CITY OF PUYALLUP PERMITTING PORTAL

Permit Application Status

B-20-0235


In order to request inspections, you need to be signed in.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

B-20-0235
Commercial - New Construction
Closed
CH REALTYIX-JV I PUYALLUP LOGISTICS LP
Other
TILT UP WAREHOUSE ~ PUYALLUP CORPORATE CENTER BLDG/MECH/DEEP UNDERGROUND PLUMB
04/06/2020
03/02/2021
09/17/2022
03/21/2022

Locations

Reviews

Review Type Outcome Est. Completion Date Completed
Engineering Review Approved 02/22/2021
Engineering Review Incomplete 04/06/2020 10/27/2020
Planning Review In Progress 05/27/2020 10/27/2020
Building Review Approved 10/23/2020
Engineering Traffic Review Approved 04/06/2020 08/03/2020
Building Review Incomplete 04/06/2020 06/23/2020
Planning Review Incomplete 04/06/2020 05/27/2020

Fees

Paid Fees Amount Paid Owing Date Paid
Fire Review Fee (Commercial Building) $265.00 $265.00 Paid 03/02/2021
No
WA State Building Code Council Fee (Residential) $25.00 $25.00 Paid 03/02/2021
No
Traffic Impact Fee $166,500.00 $166,500.00 Paid 03/02/2021
No
Plumbing Permit Fee $53.00 $53.00 Paid 03/02/2021
No
Planning Building Permit Fee $120.00 $120.00 Paid 03/02/2021
No
Plumbing Plan Review Fee $34.45 $34.45 Paid 03/02/2021
No
Park Impact Fee $169,603.89 $169,603.89 Paid 03/02/2021
No
Building Division Fee (Hourly) $130.00 $130.00 Paid 03/02/2021
No
Mechanical Permit Fee $220.70 $220.70 Paid 03/02/2021
No
Planning Landscape Review Fee $300.00 $300.00 Paid 03/02/2021
No
Building Plan Review Fee $16,872.38 $16,872.38 Paid 03/02/2021
No
Mechanical Plan Review Fee $143.46 $143.46 Paid 03/02/2021
No
Building Permit Fee $25,957.50 $25,957.50 Paid 03/02/2021
No
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


Permit(s) will not be issued until outstanding fees have been paid in full. Fee details shown above only include currently payable fees, there might be addtional fees to be paid before issuance.

