CITY OF PUYALLUP PERMITTING PORTAL

Permit Application Status

B-21-0225


In order to request inspections, you need to be signed in.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

B-21-0225
Commercial - Tenant Improvement/Remodel
Closed
MULTICARE HEALTH SYSTEM
Alteration/Remodel
BUILD-OUT OF OR 7 & 8 IN EXISTING SHELL SPACE ~VALLEY TOWER/2ND FL
04/05/2021
02/10/2023
07/03/2024

Locations

Reviews

Documents Returned For Corrections

Review Type Outcome Est. Completion Date Completed
Engineering Review Approved 05/12/2022 05/11/2022
Engineering Review VOID 12/10/2021
Fire Review Approved 06/07/2021
Building Review Approved 05/07/2021 05/07/2021
Planning Review Approved 04/30/2021

Fees

Paid Fees Amount Paid Owing Date Paid
Building Plan Review Fee $3,201.09 $3,201.09 Paid 04/26/2021
No
Fire Review Fee (Commercial Building) $265.00 $265.00 Paid 02/10/2023
Building Permit Fee $4,924.75 $4,924.75 Paid 02/10/2023
Mechanical Permit Fee $68.20 $68.20 Paid 02/10/2023
$40.00
Plumbing Permit Fee $429.50 $429.50 Paid 02/10/2023
$40.00
Mechanical Plan Review Fee $44.33 $44.33 Paid 02/10/2023
Plumbing Plan Review Fee $279.18 $279.18 Paid 02/10/2023
WA State Building Code Council Fee (Commercial) $25.00 $25.00 Paid 02/10/2023
Planning Landscape Review Fee $300.00 $300.00 Paid 02/10/2023
Planning Review Fee $120.00 $120.00 Paid 02/10/2023
$30.00
Sewer System Development ChargeFee - Tenant Improvment/Addition $3,157.04 $3,157.04 Paid 02/10/2023
Water System Development ChargeFee - Tenant Improvment/Addition $2,283.36 $2,283.36 Paid 02/10/2023
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


Permit(s) will not be issued until outstanding fees have been paid in full. Fee details shown above only include currently payable fees, there might be addtional fees to be paid before issuance.

$0.00

Inspections

Inspection Outcome Requested Scheduled Date Inspected
Comment Building Div Inspection Approved 05/07/2021
Ray Cockerham ((253) 841-5585)
Building Final Inspection Not Ready 5/26/2023 5/26/2023 05/26/2023
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Resolved
01/05/2024
1. will need to contact inspector of record

Comment Building Div Inspection Not Ready 5/31/2023 5/31/2023 05/31/2023
Shannon King ((253) 840-6684)
Combination Frame And Rough In Inspection Partial Pass 6/27/2023 6/27/2023 06/27/2023
Shannon King ((253) 840-6684)
Other/Miscellaneous
Resolved
01/05/2024
1 ; complete framing as per city approved plans. ( inspection of OR7 & OR8 only) 2 ; provide electrical cover approval prior to frame inspection. 3 ; complete nail plates at electrical as discussed with contractor. 4 ; plumbing approved as noted on sheet m3.02 of approved plans (d.w.v. and supply only) 5 ; mechanical approved as noted on sheet m4.02 0f city approved plans.

Wallboard / Drywall Inspection Not Ready 6/30/2023 6/30/2023 06/30/2023
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Resolved
01/05/2024
1. cancelled by contractor

Medical Gas Inspection Partial Pass 7/14/2023 7/14/2023 07/14/2023
Ray Cockerham ((253) 841-5585)
Other/Miscellaneous
Resolved
07/14/2023
Med. Gas pressure test bank at OR seven and OR eight.. contractor confirmed third-party inspection is complete, report to be available for next inspection

Wallboard / Drywall Inspection Partial Pass 7/31/2023 7/31/2023 07/31/2023
Shannon King ((253) 840-6684)
Other/Miscellaneous
Resolved
07/31/2023
1. cancelled by contractor

Combination Frame And Rough In Inspection Partial Pass 8/4/2023 8/4/2023 08/04/2023
Shannon King ((253) 840-6684)
Other/Miscellaneous
Resolved
01/05/2024
1 ; complete framing as per city approved plans. ( inspection of OR7 & OR8 only) 2 ; provide electrical cover approval prior to frame inspection. 3 ; complete nail plates at electrical as discussed with contractor. 4 ; plumbing approved as noted on sheet m3.02 of approved plans (d.w.v. and supply only) 5 ; mechanical approved as noted on sheet m4.02 0f city approved plans.

