CITY OF PUYALLUP PERMITTING PORTAL

Engineering Permit Application Status

E-13-0302


In order to request inspections, you need to be signed in.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

E-13-0302
Utility Service Repair/PRIVATE PROPERTY ONLY
Closed
DEBERRY JAMES & HELENE
Repair
CONNECT FLOOR DRAIN TO SEWER OUTSIDE OF BLDG ~ PIG PALACE ~ WWF
08/09/2013
08/12/2013
10/11/2013
08/15/2013

Locations

Property
0420331121

* Address
902 S MERIDIAN

Reviews

There are no reviews for this permit application, or you are not authorized to view them.

Fees

Paid Fees Amount Paid Owing Date Paid
Sewer Line Repair Inspection Fee (Private) $160.00 $160.00 Paid 08/12/2013
No
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


Permit(s) will not be issued until outstanding fees have been paid in full. Fee details shown above only include currently payable fees, there might be addtional fees to be paid before issuance.

$0.00

Inspections

There are no inspections for this engineering permit application, or you are not authorized to view them.

Conditions

Condition Status Department Category Expiration Date Due Date
Right Of Way Permit Conditions Resolved Engineering Division Standard Conditions
: *** WASHINGTON STATE FAIR IS SEPTEMBER 6 - 22, 2013. *** * THERE WILL BE NO RIGHT-OF-WAY WORK IN THE FAIR RESTRICTED AREA.* 1. I agree to call the the Engineering Inspector at 253-405-1707 prior to starting work. 2. I agree to have the approved permit on site at all times. 3. UTILITY INSPECTIONS ARE REQUIRED PRIOR TO BACKFILLING. 4. No work shall be done in or on the public right of way without a licensed and bonded contractor first obtaining a right of way permit. 5. I agree to keep the existing right of way free of debris and dirt. 6. I agree to call the Utility Notification Center at 1-800-424-5555 before beginning any excavation. Call before you dig, it's the law. 7. I agree to adhere to the approved Traffic Control Plan. 8. I agree to perform all work in accordance with City's Standards. Any curb, gutter or sidewalk broken now or during construction shall be removed and replaced. 9. I hereby acknowledge that I have read and understand the contents of this permit and I hereby state that the information I have supplied is true and correct. The Applicant shall defend, indemnify, and hold the City, its officers, employees and volunteers harmless from any and all claims, injuries, damages, losses or suits including attorney fees, arising out of or in connection with activities or operations performed by the Applicant or on the Applicant's behalf out of issuance of this permit.
Pipeline Notfication Rcw 19.122.033 Resolved Engineering Division Standard Conditions
: Effective January 1, 2013 RCW 19.122 Before conducting any construction or excavation within 100 feet of a right-of-way or utility easement containing a transmission pipeline a person must notify the pipeline companies of the scheduled excavation through the one-number locator service 811. Notification must occur in a window of not less than 2 business days but not more than 10 business days before beginning the excavation. If a transmission pipeline company is notified that excavation work will occur near a pipeline, a representative of the company must consult with the excavator on-site prior to excavation.
Utility Service Repair Standard Condition Open Engineering Division Standard Conditions
: Development Engineering standard utility service repair conditions: Site-specific Conditions: Applicant/Contractor Responsibility: 1. The issued permit is always required to be available at the job site and readily available to all City inspectors. The applicant shall be subject to a triple permit fee for failing to have a valid permit on site. 2. The applicant/contractor shall notify the City 24-48 business hours prior to starting work by requesting an inspection through the CityView portal. Inspections performed during a City of Puyallup business day (Monday - Friday 7:00 am – 3:30 pm) are included in the permit fee. Inspections performed outside of the regular hours are charged to the permit holder at the current City of Puyallup Fee Schedule inspection rate with a three-hour minimum. Prior to scheduling weekend and night work, coordinate with a City Inspector by calling 253-435-3650 at least 48 business hours in advance of work. 3. The applicant/contractor shall notify the City prior to starting work by requesting an erosion and sediment inspection, prior to backfilling, prior to site restoration, immediately after all work and restoration are complete, and when the site is ready for final inspection. The applicant/contractor shall request a final inspection through the CityView portal prior to the permit expiration date. General Conditions: 1. No work is permitted in the public right-of-way without a licensed and bonded contractor first obtaining a City of Puyallup right-of-way permit. The permit holder is responsible to keep the existing right-of-way free of debris, dirt, and traffic obstructions. 2. Call the utility notification center at 1-800-424-5555 before beginning any excavation. Call before you dig, it's the law. 3. Comply with all permit conditions and the Traffic Control Plans (TCP) issued by the City. Follow the allowed work hours as listed on the issued permit or on each page of the TCP. 4. If a travel lane will be closed, the applicant/contractor shall call the Communications Center at 253-287-4456 prior to starting work on day of closure and again once the lane is reopened. 5. Request all inspections through the CityView portal on the City website. Prior to scheduling weekend and night work, coordinate with a City Inspector by calling 253-435-3650 at least 48 business hours in advance of work. 6. Do not park vehicles on City sidewalk. Any public curb, gutter, or sidewalk broken now or during construction shall be removed and replaced per City Standards. Indemnification / Hold Harmless: The Permittee shall defend, indemnify and hold the Public Entity, its officers, officials, employees and volunteers harmless from any and all claims, injuries, damages, losses or suits including attorney fees, arising out of or in connection with activities or operations performed by the Permittee or on the Permittee's behalf out of issuance of this Permit, except for injuries and damages caused by the sole negligence of the Public Entity. However, should a court of competent jurisdiction determine that RCW 4.24.115 applies to this Permit, then the Permittee agrees to defend, indemnify and hold the Public Entity, its officers, officials, employees and volunteers harmless to the maximum extent permitted thereunder. It is further specifically and expressly understood that the indemnification provided herein constitutes the Permittee's waiver of immunity under Industrial Insurance, Title 51 RCW, solely for the purposes of this indemnification. This waiver has been mutually negotiated by the parties. The provisions of this section shall survive the expiration or termination of this Agreement.

Related Permit & Planning Applications

There are no related items for this engineering permit application.

Documents & Images

No documents are currently available for viewing.


Should you need assistance, please contact the Permit Center at (253) 864-4165 option 1.