$0.00

Inspections

Inspection Outcome Requested Scheduled Date Inspected
Foundation/Rebar Inspection In Progress 3/22/2021 03/22/2021
Gary Webster ((253) 841-5590)
Foundation/Rebar Inspection In Progress 3/29/2021 03/29/2021
Gary Webster ((253) 841-5590)
Tilt Up Panel Inspection In Progress 3/30/2021 03/30/2021
Gary Webster ((253) 841-5590)
Plumbing Below Slab Inspection Failed 4/27/2021 04/27/2021
Gary Webster ((253) 841-5590)
Tilt Up Panel Inspection Comments 5/14/2021 05/14/2021
Monty Johnson ((253) 770-3326)
Tilt Up Panel Inspection In Progress 5/17/2021 05/17/2021
Gary Webster ((253) 841-5590)
Tilt Up Panel Inspection In Progress 5/27/2021 05/27/2021
Gary Webster ((253) 841-5590)
Comment Building Div Inspection Comments 6/23/2021 06/23/2021
Gary Webster ((253) 841-5590)
Comment Building Div Inspection Comments 6/25/2021 06/25/2021
Gary Webster ((253) 841-5590)
Plumbing Below Slab Inspection In Progress 7/12/2021 07/12/2021
Gary Webster ((253) 841-5590)
Foundation/Rebar Inspection In Progress 7/12/2021 07/12/2021
Gary Webster ((253) 841-5590)
Foundation/Rebar Inspection In Progress 7/19/2021 07/19/2021
Gary Webster ((253) 841-5590)
Foundation/Rebar Inspection In Progress 7/23/2021 07/23/2021
Gary Webster ((253) 841-5590)
Foundation/Rebar Inspection In Progress 7/27/2021 07/27/2021
Gary Webster ((253) 841-5590)
Energy (Insulation) Inspection Comments 7/30/2021 07/30/2021
Gary Webster ((253) 841-5590)
Frame Inspection In Progress 7/30/2021 07/30/2021
Gary Webster ((253) 841-5590)
Energy (Insulation) Inspection In Progress 8/3/2021 08/03/2021
Gary Webster ((253) 841-5590)
Energy (Insulation) Inspection In Progress 8/5/2021 08/05/2021
Gary Webster ((253) 841-5590)
Energy (Insulation) Inspection In Progress 8/9/2021 08/09/2021
Gary Webster ((253) 841-5590)
Frame Inspection In Progress 8/9/2021 08/09/2021
Gary Webster ((253) 841-5590)
Energy (Insulation) Inspection In Progress 8/13/2021 08/13/2021
Gary Webster ((253) 841-5590)
Foundation/Rebar Inspection Comments 8/17/2021 08/17/2021
Shannon King ((253) 840-6684)
Energy (Insulation) Inspection Comments 8/17/2021 08/17/2021
Shannon King ((253) 840-6684)
Energy (Insulation) Inspection In Progress 8/19/2021 08/19/2021
Shannon King ((253) 840-6684)
Frame Inspection In Progress 8/19/2021 08/19/2021
Shannon King ((253) 840-6684)
Wallboard / Drywall Inspection In Progress 8/23/2021 08/23/2021
Gary Webster ((253) 841-5590)
Frame Inspection In Progress 8/24/2021 08/24/2021
Gary Webster ((253) 841-5590)
Energy (Insulation) Inspection In Progress 8/24/2021 08/24/2021
Gary Webster ((253) 841-5590)
Wallboard / Drywall Inspection In Progress 8/26/2021 08/26/2021
Gary Webster ((253) 841-5590)
Energy (Insulation) Inspection In Progress 8/26/2021 08/26/2021
Gary Webster ((253) 841-5590)
Energy (Insulation) Inspection In Progress 9/1/2021 09/01/2021
Gary Webster ((253) 841-5590)
Foundation/Rebar Inspection In Progress 9/1/2021 09/01/2021
Gary Webster ((253) 841-5590)
Foundation/Rebar Inspection Comments 9/7/2021 09/07/2021
Gary Webster ((253) 841-5590)
Energy (Insulation) Inspection In Progress 9/7/2021 09/07/2021
Gary Webster ((253) 841-5590)
Foundation/Rebar Inspection In Progress 9/8/2021 09/08/2021
Gary Webster ((253) 841-5590)
Foundation/Rebar Inspection In Progress 9/13/2021 09/13/2021
Gary Webster ((253) 841-5590)
Wallboard / Drywall Inspection In Progress 9/13/2021 09/13/2021
Gary Webster ((253) 841-5590)
Frame Inspection In Progress 9/13/2021 09/13/2021
Gary Webster ((253) 841-5590)
Mechanical Rough In Inspection In Progress 9/22/2021 09/22/2021
Gary Webster ((253) 841-5590)
Wallboard / Drywall Inspection In Progress 10/8/2021 10/08/2021
Gary Webster ((253) 841-5590)
Frame Inspection In Progress 10/8/2021 10/08/2021
Gary Webster ((253) 841-5590)
Foundation/Rebar Inspection In Progress 10/8/2021 10/08/2021
Gary Webster ((253) 841-5590)
Plumbing Rough In Inspection In Progress 11/4/2021 11/04/2021
Gary Webster ((253) 841-5590)
Plumbing Final Inspection Comments 12/7/2021 12/07/2021
Shannon King ((253) 840-6684)
Mechanical Final Inspection Comments 12/7/2021 12/07/2021
Shannon King ((253) 840-6684)
Fire Final Inspection Passed w/ Conditions 12/15/2021 12/15/2021
David Drake ((253) 864-4171)
Miscellaneous Planning Correction
Carried Forward
12/15/2021
Complete entrance per Engineering Standards and Bond. EXIT SIGNS TESTED, EMERGENCY LIGHTING TEST AT T.I. EMERGENCY RADIO TEST AT T.I.

