CITY OF PUYALLUP PERMITTING PORTAL

Permit Application Status

B-21-0386


In order to request inspections, you need to be signed in.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

B-21-0386
Commercial - Tenant Improvement/Remodel
Closed
CH REALTYIX-JV I PUYALLUP LOGISTICS LP
Alteration/Remodel
TI - NEW OFFICE SPACE MEZZANINE WITHIN EXISTING WAREHOUSE ~ IDI LOGISTICSBLDG ONLY
05/27/2021
08/20/2021
11/20/2022
03/31/2022

Locations

Reviews

Review Type Outcome Est. Completion Date Completed
Engineering Review Approved 08/03/2021
Building Review Approved 08/02/2021
Building Review Incomplete 07/16/2021
Building Review Incomplete 06/23/2021
Planning Review In Progress 06/14/2021
Engineering Review Approved 06/07/2021
Fire Review Approved 06/07/2021

Fees

Paid Fees Amount Paid Owing Date Paid
Building Permit Fee $3,708.75 $3,708.75 Paid 08/20/2021
No
Planning Building Permit Fee $30.00 $30.00 Paid 08/20/2021
No
WA State Building Code Council Fee (Residential) $25.00 $25.00 Paid 08/20/2021
No
Planning Landscape Review Fee $90.00 $90.00 Paid 08/20/2021
No
Building Plan Review Fee $2,410.69 $2,410.69 Paid 08/20/2021
No
Water System Development Charge $7,676.19 $7,676.19 Paid 08/20/2021
No
Building Division Fee (Hourly) $130.00 $130.00 Paid 08/20/2021
No
Legacy Fee $130.00 $130.00 Paid 08/20/2021
No
Fire Review Fee (Commercial Building) $265.00 $265.00 Paid 08/20/2021
No
Sewer System Development Charge $13,224.46 $13,224.46 Paid 08/20/2021
No
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


Permit(s) will not be issued until outstanding fees have been paid in full. Fee details shown above only include currently payable fees, there might be addtional fees to be paid before issuance.

$0.00

Inspections

Inspection Outcome Requested Scheduled Date Inspected
Plumbing Rough In Inspection In Progress 9/15/2021 09/15/2021
Gary Webster ((253) 841-5590)
Frame Inspection In Progress 10/15/2021 10/15/2021
Gary Webster ((253) 841-5590)
Frame Inspection In Progress 10/26/2021 10/26/2021
Gary Webster ((253) 841-5590)
Shear Wall Inspection Comments 10/26/2021 10/26/2021
Gary Webster ((253) 841-5590)
Combination Frame And Rough In Inspection Comments 11/3/2021 11/03/2021
Monty Johnson ((253) 770-3326)
Combination Frame And Rough In Inspection In Progress 11/12/2021 11/12/2021
Gary Webster ((253) 841-5590)
Comment Building Div Inspection Comments 11/12/2021 11/12/2021
Gary Webster ((253) 841-5590)
Combination Frame And Rough In Inspection Not Ready 11/16/2021 11/16/2021
Gary Webster ((253) 841-5590)
Energy (Insulation) Inspection In Progress 11/16/2021 11/16/2021
Gary Webster ((253) 841-5590)
Energy (Insulation) Inspection In Progress 11/18/2021 11/18/2021
Gary Webster ((253) 841-5590)
Wallboard / Drywall Inspection In Progress 11/18/2021 11/18/2021
Gary Webster ((253) 841-5590)
Plumbing Rough In Inspection In Progress 11/23/2021 11/23/2021
Monty Johnson ((253) 770-3326)
Combination Frame And Rough In Inspection Failed 11/23/2021 11/23/2021
Monty Johnson ((253) 770-3326)
Wallboard / Drywall Inspection In Progress 11/23/2021 11/23/2021
Monty Johnson ((253) 770-3326)
Frame Inspection In Progress 11/24/2021 11/24/2021
Monty Johnson ((253) 770-3326)
Mechanical Rough In Inspection In Progress 11/29/2021 11/29/2021
Gary Webster ((253) 841-5590)
Combination Frame And Rough In Inspection In Progress 11/29/2021 11/29/2021
Gary Webster ((253) 841-5590)
Energy (Insulation) Inspection Approved 11/30/2021 11/30/2021
Gary Webster ((253) 841-5590)
Wallboard / Drywall Inspection In Progress 12/3/2021 12/03/2021
Monty Johnson ((253) 770-3326)
Wallboard / Drywall Inspection In Progress 12/07/2021
Shannon King ((253) 840-6684)
Mechanical Rough In Inspection Partial Pass 12/15/2021 12/15/2021 12/15/2021
Monty Johnson ((253) 770-3326)
Mechanical Final Inspection Not Ready 12/20/2021 12/20/2021
Gary Webster ((253) 841-5590)
Ceiling Grid/T-Bar Inspection Failed 1/6/2022 1/6/2022 01/06/2022
Shannon King ((253) 840-6684)
Other/Miscellaneous
Carried Forward
01/06/2022
1 ; provide electrical and fire cover approval prior to ceiling grid inspection. 2 ; complete all mechanical rough-in of duct work and complete install of diffusers with positive connection to main and cross-tee of ceiling grid. 3 ; complete all ceiling grid requirements as per city approved plans prior to inspection - not ready