Frame Inspection Not Ready 8/30/2023 8/30/2023 08/30/2023
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Resolved
01/05/2024
1. provide electrical cover approval 2. provide MED gas report 3.provide missing screws at studs as discussed with contractor 4.clean all bottom tracks of walls 5. not ready

Combination Frame And Rough In Inspection Partial Pass 8/31/2023 8/31/2023 09/01/2023
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Resolved
01/05/2024
1 ; complete framing as per city approved plans. ( inspection of OR7 & OR8 only) 2 ; provide electrical cover approval prior to frame inspection. 3 ; complete nail plates at electrical as discussed with contractor. 4 ; plumbing approved as noted on sheet m3.02 of approved plans (d.w.v. and supply only) 5 ; mechanical approved as noted on sheet m4.02 0f city approved plans.

Frame Inspection Failed 9/5/2023 9/5/2023 09/05/2023
Shannon King ((253) 840-6684)
Other/Miscellaneous
Resolved
09/05/2023
1. provide electrical cover approval 2. provide MED gas report 3.provide missing screws at studs as discussed with contractor 4.clean all bottom tracks of walls 5. not ready

Other/Miscellaneous
Resolved
01/05/2024
1 ; provide city approved plans and engineering on-site for inspection of hard lids. not ready

Frame Inspection Failed 9/7/2023 9/7/2023 09/07/2023
Shannon King ((253) 840-6684)
Other/Miscellaneous
Resolved
01/05/2024
1 ; provide city approved plans and engineering on-site for inspection of hard lids. not ready

Other/Miscellaneous
Resolved
01/05/2024
1 ; provide engineering on-site for inspection of hard lids in O.R. 7&8. not ready

Frame Inspection Not Ready 9/11/2023 9/11/2023 09/11/2023
Shannon King ((253) 840-6684)
Other/Miscellaneous
Resolved
01/05/2024
1 ; provide city approved plans and engineering on-site for inspection of hard lids. not ready

Other/Miscellaneous
Resolved
01/05/2024
1 ; provide engineering on-site for inspection of hard lids in O.R. 7&8. not ready

Frame Inspection Not Ready 9/14/2023 9/14/2023 09/14/2023
Shannon King ((253) 840-6684)
Other/Miscellaneous
Resolved
01/05/2024
1 ; provide city approved plans and engineering on-site for inspection of hard lids. not ready

Other/Miscellaneous
Resolved
01/05/2024
1 ; provide engineering on-site for inspection of hard lids in O.R. 7&8. not ready

Other/Miscellaneous
Resolved
01/05/2024
1 ; provide engineering for hard lid ceiling in O.R 7&8 as discussed with contractor. 2 ; complete framing as per engineering at bracing removed as discussed with contractor. not ready

Frame Inspection Partial Pass 9/26/2023 9/26/2023 09/26/2023
Shannon King ((253) 840-6684)
Other/Miscellaneous
Resolved
01/05/2024
1 ; provide city approved plans and engineering on-site for inspection of hard lids. not ready

Other/Miscellaneous
Resolved
01/05/2024
1 ; provide engineering on-site for inspection of hard lids in O.R. 7&8. not ready

Other/Miscellaneous
Resolved
01/05/2024
1 ; provide engineering for hard lid ceiling in O.R 7&8 as discussed with contractor. 2 ; complete framing as per engineering at bracing removed as discussed with contractor. not ready