Mechanical Final Inspection Failed 1/24/2022 1/24/2022 01/24/2022
Gary Webster ((253) 841-5590)
Other/Miscellaneous
Carried Forward
01/24/2022
1 seal chase (doghouse) for line sets @ roof 2 complete insulation of line on roof 3 provide uv protectant wrap on roof

Comment Building Div Inspection Failed 1/31/2022 1/31/2022 01/31/2022
Gary Webster ((253) 841-5590)
Other/Miscellaneous
Carried Forward
01/31/2022

Other/Miscellaneous
Carried Forward
01/31/2022
onsite for final building inspection

Energy (Insulation) Inspection VOID 01/31/2022
Gary Webster ((253) 841-5590)
Frame Inspection VOID 01/31/2022
Gary Webster ((253) 841-5590)
Combination Frame And Rough In Inspection VOID 01/31/2022
Gary Webster ((253) 841-5590)
Plumbing Below Slab Inspection VOID 01/31/2022
Gary Webster ((253) 841-5590)
Foundation/Rebar Inspection VOID 01/31/2022
Gary Webster ((253) 841-5590)
Tilt Up Panel Inspection VOID 01/31/2022
Gary Webster ((253) 841-5590)
Footing/Setback Inspection VOID 01/31/2022
Gary Webster ((253) 841-5590)
Tilt Up Panel Inspection VOID 01/31/2022
Gary Webster ((253) 841-5590)
Mechanical Rough In Inspection VOID 01/31/2022
Gary Webster ((253) 841-5590)
Tilt Up Panel Inspection VOID 01/31/2022
Gary Webster ((253) 841-5590)
Wallboard / Drywall Inspection VOID 01/31/2022
Gary Webster ((253) 841-5590)
Plumbing Final Inspection VOID 01/31/2022
Gary Webster ((253) 841-5590)
Building Final Inspection Failed 01/31/2022
Gary Webster ((253) 841-5590)
Other/Miscellaneous
Outstanding
01/31/2022
provide all other city of puyallup departments final approvals

Other/Miscellaneous
Outstanding
01/31/2022
provide all other city of puyallup departments final approvals

Engineering Final Inspection Not Ready 1/31/2022 1/31/2022 02/01/2022
Jeff Hill ((253) 204-5633)
Planning Final Inspection Failed 2/17/2022 2/18/2022 02/22/2022
Nabila Comstock ((253) 770-3361)
Miscellaneous Planning Correction
Carried Forward
02/22/2022
1. Historical tree plaque – as a SEPA mitigation measure for removal of historical linden trees along the frontage, a plaque is required to be installed next to the sidewalk at the front of the site. The concrete pad for the plaque appears to have been poured, but the plaque is not there. The text for the plaque was emailed to Kevin Cash, AHBL, on April 13, 2021 by the project review planner, Kendall Wals. The plaque location and specs are provided on the approved landscape plan (sheet L100 and L505) and civil plan (C12).

Miscellaneous Planning Correction
Carried Forward
02/22/2022
2. Mulch – it appears that mulch is missing from the front yard landscaping and other landscape islands/perimeter landscape beds. All landscape areas shall be mulched per the approved plans.

Miscellaneous Planning Correction
Carried Forward
02/22/2022
3. Missing/uninstalled plants – a. At the time of inspection, there were two trees sitting within the perimeter landscape bed at the northwest corner that were not installed. b. In the landscape beds at the entry, there appear to be placeholders (i.e. empty pots in the dirt of the landscape bed) for some of the shrubs, but not all of the landscaping had been installed. c. At the southwest corner of the site, it appears that four pacific ninebark shrubs were missing within the perimeter landscape bed.

