CITY OF PUYALLUP PERMITTING PORTAL

Permit Application Status

E-11-0323


In order to request inspections, you need to be signed in.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

E-11-0323
UNKOWN LEGACY PERMIT TYPE
Closed
BCC PUYALLUP LLC
Other
JOB # 105068003
12/28/2011
12/28/2011
03/26/2012
03/02/2012

Locations

Reviews

Review Type Outcome Est. Completion Date Completed
Engineering Review Approved 03/02/2012
Engineering Traffic Review Approved 12/28/2011
Engineering Review Approved 12/28/2011

Inspections

Inspection Outcome Requested Scheduled Date Inspected
Close All Restoration Complete Inspection Approved 03/02/2012
Marcus Sedlickas ((253) 405-1707)

Conditions

Condition Status Department Category Expiration Date Due Date
General E-Permit For All Permits Resolved Engineering Division Standard Conditions
: JOB DESCRIPTION: TRENCH APPROXIMATELY 100' EAST ALONG 39TH AVE SE AND BORE APPROXIMATELY 60' UNDER ROADWAY TO INSTALL NEW COMMERCIAL ELECTRIC SERVICE.
Private Utility Permit Conditions Resolved Engineering Division Standard Conditions
: *** PERMIT IS REQUIRED TO BE VISIBLE AT JOB SITE *** THIS WORK WILL BE DONE IN COOPERATION OF ALL OTHER UTILITIES (QWEST,COMCAST, ETC..) AND THE SITE GENERAL. CALL EARL VANDERHOOF, CITY INSPECTOR, AT 253-377-2379 TO COORDINATE WORK SCHEDULE. WORK BETWEEN THE HOURS OF 9AM & 3 PM ONLY RCW 19.27 requires the notification to “transmission pipeline companies” of proposed construction within 100’ of a pipeline easement or right-of-way prior to construction activity being permitted 1. CALL 253-841-5577 24hrs PRIOR TO STARTING WORK TO OPEN PERMIT. 2. CALL 253-405-1707 TO NOTIFY INSPECTOR OF SPECIFIC PROJECT SCHEDULING. 3. ADHERE TO APPROVED TRAFFIC CONTROL PLAN. 4. DO NOT PARK VEHICLES ON CITY SIDEWALK. 5. DO NOT OPEN CUT WITHOUT PRIOR APPROVAL. 6. ANY CURB, GUTTER OR SIDEWALK DAMAGED SHALL BE REMOVED AND REPLACED. 7. CALL 253-841-5577 TO CLOSE PERMIT WHEN WORK IS COMPLETE. 8. I hereby acknowledge that I have read and understand the contents of this permit and I hereby state that the information I have supplied is true and correct. The Applicant shall defend, indemnify, and hold the City, its officers, employees and volunteers harmless from any and all claims, injuries, damages, losses or suits including attorney fees, arising out of or in connection with activities or operations performed by the Applicant or on the Applicant's behalf out of issuance of this permit. RCW 19.27 requires the city to provide notification to “transmission pipeline companies” of proposed construction within 100’ of a pipeline easement or right-of-way prior to construction activity being permitted or require consultation between the person proposing the construction activity and the transmission pipeline company as a condition of receiving the permit.

Related Permit & Planning Applications

There are no related items for this permit application.

Documents & Images

No documents are currently available for viewing.


Should you need assistance, please contact the Permit Center at (253) 864-4165 option 1.