Wallboard / Drywall Inspection Partial Pass 9/28/2023 9/28/2023 09/28/2023
Shannon King ((253) 840-6684)
Planning Final Inspection VOID 10/24/2023
Chris Beale ((253) 841-5418)
Frame Inspection Partial Pass 10/24/2023 10/24/2023 10/24/2023
Shannon King ((253) 840-6684)
Other/Miscellaneous
Resolved
01/05/2024
1 ; provide city approved plans and engineering on-site for inspection of hard lids. not ready

Other/Miscellaneous
Resolved
01/05/2024
1 ; provide engineering on-site for inspection of hard lids in O.R. 7&8. not ready

Other/Miscellaneous
Resolved
01/05/2024
1 ; provide engineering for hard lid ceiling in O.R 7&8 as discussed with contractor. 2 ; complete framing as per engineering at bracing removed as discussed with contractor. not ready

Wallboard / Drywall Inspection Partial Pass 10/25/2023 10/25/2023 10/25/2023
Shannon King ((253) 840-6684)
Comment Building Div Inspection Not Ready 11/22/2023 11/22/2023 11/22/2023
Shannon King ((253) 840-6684)
Other/Miscellaneous
Resolved
01/05/2024
cancel per Ryan

Comment Building Div Inspection Not Ready 11/27/2023 11/27/2023 11/27/2023
Shannon King ((253) 840-6684)
Other/Miscellaneous
Resolved
11/27/2023
cancel per Ryan

Building Final Inspection Not Ready 12/28/2023 12/28/2023 12/29/2023
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Resolved
12/29/2023
1. will need to contact inspector of record

Other/Miscellaneous
Resolved
01/05/2024
1. provide fire final approval 2. provide DOH letter of approval 3.provide electrical final approval

Comment Engineering Div Inspection VOID 01/05/2024
Kevin Spruell ((253) 841-5590)
Slab/Insulation Inspection VOID 01/05/2024
Kevin Spruell ((253) 841-5590)
Roof Sheathing Inspection VOID 01/05/2024
Kevin Spruell ((253) 841-5590)
Shear Wall Inspection VOID 01/05/2024
Kevin Spruell ((253) 841-5590)
Firewall/Firestop Inspection VOID 01/05/2024
Kevin Spruell ((253) 841-5590)
Plumbing Rough In Inspection VOID 01/05/2024
Kevin Spruell ((253) 841-5590)
Energy (Insulation) Inspection VOID 01/05/2024
Kevin Spruell ((253) 841-5590)
Ceiling Grid/T-Bar Inspection VOID 01/05/2024
Kevin Spruell ((253) 841-5590)
Exit Lighting Test Inspection VOID 01/05/2024
Kevin Spruell ((253) 841-5590)
Hydronic Piping Inspection VOID 01/05/2024
Kevin Spruell ((253) 841-5590)
Refrigeration Line Test Inspection VOID 01/05/2024
Kevin Spruell ((253) 841-5590)
Exhaust Hood Inspection VOID 01/05/2024
Kevin Spruell ((253) 841-5590)
Light Test For Grease Duct Inspection VOID 01/05/2024
Kevin Spruell ((253) 841-5590)
Exhaust/Vent Fans Inspection VOID 01/05/2024
Kevin Spruell ((253) 841-5590)
Fire Or Smoke Damper Inspection VOID 01/05/2024
Kevin Spruell ((253) 841-5590)
Hydrostatic Test 200Lbs 2Hrs VOID 01/05/2024
Kevin Spruell ((253) 841-5590)
Emergency Radio Test Review Inspection VOID 01/05/2024
Kevin Spruell ((253) 841-5590)
Engineering Final Inspection VOID 01/05/2024
Kevin Spruell ((253) 841-5590)
Fire Final Inspection VOID 01/05/2024
Kevin Spruell ((253) 841-5590)
Combination Frame And Rough In Inspection VOID 01/05/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Outstanding
09/01/2023
1 ; complete framing as per city approved plans. ( inspection of OR7 & OR8 only) 2 ; provide electrical cover approval prior to frame inspection. 3 ; complete nail plates at electrical as discussed with contractor. 4 ; plumbing approved as noted on sheet m3.02 of approved plans (d.w.v. and supply only) 5 ; mechanical approved as noted on sheet m4.02 0f city approved plans.

