CITY OF PUYALLUP PERMITTING PORTAL

Permit Application Status

B-19-0589


In order to request inspections, you need to be signed in.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

B-19-0589
Commercial - Tenant Improvement/Remodel
Closed
Alteration/Remodel
TI ~ KITCHEN, DINING ROOM & CLASSROOM #181 ~ SEVENTH DAY ADVENTIST **9.24.19 ADDED 1188SF STORAGE** BLDG/ PLUMB//MECH PROJECT IS STILL UNDERWAY WITH PHASE II**
07/01/2019
10/02/2019
07/19/2021
01/28/2021

Locations

Reviews

Review Type Outcome Est. Completion Date Completed
Building Review VOID 12/09/2021
Building Review Approved 09/27/2019
Planning Review Approved 09/24/2019
Engineering Review Approved 08/29/2019
Fire Review Approved 07/31/2019

Fees

Paid Fees Amount Paid Owing Date Paid
WA State Building Code Council Fee (Residential) $25.00 $25.00 Paid 10/02/2019
No
Planning Building Permit Fee $30.00 $30.00 Paid 10/02/2019
No
Mechanical Plan Review Fee $51.42 $51.42 Paid 10/02/2019
No
Plumbing Plan Review Fee $60.61 $60.61 Paid 10/02/2019
No
Mechanical Permit Fee $79.10 $79.10 Paid 10/02/2019
No
Building Permit Fee $8,346.25 $8,346.25 Paid 10/02/2019
No
Plumbing Permit Fee $93.25 $93.25 Paid 10/02/2019
No
Planning Landscape Review Fee $90.00 $90.00 Paid 10/02/2019
No
Building Division Fee (Hourly) $130.00 $130.00 Paid 10/02/2019
No
Legacy Fee $130.00 $130.00 Paid 10/02/2019
No
Fire Review Fee (Commercial Building) $265.00 $265.00 Paid 10/02/2019
No
Building Plan Review Fee $5,425.06 $5,425.06 Paid 10/02/2019
No
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


Permit(s) will not be issued until outstanding fees have been paid in full. Fee details shown above only include currently payable fees, there might be addtional fees to be paid before issuance.

$0.00

Inspections

Inspection Outcome Requested Scheduled Date Inspected
Footing/Setback Inspection Approved 11/22/2019 11/22/2019
Monty Johnson ((253) 770-3326)
Comment Building Div Inspection Approved 03/03/2020
Ray Cockerham ((253) 841-5585)
Plumbing Rough In Inspection In Progress 3/19/2020 03/19/2020
Monty Johnson ((253) 770-3326)
Plumbing Rough In Inspection In Progress 3/23/2020 03/23/2020
Gary Webster ((253) 841-5590)
Energy (Insulation) Inspection Approved 5/12/2020 05/12/2020
Monty Johnson ((253) 770-3326)
Wallboard / Drywall Inspection Approved 6/1/2020 06/01/2020
Gary Webster ((253) 841-5590)
Comment Building Div Inspection In Progress 7/8/2020 07/08/2020
Monty Johnson ((253) 770-3326)
Engineering Final Inspection Approved 12/2/2020 12/02/2020
Marcus Sedlickas ((253) 405-1707)
Plumbing Final Inspection Approved 12/11/2020 12/11/2020
Monty Johnson ((253) 770-3326)
Planning Final Inspection In Progress 12/15/2020 12/15/2020
Nabila Comstock ((253) 770-3361)
Fire Final Inspection Approved 1/26/2021 01/26/2021
David Drake ((253) 864-4171)
Building Final Inspection Approved 01/28/2021
Monty Johnson ((253) 770-3326)
Mechanical Final Inspection VOID 12/09/2021
Monty Johnson ((253) 770-3326)
Comment Building Div Inspection VOID 12/09/2021
Ray Cockerham ((253) 841-5585)
Frame Inspection VOID 12/17/2019 12/09/2021
Monty Johnson ((253) 770-3326)
Shear Wall Inspection VOID 12/17/2019 12/09/2021
Monty Johnson ((253) 770-3326)
Frame Inspection VOID 2/5/2020 12/09/2021
Monty Johnson ((253) 770-3326)
Frame Inspection VOID 3/23/2020 12/09/2021
Gary Webster ((253) 841-5590)
Combination Frame And Rough In Inspection VOID 4/30/2020 12/09/2021
Monty Johnson ((253) 770-3326)
Energy (Insulation) Inspection VOID 4/30/2020 12/09/2021
Monty Johnson ((253) 770-3326)
Combination Frame And Rough In Inspection VOID 5/12/2020 12/09/2021
Monty Johnson ((253) 770-3326)
Ceiling Grid/T-Bar Inspection VOID 7/2/2020 12/09/2021
Monty Johnson ((253) 770-3326)
Comment Building Div Inspection VOID 8/21/2020 12/09/2021
Gary Webster ((253) 841-5590)
Plumbing Final Inspection VOID 10/30/2020 12/09/2021
Monty Johnson ((253) 770-3326)
Plumbing Rough In Inspection VOID 12/8/2020 12/09/2021
Monty Johnson ((253) 770-3326)
Plumbing Final Inspection VOID 12/8/2020 12/09/2021
Monty Johnson ((253) 770-3326)
Mechanical Final Inspection VOID 12/11/2020 12/09/2021
Monty Johnson ((253) 770-3326)
Building Final Inspection VOID 12/11/2020 12/09/2021
Monty Johnson ((253) 770-3326)
Building Final Inspection VOID 12/16/2020 12/09/2021
Monty Johnson ((253) 770-3326)
Mechanical Final Inspection VOID 12/16/2020 12/09/2021
Monty Johnson ((253) 770-3326)
Building Final Inspection VOID 12/17/2020 12/09/2021
Monty Johnson ((253) 770-3326)
Mechanical Final Inspection VOID 12/17/2020 12/09/2021
Monty Johnson ((253) 770-3326)
Mechanical Final Inspection VOID 12/18/2020 12/09/2021
Monty Johnson ((253) 770-3326)
Building Final Inspection VOID 12/18/2020 12/09/2021
Monty Johnson ((253) 770-3326)
Mechanical Final Inspection VOID 1/15/2021 12/09/2021
Monty Johnson ((253) 770-3326)
Building Final Inspection VOID 1/15/2021 12/09/2021
Monty Johnson ((253) 770-3326)
Mechanical Final Inspection VOID 1/20/2021 12/09/2021
Monty Johnson ((253) 770-3326)