Ceiling Grid/T-Bar Inspection Failed 1/18/2022 1/18/2022 01/18/2022
Gary Webster ((253) 841-5590)
Other/Miscellaneous
Resolved
01/18/2022
1 ; provide electrical and fire cover approval prior to ceiling grid inspection. 2 ; complete all mechanical rough-in of duct work and complete install of diffusers with positive connection to main and cross-tee of ceiling grid. 3 ; complete all ceiling grid requirements as per city approved plans prior to inspection - not ready

Other/Miscellaneous
Carried Forward
01/18/2022
provide fire & electrical cover approval

Mechanical Final Inspection Failed 1/24/2022 1/24/2022 01/24/2022
Gary Webster ((253) 841-5590)
Other/Miscellaneous
Carried Forward
01/24/2022
provide final for permit shell permit final balance report received

Comment Building Div Inspection VOID 3/30/2022 3/30/2022 03/30/2022
Gary Webster ((253) 841-5590)
Plumbing Final Inspection VOID 05/24/2022
Joyce Kennedy ((253) 841-5405)
Exit Lighting Test Inspection VOID 05/24/2022
Joyce Kennedy ((253) 841-5405)
Carbon Monoxide Detectors Inspection VOID 05/24/2022
Joyce Kennedy ((253) 841-5405)
Combination Frame And Rough In Inspection VOID 05/24/2022
Joyce Kennedy ((253) 841-5405)
Footing/Setback Inspection VOID 05/24/2022
Joyce Kennedy ((253) 841-5405)
Plumbing Rough In Inspection VOID 05/24/2022
Joyce Kennedy ((253) 841-5405)
Shear Wall Inspection VOID 05/24/2022
Joyce Kennedy ((253) 841-5405)
Wallboard / Drywall Inspection VOID 05/24/2022
Joyce Kennedy ((253) 841-5405)
Foundation/Rebar Inspection VOID 05/24/2022
Joyce Kennedy ((253) 841-5405)
Frame Inspection VOID 05/24/2022
Joyce Kennedy ((253) 841-5405)
Ceiling Grid/T-Bar Inspection VOID 05/24/2022
Joyce Kennedy ((253) 841-5405)
Other/Miscellaneous
Outstanding
01/18/2022
1 ; provide electrical and fire cover approval prior to ceiling grid inspection. 2 ; complete all mechanical rough-in of duct work and complete install of diffusers with positive connection to main and cross-tee of ceiling grid. 3 ; complete all ceiling grid requirements as per city approved plans prior to inspection - not ready