Frame Inspection VOID 01/05/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Outstanding
10/24/2023
1 ; provide city approved plans and engineering on-site for inspection of hard lids. not ready

Other/Miscellaneous
Outstanding
10/24/2023
1 ; provide engineering on-site for inspection of hard lids in O.R. 7&8. not ready

Other/Miscellaneous
Outstanding
10/24/2023
1 ; provide engineering for hard lid ceiling in O.R 7&8 as discussed with contractor. 2 ; complete framing as per engineering at bracing removed as discussed with contractor. not ready

Wallboard / Drywall Inspection VOID 01/05/2024
Kevin Spruell ((253) 841-5590)
Comment Building Div Inspection VOID 01/05/2024
Kevin Spruell ((253) 841-5590)

Conditions

Condition Status Department Category Expiration Date Due Date
General Permit Conditions Open Building Division Standard Conditions
: * Final approval by the Building Official is required prior to use or occupancy. * Work shall not proceed until the inspector has approved the stages of construction. * Surface storm water shall be diverted from the building site and shall not drain onto adjacent properties. * I hereby acknowledge that I have read this Permit/Application, that the information given is correct; that I am the owner or the duly authorized agent of the owner; that plans submitted herewith are in compliance with all applicable city, county and state laws and that all construction will proceed in accordance with said laws. This permit shall expire if work is not commenced with 180 days or if the work is suspended for a period of 180 days. Permits expire two years from issuance. * By leaving the contractor information section blank, I hereby certify further that contractors (general or subcontractors) will not be hired to perform any work in association with this permit. I also certify that if I do choose to hire a contractor (general or subcontractor) I will only hire those contractors that are licensed by the State of Washington. * TO SCHEDULE INSPECTIONS, CHECK PERMIT STATUS OR TO MAKE PAYMENTS ON THE CITY WEB SITE VISIT https://secure.puyallupwa.gov
Engineering Commercial Standard Conditions Open Engineering Division Standard Conditions
: ** OCCUPANCY WILL NOT BE GRANTED UNTIL CIVIL PLANS FOR THE CONSTRUCTION OF THE SIDEWALK EXTENSION ON THE NORTH SIDE OF 13TH AVE SE HAVE BEEN SUBMITTED TO THE CITY FOR REVIEW AND APPROVAL ** * Any addition/expansion to the foot print of the building including decks and porches not originally shown on the approved set of plans must obtain proper permits prior to construction. * Any code requirement that may have been overlooked in this plan review does not imply that the requirements have been waived.
Building Permit Standard Conditions Open Building Division Standard Conditions
: PERMIT CONDITIONS: 1- COMPLY WITH 2018 IFC AND 2018 IBC 2- EXIT LIGHTING TEST REQUIRED CONTRACTOR TO PROVIDE LIGHT METER 3- A SEPARATE PERMIT MAY BE REQUIRED IF FIRE ALARM OR SRPINKLER SYSTEM IS ALTERED 4- RTU'S WILL BE REQUIRED TO BE TESTED FOR SHUT DOWN. 5- FIRE EXTINGUISHERS REQUIRED PER CODE 6- ALL ABOVE ITEMS TO BE COMPLETED PRIOR TO FIRE FINAL. FIRE FINAL REQUIRED BEFORE BUILDING FINAL INSPECTION REQUEST CODES: 2252 EXIT LIGHT TEST 9200 FIRE BUILDING FINAL SCHEDULE YOUR INSPECTION BY PHONE OR ONLINE THROUGH THE CITY OF PUYALLUP ONLINE PERMIT SYSTEM. THEN CALL MORNING OF INSPECTION BETWEEN 7AM - 8AM TO SET UP A TIME. INSPECTIONS ARE MONDAY - THURSDAY THERE WILL BE NO INSPECTIONS ON FRIDAYS. HTTPS://SECURE.CITYOFPUYALLUP.ORG/ INSPECTION LINE 1-877-232-6456 (USE MUTE TO AVOID BACKGROUND NOISE) DAVID DRAKE AT 253-864-4171 OR RAY COCKERHAM AT 253-841-5585
Pipeline Notfication Rcw 19.122.033 Open Engineering Division Standard Conditions
: Effective January 1, 2013 RCW 19.122 Before conducting any construction or excavation within 100 feet of a right-of-way or utility easement containing a transmission pipeline a person must notify the pipeline companies of the scheduled excavation through the one-number locator service 811. Notification must occur in a window of not less than 2 business days but not more than 10 business days before beginning the excavation. If a transmission pipeline company is notified that excavation work will occur near a pipeline, a representative of the company must consult with the excavator on-site prior to excavation.
Miscellaneous Condition Resolved Development & Permitting Services Prior to Occupancy
: OCCUPANCY WILL NOT BE GRANTED UNTIL CIVIL PLANS FOR THE CONSTRUCTION OF THE SIDEWALK EXTENSION ON THE NORTH SIDE OF 13TH AVE SE HAVE BEEN SUBMITTED TO THE CITY FOR REVIEW AND APPROVAL. However, if PRCTI20221788 is issued first, the condition of B-21-0225 will be: OCCUPANCY WILL NOT BE GRANTED UNTIL THE CONSTRUCTION OF THE SIDEWALK EXTENSION ON THE NORTH SIDE OF 13TH AVE SE HAS BEEN COMPLETED AND A FINAL APPROVAL GIVEN. 05/11/2022 LL 05/11/2022