Conditions

Condition Status Department Category Expiration Date Due Date
General Permit Conditions Resolved Building Division Standard Conditions
: * Final approval by the Building Official is required prior to use or occupancy. * Work shall not proceed until the inspector has approved the stages of construction. * Surface storm water shall be diverted from the building site and shall not drain onto adjacent properties. * I hereby acknowledge that I have read this Permit/Application, that the information given is correct; that I am the owner or the duly authorized agent of the owner; that plans submitted herewith are in compliance with all applicable city, county and state laws and that all construction will proceed in accordance with said laws. This permit shall expire if work is not commenced with 180 days or if the work is suspended for a period of 180 days. Permits expire two years from issuance. * By leaving the contractor information section blank, I hereby certify further that contractors (general or subcontractors) will not be hired to perform any work in association with this permit. I also certify that if I do choose to hire a contractor (general or subcontractor) I will only hire those contractors that are licensed by the State of Washington. * TO SCHEDULE INSPECTIONS, CHECK PERMIT STATUS OR TO MAKE PAYMENTS ON THE CITY WEB SITE VISIT https://secure.cityofpuyallup.org/
Engineering Commercial Standard Conditions Resolved Engineering Division Standard Conditions
: * Any addition/expansion to the foot print of the building including decks and porches not originally shown on the approved set of plans must obtain proper permits prior to construction. * Any code requirement that may have been overlooked in this plan review does not imply that the requirements have been waived.
Building Permit Standard Conditions Resolved Building Division Standard Conditions
: PERMIT CONDITIONS:
Building Permit Standard Conditions Resolved Building Division Standard Conditions
: PERMIT CONDITIONS: 1- COMPLY WITH 2015 IFC AND 2015 IBC 2- TOTAL COVERAGE REQUIRED IN THE CITY OF PUYALLUP 3- EXIT LIGHTING TEST REQUIRED CONTRACTOR TO PROVIDE LIGHT METER 4- EMERGENCY RADIO TEST REQUIRED COMPLY WITH IFC SECTION 510. FIRE FINAL APPROVAL APON COMPLETED TEST RESULTS 5- SEPERATE PERMITS ARE REQUIRED FOR FIRE ALARM AND FIRE SPRINKLER. 6- RTU'S WILL BE REQUIRED TO BE TESTED FOR SHUT DOWN. 7- FIRE EXTINGUISHERS REQUIRED PER CODE 8- A KNOX BOX IS REQUIRED AT THE FRONT ENTRY ON THE EXTERIOR OF THE BUILDING 9- PIV MUST HAVE A KNOX LOCK OR APPROVED LOCK WITH AN EXTRA KEY PROVIDED IN KNOX BOX 10- EXISTING BUILDINGS WILL NEED TO CONTACT CENTRAL PIERCE FIRE & RESCUE AND UPDATE THE KEY IN THE KNOX BOX 11- ALL ABOVE ITEMS TO BE COMPLETED PRIOR TO FIRE FINAL. FIRE FINAL REQUIRED BEFORE BUILDING FINAL INSPECTION REQUEST CODES: 2252 EXIT LIGHT TEST 5610 EMERGENCY RADIO TEST 9200 FIRE BUILDING FINAL SCHEDULE YOUR INSPECTION BY PHONE OR ONLINE THROUGH THE CITY OF PUYALLUP ONLINE PERMIT SYSTEM. THEN CALL MORNING OF INSPECTION BETWEEN 7AM - 8PM TO SET UP A TIME. HTTPS://SECURE.CITYOFPUYALLUP.ORG/ INSPECTION LINE 1-877-232-6456 (USE MUTE TO AVOID BACKGROUND NOISE) DAVID DRAKE AT 253-864-4171 OR RAY COCKERHAM AT 253-841-5585
Pipeline Notfication Rcw 19.122.033 Resolved Engineering Division Standard Conditions
: Effective January 1, 2013 RCW 19.122 Before conducting any construction or excavation within 100 feet of a right-of-way or utility easement containing a transmission pipeline a person must notify the pipeline companies of the scheduled excavation through the one-number locator service 811. Notification must occur in a window of not less than 2 business days but not more than 10 business days before beginning the excavation. If a transmission pipeline company is notified that excavation work will occur near a pipeline, a representative of the company must consult with the excavator on-site prior to excavation.

Related Permit & Planning Applications

There are no related items for this permit application.

Documents & Images

No documents are currently available for viewing.


Should you need assistance, please contact the Permit Center at (253) 864-4165 option 1.