Summary

E-14-0239
UNKOWN LEGACY PERMIT TYPE
Closed
LARSON FAMILY PARTNERSHIP
Other
JOB # 109083840 30 day extension expires on 9/18/2014 LL
06/19/2014
06/20/2014
10/17/2014
04/16/2015

Locations

Reviews

Review Type Outcome Est. Completion Date Completed
Engineering Review Approved 04/16/2015
Engineering Traffic Review Approved 06/20/2014
Engineering Review Approved 06/20/2014

Inspections

Inspection Outcome Requested Scheduled Date Inspected
Close All Restoration Complete Inspection Approved 04/14/2015
Linda Lian ((253) 841-5577)

Conditions

Condition Status Department Category Expiration Date Due Date
General E-Permit For All Permits Resolved Engineering Division Standard Conditions
: JOB DESCRIPTION: Replace 3/4" STW commercial gas service with 1 1/4" PE. New service is to run off of 4th St NW, also retire existing service on River Rd.
Private Utility Permit Conditions Resolved Engineering Division Standard Conditions
: *** PERMIT IS REQUIRED TO BE VISIBLE AT JOB SITE *** MEEKER DAYS IS JUNE 20 - 21, 2014 THERE WILL BE NO RIGHT OF WORK IN THE DOWNTOWN CORE AREA Work between the hours of 9am and 3pm only. Please note location change for sidewalk closure signs on River Rd. If you have questions concerning placement call Linda Lian at 253-841-5577 Sidewalk to remain open on 4th St NW per the approved TCP Call Comm Center day of closure at 253-841-5431 Maintain 11' lane of travel 1. CALL 253-841-5577 24hrs PRIOR TO STARTING WORK TO OPEN PERMIT. 2. CALL 253-405-1707 TO NOTIFY INSPECTOR OF SPECIFIC PROJECT SCHEDULING. 3. ADHERE TO APPROVED TRAFFIC CONTROL PLAN. 4. DO NOT PARK VEHICLES ON CITY SIDEWALK. 5. DO NOT OPEN CUT WITHOUT PRIOR APPROVAL. 6. ANY CURB, GUTTER OR SIDEWALK DAMAGED SHALL BE REMOVED AND REPLACED. 7. CALL 253-841-5577 TO CLOSE PERMIT WHEN WORK IS COMPLETE. 8. RCW 19.122 requires all owners of underground facilities to notify pipeline companies of scheduled excavations through the one-number locator service if proposed excavation is within 100 feet. Notification must occur in a window of not less than 2 business days but not more than 10 business days before beginning the excavation. If a transmission pipeline company is notified that excavation work will occur near a pipeline, a representative of the company must consult with the excavator on-site prior to excavation. 9. I hereby acknowledge that I have read and understand the contents of this permit and I hereby state that the information I have supplied is true and correct. 10. The Applicant shall defend, indemnify, and hold the City, its officers, employees and volunteers harmless from any and all claims, injuries, damages, losses or suits including attorney fees, arising out of or in connection with activities or operations performed by the Applicant or on the Applicant's behalf out of issuance of this permit.

Related Permit & Planning Applications

There are no related items for this permit application.

Documents & Images

No documents are currently available for viewing.


Should you need assistance, please contact the Permit Center at (253) 864-4165 option 1.