The builder/owner shall be responsible for keeping the existing right-of-way free of debris and dirt. Any violation of PMC Chapter 21.14 pertaining to clearing, filling and grading, erosion and sediment control, and storm water discharges shall be prosecuted to the fullest extent of the law. * Any addition/expansion to the foot print of the building including decks and porches not originally shown on the approved set of plans must obtain proper permits prior to construction. * The applicant is responsible to call the Utility Notification Center at 1-800-424-5555 before beginning any excavation. Call before you dig, it's the law. * No work shall be done in or on the public right of way without a licensed and bonded contractor first obtaining a right of way permit. * Any code requirement that may have been overlooked in this plan review does not imply that the requirements have been waived.
Building Permit Standard Conditions Resolved Building Division Standard Conditions
: PERMIT CONDITIONS: 1- COMPLY WITH 2015 IFC AND 2015 IBC 2- FIRE ALARM SYSTEM TO BE DESIGNED TO TOTAL COVERAGE NFPA72. PER PUYALLUP PMC. 3- EXIT LIGHTING TEST REQUIRED CONTRACTOR TO PROVIDE LIGHT METER 4- EMERGENCY RADIO TEST REQUIRED COMPLY WITH IFC SECTION 510 5- FIRE EXTINGUISHERS REQUIRED PER CODE 6- SEPARATE PERMITS ARE REQUIRED FOR FIRE ALARM AND FIRE SRPINKLER SYSTEM 7- SEPERATE PERMIT REQUIRED FOR BACK UP GENERATOR. 8- SEPERATE PERMIT REQUIRED FOR HODD SUPRESSION. 9- FIRE ACCESS ROAD SHALL NOT EXCEED 10% GRADE. 10- ALL ABOVE ITEMS TO BE COMPLETED PRIOR TO FIRE FINAL. FIRE FINAL REQUIRED BEFORE BUILDING FINAL INSPECTION REQUEST CODES: 2252 EXIT LIGHT TEST 5610 EMERGENCY RADIO TEST 9200 FIRE BUILDING FINAL SCHEDULE YOUR INSPECTION BY PHONE OR ONLINE THROUGH THE CITY OF PUYALLUP ONLINE PERMIT SYSTEM. THEN CALL MORNING OF INSPECTION BETWEEN 7AM - 8PM TO SET UP A TIME. HTTPS://SECURE.CITYOFPUYALLUP.ORG/ INSPECTION LINE 1-877-232-6456 (USE MUTE TO AVOID BACKGROUND NOISE) DAVID DRAKE AT 253-864-4171 OR RAY COCKERHAM AT 253-864-4171
Pipeline Notfication Rcw 19.122.033 Resolved Engineering Division Standard Conditions
: Effective January 1, 2013 RCW 19.122 Before conducting any construction or excavation within 100 feet of a right-of-way or utility easement containing a transmission pipeline a person must notify the pipeline companies of the scheduled excavation through the one-number locator service 811. Notification must occur in a window of not less than 2 business days but not more than 10 business days before beginning the excavation. If a transmission pipeline company is notified that excavation work will occur near a pipeline, a representative of the company must consult with the excavator on-site prior to excavation.

Related Permit & Planning Applications

There are no related items for this permit application.

Documents & Images

No documents are currently available for viewing.


Should you need assistance, please contact the Permit Center at (253) 864-4165 option 1.