*****PLEASE READ NEW PERMIT CONDITIONS*****
***SITE SPECIFIC CONDITIONS***
(This may include night work, coordination with inspector prior to work start, school zone restrictions, etc.)
NIGHT WORK REQUIRED.
CLOSURE ALLOWED:
Sunday - Thursday
9PM - 5AM
Call communications center at 253-841-5431 on day of closure.
The applicant shall notify all residents and businesses within 300 feet of the work area 48 hours in advance of work commencement. The notification shall include the duration of the project, the location of work, and any traffic impacts, and the notification shall be distributed on informational door hangers, displayed on message boards, or on signs posted visibly along the right-of-way.
The new, proposed handhole shall be located at back of sidewalk at the base of pole within the 11.5' public utility easement. The new handhole shall not be located in the existing sidewalk. The new handhole shall not interfere with the existing water meter or service adjacent to the pole.
The applicant shall schedule an inspection with a City Engineering Inspector by calling 253-435-3650 at least 48 hours in advance of work commencement.
The applicant shall contact Tamara Ferrin, Puyallup Police Department Support Specialist, at 253-841-5436 or tame@puyallupwa.gov to coordinate traffic support with a uniformed police officer at least 24 hours in advance of work commencement.
The applicant shall notify public transportation agencies whose routes or stops are affected by the traffic control plan 24 hours in advance of work commencement.
Work shall cease in the work zone for a flagger/spotter to escort pedestrians around the work area.
Inspection time performed during a regular 8 hour day Monday - Friday 7:00 am - 5:00 pm is included in the permit fee. Inspection time performed outside of those hours are charged to the permit holder at a rate of $130 per hour with a three hour minimum.
GENERAL CONDITIONS:
1. PERMIT AND APPROVED TRAFFIC CONTROL PLAN ARE REQUIRED TO BE AVAILABLE AT JOB SITE. NO PERMIT AT SITE SHALL BE SUBJECT TO TRIPLE PERMIT FEE.
2. Applicant/contractor shall notify the City within 48 hours prior to work start date and also to close the permit when all work and restoration are complete and ready for final inspection.
Go to: https://secure.cityofpuyallup.org/ and click on inspection requests to open the permit and schedule the inspection. Please select from the following codes:
6950 - PERMIT START
6955 - CLOSE ALL RESTORATION COMPLETE
In lieu of online access, call the Inspection Request line at 1-877-232-6456.
Civil Engineers Inspection Line (message line only): 253-435-3650- use this to cancel a job start, postpone a job or for questions regarding your permit
3. Follow approved Traffic Control Plan (TCP)
4. Follow allowed work hours as seen above.
5. If a lane will be closed, call Comm Center at least 24 hours prior to closure at 253-841-5431.
6. Spotter must be available to assist with pedestrians if needed.
7. To schedule inspection, go to: Secure.cityofpuyallup.org and select appropriate code.
8. Please utilize traffic control information below for TCP:
A. Distance between cones equals speed limit in unit feet.
B. Taper length equals width of offset times speed limit squared divided by 60.
L = WS² /60 - W= lane width S = speed limit
C. Sign spacing shall be 100 feet when speed limit is 30 MPH or less
D. Sign spacing shall be 350 feet when speed limit is greater than 30 MPH
E. Distance between signs is mandatory unless field conditions determine otherwise.
9. DO NOT open cut without prior approval.
10. DO NOT park vehicles on city sidewalk. Curb, gutter or sidewalk damaged shall be replaced.
Indemnification / Hold Harmless
The Permittee shall defend, indemnify and hold the Public Entity, its officers, officials, employees and volunteers harmless from any and all claims, injuries, damages, losses or suits including attorney fees, arising out of or in connection with activities or operations performed by the Permittee or on the Permittee's behalf out of issuance of this Permit, except for injuries and damages caused by the sole negligence of the Public Entity.
However, should a court of competent jurisdiction determine that RCW 4.24.115 applies to this Permit, then the Permittee agrees to defend, indemnify and hold the Public Entity, its officers, officials, employees and volunteers harmless to the maximum extent permitted thereunder. It is further specifically and expressly understood that the indemnification provided herein constitutes the Permittee's waiver of immunity under Industrial Insurance, Title 51 RCW, solely for the purposes of this indemnification. This waiver has been mutually negotiated by the parties. The provisions of this section shall survive the expiration or termination of this Agreement.
|