Plumbing Rough In Inspection VOID 03/21/2022
Gary Webster ((253) 841-5590)
Tilt Up Panel Inspection VOID 03/21/2022
Gary Webster ((253) 841-5590)
Mechanical Final Inspection VOID 03/21/2022
Gary Webster ((253) 841-5590)
Other/Miscellaneous
Outstanding
01/24/2022
1 seal chase (doghouse) for line sets @ roof 2 complete insulation of line on roof 3 provide uv protectant wrap on roof

Comment Building Div Inspection VOID 03/21/2022
Gary Webster ((253) 841-5590)
Other/Miscellaneous
Outstanding
01/31/2022

Other/Miscellaneous
Outstanding
01/31/2022
onsite for final building inspection

Conditions

Condition Status Department Category Expiration Date Due Date
General Permit Conditions Resolved Building Division Standard Conditions
: * Final approval by the Building Official is required prior to use or occupancy. * Work shall not proceed until the inspector has approved the stages of construction. * Surface storm water shall be diverted from the building site and shall not drain onto adjacent properties. * I hereby acknowledge that I have read this Permit/Application, that the information given is correct; that I am the owner or the duly authorized agent of the owner; that plans submitted herewith are in compliance with all applicable city, county and state laws and that all construction will proceed in accordance with said laws. This permit shall expire if work is not commenced with 180 days or if the work is suspended for a period of 180 days. Permits expire two years from issuance. * By leaving the contractor information section blank, I hereby certify further that contractors (general or subcontractors) will not be hired to perform any work in association with this permit. I also certify that if I do choose to hire a contractor (general or subcontractor) I will only hire those contractors that are licensed by the State of Washington. * TO SCHEDULE INSPECTIONS, CHECK PERMIT STATUS OR TO MAKE PAYMENTS ON THE CITY WEB SITE VISIT https://secure.cityofpuyallup.org/
Engineering Commercial Standard Conditions Resolved Engineering Division Standard Conditions
: ** OCCUPANCY WILL NOT BE GRANTED UNTIL ALL WORK ASSOCIATED WITH CIVIL PERMIT E-20-0137 HAS BEEN COMPLETED ** * THE APPLICANT IS RESPONSIBLE TO CALL THE INSPECTION LINE AT 877-232-6456 TO SCHEDULE INSPECTIONS. UTILITY INSPECTIONS ARE REQUIRED PRIOR TO BACKFILLING. ** SEDIMENT CONTROL AND EROSION PROCEDURES SHALL BE PRACTICE TO ELIMINATE AND PREVENT OFF SITE DAMAGE. STORMWATER RUNOFF ORIGINATING UPGRADE OF EXPOSED AREAS SHALL BE CONTROLLED TO REDUCE EROSION AND SEDIMENT LOSS DURING THE PERIOD OF EXPOSURE. SEE CIVIL PERMIT E-20-0137 FOR REQUIREMENTS. ** STORMWATER CONTROL OF ROOF DOWNSPOUTS MUST BE CONTROLLED. SEE CIVIL PERMIT E-20-0137 FOR REQUIREMENTS. * Curb, gutter, sidewalk and approach must be poured per City Standards. * Driveway approach must be a minimum of 30' wide. * The builder/owner shall be responsible for keeping the existing right-of-way free of debris and dirt. Any violation of PMC Chapter 21.14 pertaining to clearing, filling and grading, erosion and sediment control, and storm water discharges shall be prosecuted to the fullest extent of the law. * Any addition/expansion to the foot print of the building including decks and porches not originally shown on the approved set of plans must obtain proper permits prior to construction. * The applicant is responsible to call the Utility Notification Center at 1-800-424-5555 before beginning any excavation. Call before you dig, it's the law. * No work shall