Summary

E-18-0571
Franchise Utility Permit
Closed
PUY SEVENTH-DAY ADVEN SC
Other
JOB # 887035275 Extended to 4/12/19 rh Extended through 6/20/19 rh (PAVING EXPECTED)
12/12/2018
01/02/2019
07/16/2019
05/17/2019

Locations

Reviews

Review Type Outcome Est. Completion Date Completed
Engineering Review Approved 05/17/2019
Engineering Review Approved 12/14/2018
Engineering Traffic Review Approved 12/14/2018

Fees

Paid Fees Amount Paid Owing Date Paid
Franchise Traffic Control Fee $90.00 $90.00 Paid 01/09/2019
No
ROW Permit Fee $80.00 $80.00 Paid 01/09/2019
No
Franchise Utility Review Fee $110.00 $110.00 Paid 01/09/2019
No
Legacy Fee $110.00 $110.00 Paid 01/09/2019
No
E Franchise ROW Inspection Fee $130.00 $130.00 Paid 01/09/2019
No
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


Permit(s) will not be issued until outstanding fees have been paid in full. Fee details shown above only include currently payable fees, there might be addtional fees to be paid before issuance.

$0.00

Inspections

Inspection Outcome Requested Scheduled Date Inspected
Close All Restoration Complete Inspection Approved 05/17/2019
Jason Little ((253) 244-0387)

Conditions

Condition Status Department Category Expiration Date Due Date
General E-Permit For All Permits Resolved Engineering Division Standard Conditions
: JOB DESCRIPTION:
Private Utility Permit Conditions Resolved Engineering Division Standard Conditions
: Follow approved Traffic Control Plan (TCP) Work between the hours of 10am-3pm on Mondays and 9am-3pm Tuesday through Friday to avoid school bus schedules. Call Comm Center day(s) of lane closure at 253-841-5431 A. Distance between cones equals speed limit in unit feet. B. Taper length equals width of offset times speed limit squared divided by 60. L = WS² /60 - W= lane width S = speed limit C. Sign spacing shall be 100 feet when speed limit is 30 MPH or less D. Sign spacing shall be 350 feet when speed limit is greater than 30 MPH E. Distance between signs is mandatory unless field conditions determine otherwise. 1. PERMIT IS REQUIRED TO BE VISIBLE AT JOB SITE. 2. Call 253-841-5577 24hrs PRIOR to starting work to open the permit. 3. Call 253-405-1707 to notify the inspector of specific project scheduling. 4. Adhere to the approved traffic control plan. 5. DO NOT open cut without prior approval. 6. DO NOT park vehicles on city sidewalk. Curb, gutter or sidewalk damaged shall be replaced. 7. Call 253-841-5577 to closse the permit when work is complete. 8. RCW 19.122 requires all owners of underground facilities to notify pipeline companies of scheduled excavations through the one-number locator service if proposed excavation is within 100 feet. Notification must occur in a window of not less than 2 business days but not more than 10 business days before beginning the excavation. If a transmission pipeline company is notified that excavation work will occur near a pipeline, a representative of the company must consult with the excavator on-site prior to excavation. 9. I hereby acknowledge that I have read and understand the contents of this permit and I hereby state that the information I have supplied is true and correct. 10. The Applicant shall defend, indemnify, and hold the City, its officers, employees and volunteers harmless from any and all claims, injuries, damages, losses or suits including attorney fees, arising out of or in connection with activities or operations performed by the Applicant or on the Applicant's behalf out of issuance of this permit.

Related Permit & Planning Applications

There are no related items for this engineering permit application.

Documents & Images

No documents are currently available for viewing.


Should you need assistance, please contact the Permit Center at (253) 864-4165 option 1.