E-19-0544
Franchise Utility Permit
Closed
BCC PUYALLUP LLC
Other
JOB #N.636651
12/09/2019
01/30/2020
06/12/2021
04/13/2021

Locations

Reviews

There are no reviews for this permit application, or you are not authorized to view them.

Fees

Paid Fees Amount Paid Owing Date Paid
ROW Permit Fee $80.00 $80.00 Paid 12/12/2019
No
Franchise Utility Review Fee $110.00 $110.00 Paid 12/12/2019
No
Franchise Traffic Control Fee $90.00 $90.00 Paid 12/12/2019
No
Legacy Fee $110.00 $110.00 Paid 12/12/2019
No
E Franchise ROW Inspection Fee $130.00 $130.00 Paid 12/12/2019
No
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


Permit(s) will not be issued until outstanding fees have been paid in full. Fee details shown above only include currently payable fees, there might be addtional fees to be paid before issuance.

$0.00

Inspections

Inspection Outcome Requested Scheduled Date Inspected
Close All Restoration Complete Inspection Approved 04/13/2021
Cheryl Trimble ((253) 841-5464)

Conditions

Condition Status Department Category Expiration Date Due Date
General E-Permit For All Permits Resolved Engineering Division Standard Conditions
: JOB DESCRIPTION:
Private Utility Permit Conditions Resolved Engineering Division Standard Conditions
: *****PLEASE READ NEW PERMIT CONDITIONS***** ***SITE SPECIFIC CONDITIONS***: (This may include night work, coordination with inspector prior to work start, school zone restrictions, etc.) Closure allowed Monday- Thursday 10A.M. - 2P.M. Call communitcaiton center at 253-841-5431 on day of closure Shift traffic before the intersection of 23rd Ave SE and Wildwood Park Dr Flaggers must stay in radio contact 11' wide traffic lanes in both directions on Wildwood Park Drive and 27th Ave SE must be maintained at all times GENERAL CONDITIONS: 1. PERMIT AND APPROVED TRAFFIC CONTROL PLAN ARE REQUIRED TO BE AVAILABLE AT JOB SITE. NO PERMIT AT SITE SHALL BE SUBJECT TO TRIPLE PERMIT FEE. 2. Applicant/contractor shall notify the City within 5 days prior to work start date and also to close the permit when all work and restoration are complete and ready for final inspection. Go to: https://secure.cityofpuyallup.org/ and click on inspection requests to open the permit and schedule the inspection. Please select from the following codes: 6950 - PERMIT START 6955 - CLOSE ALL RESTORATION COMPLETE In lieu of online access, call the Inspection Request line at 1-877-232-6456. 3. Follow approved Traffic Control Plan (TCP) 4. Follow allowed work hours (example) Monday through Friday 9am-3pm 5. If a lane will be closed, call Comm Center at least 24 hours prior to closure at 253-841-5431. 6. Spotter must be available to assist with pedestrians if needed. 7. To schedule inspection, go to: Secure.cityofpuyallup.org and select appropriate code. 8. Please utilize traffic control information below for TCP: A. Distance between cones equals speed limit in unit feet. B. Taper length equals width of offset times speed limit squared divided by 60. L = WS² /60 - W= lane width S = speed limit C. Sign spacing shall be 100 feet when speed limit is 30 MPH or less D. Sign spacing shall be 350 feet when speed limit is greater than 30 MPH E. Distance between signs is mandatory unless field conditions determine otherwise. 9. DO NOT open cut without prior approval. 10. DO NOT park vehicles on city sidewalk. Curb, gutter or sidewalk damaged shall be replaced. 11. The Applicant shall defend, indemnify, and hold the City, its officers, employees and volunteers harmless from any and all claims, injuries, damages, losses or suits including attorney fees, arising out of or in connection with activities or operations performed by the Applicant or on the Applicant's behalf out of issuance of this
General E-Permit For All Permits Resolved Engineering Division Standard Conditions
: NO WORK ALLOWED IN THE RIGHT OF WAY AS DEFINED BY THE "CONSTRUCTION RESTRICTION ZONE & ROUTES MAP" DURING THE FAIR - August 30 - September 22, 2019

Related Permit & Planning Applications

There are no related items for this engineering permit application.

Documents & Images

No documents are currently available for viewing.


Should you need assistance, please contact the Permit Center at (253) 864-4165 option 1.