CITY OF PUYALLUP PERMITTING PORTAL

Permit Application Status

B-19-0190


In order to request inspections, you need to be signed in.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

B-19-0190
Retaining Wall
Closed
GOOD SAMARITIAN HOSPITAL
Other
RETAINING WALL ~ GSH CENTRAL PARKING LOT
03/13/2019
05/09/2019
11/04/2019
08/23/2019

Locations

Reviews

Review Type Outcome Est. Completion Date Completed
Building Review VOID 12/09/2021
Engineering Review Approved 05/08/2019
Building Review Approved 04/08/2019
Planning Review Approved 04/02/2019

Fees

Paid Fees Amount Paid Owing Date Paid
Building Permit Fee $1,195.35 $1,195.35 Paid 05/09/2019
No
Building Plan Review Fee $776.98 $776.98 Paid 03/13/2019
No
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


Permit(s) will not be issued until outstanding fees have been paid in full. Fee details shown above only include currently payable fees, there might be addtional fees to be paid before issuance.

$0.00

Inspections

Inspection Outcome Requested Scheduled Date Inspected
Building Final Inspection Approved 8/23/2019 08/23/2019
Gary Webster ((253) 841-5590)

Conditions

Condition Status Department Category Expiration Date Due Date
General Permit Conditions Resolved Building Division Standard Conditions
: * Final approval by the Building Official is required prior to use or occupancy. * Work shall not proceed until the inspector has approved the stages of construction. * Surface storm water shall be diverted from the building site and shall not drain onto adjacent properties. * I hereby acknowledge that I have read this Permit/Application, that the information given is correct; that I am the owner or the duly authorized agent of the owner; that plans submitted herewith are in compliance with all applicable city, county and state laws and that all construction will proceed in accordance with said laws. This permit shall expire if work is not commenced with 180 days or if the work is suspended for a period of 180 days. Permits expire two years from issuance. * By leaving the contractor information section blank, I hereby certify further that contractors (general or subcontractors) will not be hired to perform any work in association with this permit. I also certify that if I do choose to hire a contractor (general or subcontractor) I will only hire those contractors that are licensed by the State of Washington. * TO SCHEDULE INSPECTIONS, CHECK PERMIT STATUS OR TO MAKE PAYMENTS ON THE CITY WEB SITE VISIT https://secure.cityofpuyallup.org/
Building Permit Standard Conditions Resolved Building Division Standard Conditions
: PERMIT CONDITIONS: *Geo-technical inspections are required in accordance with engineering design. *Final geotechnical report is required. *Footing, drainage and backfill to be constructed as indicated in the approved Engineering Design.
Pipeline Notfication Rcw 19.122.033 Resolved Engineering Division Standard Conditions
: Effective January 1, 2013 RCW 19.122 Before conducting any construction or excavation within 100 feet of a right-of-way or utility easement containing a transmission pipeline a person must notify the pipeline companies of the scheduled excavation through the one-number locator service 811. Notification must occur in a window of not less than 2 business days but not more than 10 business days before beginning the excavation. If a transmission pipeline company is notified that excavation work will occur near a pipeline, a representative of the company must consult with the excavator on-site prior to excavation.

Related Permit & Planning Applications

There are no related items for this permit application.

Documents & Images

No documents are currently available for viewing.


Should you need assistance, please contact the Permit Center at (253) 864-4165 option 1.