Related Permit & Planning Applications

There are no related items for this permit application.

Documents & Images

Date Uploaded File Type Name
05/12/2022 Plans b-21-0225 plumbing fixture worksheet.pdf (Stamped)
05/12/2022 Plans b-21-0225 plans.pdf (Stamped)
05/12/2022 Plans b-21-0225 structural calcs.pdf (Stamped)
02/10/2023 Receipt Receipt for transaction: 2023-000213
02/10/2023 Permit Permit - Detailed
05/26/2023 Report Inspection Report (Building Final Inspection)
05/31/2023 Report Inspection Report (Comment Building Div Inspection)
06/27/2023 Report Inspection Report (Combination Frame And Rough In Inspection)
06/30/2023 Report Inspection Report (Wallboard / Drywall Inspection)
07/31/2023 Report Inspection Report (Wallboard / Drywall Inspection)
08/04/2023 Report Inspection Report (Combination Frame And Rough In Inspection)
08/30/2023 Report Inspection Report (Frame Inspection)
09/01/2023 Report Inspection Report (Combination Frame And Rough In Inspection)
09/05/2023 Report Inspection Report (Frame Inspection)
09/07/2023 Report Inspection Report (Frame Inspection)
09/11/2023 Report Inspection Report (Frame Inspection)
09/14/2023 Report Inspection Report (Frame Inspection)
09/28/2023 Report Inspection Report (Frame Inspection)
09/28/2023 Report Inspection Report (Wallboard / Drywall Inspection)
10/24/2023 Report Inspection Report (Frame Inspection)
10/25/2023 Report Inspection Report (Wallboard / Drywall Inspection)
11/22/2023 Report Inspection Report (Comment Building Div Inspection)
11/27/2023 Report Inspection Report (Comment Building Div Inspection)
12/29/2023 Report Inspection Report (Mechanical Final Inspection)
12/29/2023 Report Inspection Report (Plumbing Final Inspection)
12/29/2023 Report Inspection Report (Building Final Inspection)
12/29/2023 Report Inspection Report (Medical Gas Inspection)
01/05/2024 Report Inspection Report (Building Final Inspection)
01/23/2024 Other Certificate of Occupancy


Should you need assistance, please contact the Permit Center at (253) 864-4165 option 1.