be done in or on the public right of way without a licensed and bonded contractor first obtaining a right of way permit. * Any code requirement that may have been overlooked in this plan review does not imply that the requirements have been waived. * All commercial development water service connections are to be protected by a reduced pressure backflow assembly (RPBA), as directed by the Puyallup Municipal Code 14.02.220(3) and conforming to City Standard Section 3.2.2 and Details 03.04.02-1, 03.04.02-2 and 03.04.03. * All commercial developments, irrigation systems and multi family water service connections shall be protected by at reduced pressure backflow assembly (RPBA), as directed by the City, Fruitland Mutual Water Company, Tacoma City Water or Valley Water District conforming to City Standard Details 03.04.02-1, 03.04.02-2 and 03.04.03.
Building Permit Standard Conditions Resolved Building Division Standard Conditions
: PERMIT CONDITIONS: 1- COMPLY WITH 2015 IFC AND 2015 IBC 2- TOTAL COVERAGE REQUIRED IN THE CITY OF PUYALLUP 3- EXIT LIGHTING TEST REQUIRED CONTRACTOR TO PROVIDE LIGHT METER 4- EMERGENCY RADIO TEST REQUIRED COMPLY WITH IFC SECTION 510. FIRE FINAL APPROVAL APON COMPLETED TEST RESULTS 5- SEPERATE PERMITS ARE REQUIRED FOR FIRE ALARM AND FIRE SPRINKLER 6- RTU'S WILL BE REQUIRED TO BE TESTED FOR SHUT DOWN. 7- FIRE EXTINGUISHERS REQUIRED PER CODE 8- A KNOX BOX IS REQUIRED AT THE FRONT ENTRY ON THE EXTERIOR OF THE BUILDING 9- PIV MUST HAVE A KNOX LOCK OR APPROVED LOCK WITH AN EXTRA KEY PROVIDED IN KNOX BOX 10- CONTACT CENTRAL PIERCE FIRE & RESCUE FOR LOCKING AND UNLOCKING OF KNOX BOX. PLEASE HAVE ALL KEYS AVALIABLE AT APOINTMENT. 11- L&I APPROVAL REQUIRED PRIOR TO ALL FINALS. 11- ALL ABOVE ITEMS TO BE COMPLETED PRIOR TO FIRE FINAL. FIRE FINAL REQUIRED BEFORE BUILDING FINAL INSPECTION REQUEST CODES: 2252 EXIT LIGHT TEST 5610 EMERGENCY RADIO TEST 9200 FIRE BUILDING FINAL SCHEDULE YOUR INSPECTION BY PHONE OR ONLINE THROUGH THE CITY OF PUYALLUP ONLINE PERMIT SYSTEM. THEN CALL MORNING OF INSPECTION BETWEEN 7AM - 8PM TO SET UP A TIME. INSPECTIONS ARE MONDAY - THURSDAY THERE WILL BE NO INSPECTIONS ON FRIDAYS. HTTPS://SECURE.CITYOFPUYALLUP.ORG/ INSPECTION LINE 1-877-232-6456 (USE MUTE TO AVOID BACKGROUND NOISE) DAVID DRAKE AT 253-864-4171 OR RAY COCKERHAM AT 253-841-5585
Pipeline Notfication Rcw 19.122.033 Resolved Engineering Division Standard Conditions
: Effective January 1, 2013 RCW 19.122 Before conducting any construction or excavation within 100 feet of a right-of-way or utility easement containing a transmission pipeline a person must notify the pipeline companies of the scheduled excavation through the one-number locator service 811. Notification must occur in a window of not less than 2 business days but not more than 10 business days before beginning the excavation. If a transmission pipeline company is notified that excavation work will occur near a pipeline, a representative of the company must consult with the excavator on-site prior to excavation.

Related Permit & Planning Applications

There are no related items for this permit application.

Documents & Images

Date Uploaded File Type Name
01/24/2022 Report Inspection Report (Mechanical Final Inspection)
01/31/2022 Report Inspection Report (Building Final Inspection)
01/31/2022 Report Inspection Report (Comment Building Div Inspection)
03/21/2022 Report Inspection Report (Building Final Inspection)


Should you need assistance, please contact the Permit Center at (253) 864-4165 option 1.