Conditions

Condition Status Department Category Expiration Date Due Date
General Permit Conditions Resolved Building Division Standard Conditions
: * Final approval by the Building Official is required prior to use or occupancy. * Work shall not proceed until the inspector has approved the stages of construction. * Surface storm water shall be diverted from the building site and shall not drain onto adjacent properties. * I hereby acknowledge that I have read this Permit/Application, that the information given is correct; that I am the owner or the duly authorized agent of the owner; that plans submitted herewith are in compliance with all applicable city, county and state laws and that all construction will proceed in accordance with said laws. This permit shall expire if work is not commenced with 180 days or if the work is suspended for a period of 180 days. Permits expire two years from issuance. * By leaving the contractor information section blank, I hereby certify further that contractors (general or subcontractors) will not be hired to perform any work in association with this permit. I also certify that if I do choose to hire a contractor (general or subcontractor) I will only hire those contractors that are licensed by the State of Washington. * TO SCHEDULE INSPECTIONS, CHECK PERMIT STATUS OR TO MAKE PAYMENTS ON THE CITY WEB SITE VISIT https://secure.puyallupwa.gov
Engineering Commercial Standard Conditions Resolved Engineering Division Standard Conditions
: ** OCCUPANCY WILL NOT BE GRANTED UNTIL ALL CIVIL WORK ASSOCIATED WITH E-20-0137 IS COMPLETED AND APPROVAL HAS BEEN PROVIDED ** * The builder/owner shall be responsible for keeping the existing right-of-way free of debris and dirt. Any violation of PMC Chapter 21.14 pertaining to clearing, filling and grading, erosion and sediment control, and storm water discharges shall be prosecuted to the fullest extent of the law. * Any addition/expansion to the foot print of the building including decks and porches not originally shown on the approved set of plans must obtain proper permits prior to construction. * Any code requirement that may have been overlooked in this plan review does not imply that the requirements have been waived.
Building Permit Standard Conditions Resolved Building Division Standard Conditions
: PERMIT CONDITIONS: 1- COMPLY WITH 2018 IFC AND 2018 IBC 2- TOTAL COVERAGE REQUIRED IN THE CITY OF PUYALLUP 3- EXIT LIGHTING TEST REQUIRED CONTRACTOR TO PROVIDE LIGHT METER 4- SEPERATE PERMITS REQUIRED FOR FIRE ALARM AND FIRE SPRINKLER 5- RTU'S WILL BE REQUIRED TO BE TESTED FOR SHUT DOWN. 6- FIRE EXTINGUISHERS REQUIRED PER CODE 7- A KNOX BOX IS REQUIRED AT THE FRONT ENTRY ON THE EXTERIOR OF THE BUILDING 8- PIV MUST HAVE A KNOX LOCK OR APPROVED LOCK WITH AN EXTRA KEY PROVIDED IN KNOX BOX 9- EXISTING BUILDINGS WILL NEED TO CONTACT CENTRAL PIERCE FIRE & RESCUE AND UPDATE THE KEY IN THE KNOX BOX 10- ALL ABOVE ITEMS TO BE COMPLETED PRIOR TO FIRE FINAL. FIRE FINAL REQUIRED BEFORE BUILDING FINAL INSPECTION REQUEST CODES: 2252 EXIT LIGHT TEST 9200 FIRE BUILDING FINAL SCHEDULE YOUR INSPECTION BY PHONE OR ONLINE THROUGH THE CITY OF PUYALLUP ONLINE PERMIT SYSTEM. THEN CALL MORNING OF INSPECTION BETWEEN 7AM - 8AM TO SET UP A TIME. INSPECTIONS ARE MONDAY - THURSDAY THERE WILL BE NO INSPECTIONS ON FRIDAYS. HTTPS://SECURE.CITYOFPUYALLUP.ORG/ INSPECTION LINE 1-877-232-6456 (USE MUTE TO AVOID BACKGROUND NOISE) DAVID DRAKE AT 253-864-4171 OR RAY COCKERHAM AT 253-841-5585
Pipeline Notfication Rcw 19.122.033 Resolved Engineering Division Standard Conditions
: Effective January 1, 2013 RCW 19.122 Before conducting any construction or excavation within 100 feet of a right-of-way or utility easement containing a transmission pipeline a person must notify the pipeline companies of the scheduled excavation through the one-number locator service 811. Notification must occur in a window of not less than 2 business days but not more than 10 business days before beginning the excavation. If a transmission pipeline company is notified that excavation work will occur near a pipeline, a representative of the company must consult with the excavator on-site prior to excavation.

Related Permit & Planning Applications

There are no related items for this permit application.

Documents & Images


Should you need assistance, please contact the Permit Center at (253) 864-4165 option 1.