CITY OF PUYALLUP PERMITTING PORTAL
Permit Application Status
PRCTI20210038
Paid Fees | Amount | Paid | Owing | Date Paid |
---|---|---|---|---|
Fire Review Fee (Commercial Building) | $265.00 | $265.00 | Paid | 01/19/2022 |
Building Permit Fee | $391.25 | $391.25 | Paid | 01/19/2022 |
Building Plan Review Fee | $254.31 | $254.31 | Paid | 12/16/2021 |
WA State Building Code Council Fee (Commercial) | $25.00 | $25.00 | Paid | 01/19/2022 |
Outstanding Fees | Amount | Paid | Owing | Date Paid |
No outstanding fees. | ||||
Totals: | $935.56 | $935.56 | $0.00 |
Permit(s) will not be issued until outstanding fees have been paid in full. Fee details shown above only include currently payable fees, there might be addtional fees to be paid before issuance.
$0.00
Inspection | Outcome | Requested | Scheduled | Date Inspected |
---|---|---|---|---|
Building Final Inspection | Passed | 8/24/2023 | 8/24/2023 | 08/24/2023 |
Monty Johnson ((253) 770-3326) | ||||
Comment Building Div Inspection | VOID | 08/24/2023 | ||
Monty Johnson ((253) 770-3326) | ||||
Comment Engineering Div Inspection | VOID | 08/24/2023 | ||
Monty Johnson ((253) 770-3326) | ||||
Footing/Setback Inspection | VOID | 08/24/2023 | ||
Monty Johnson ((253) 770-3326) | ||||
Foundation/Rebar Inspection | VOID | 08/24/2023 | ||
Monty Johnson ((253) 770-3326) | ||||
Slab/Insulation Inspection | VOID | 08/24/2023 | ||
Monty Johnson ((253) 770-3326) | ||||
Roof Sheathing Inspection | VOID | 08/24/2023 | ||
Monty Johnson ((253) 770-3326) | ||||
Shear Wall Inspection | VOID | 08/24/2023 | ||
Monty Johnson ((253) 770-3326) | ||||
Firewall/Firestop Inspection | VOID | 08/24/2023 | ||
Monty Johnson ((253) 770-3326) | ||||
Energy (Insulation) Inspection | VOID | 08/24/2023 | ||
Monty Johnson ((253) 770-3326) | ||||
Frame Inspection | VOID | 08/24/2023 | ||
Monty Johnson ((253) 770-3326) | ||||
Combination Frame And Rough In Inspection | VOID | 08/24/2023 | ||
Monty Johnson ((253) 770-3326) | ||||
Wallboard / Drywall Inspection | VOID | 08/24/2023 | ||
Monty Johnson ((253) 770-3326) | ||||
Ceiling Grid/T-Bar Inspection | VOID | 08/24/2023 | ||
Monty Johnson ((253) 770-3326) | ||||
Exit Lighting Test Inspection | VOID | 08/24/2023 | ||
Monty Johnson ((253) 770-3326) | ||||
Hydronic Piping Inspection | VOID | 08/24/2023 | ||
Monty Johnson ((253) 770-3326) | ||||
Refrigeration Line Test Inspection | VOID | 08/24/2023 | ||
Monty Johnson ((253) 770-3326) | ||||
Exhaust Hood Inspection | VOID | 08/24/2023 | ||
Monty Johnson ((253) 770-3326) | ||||
Light Test For Grease Duct Inspection | VOID | 08/24/2023 | ||
Monty Johnson ((253) 770-3326) | ||||
Exhaust/Vent Fans Inspection | VOID | 08/24/2023 | ||
Monty Johnson ((253) 770-3326) | ||||
Medical Gas Inspection | VOID | 08/24/2023 | ||
Monty Johnson ((253) 770-3326) | ||||
Fire Or Smoke Damper Inspection | VOID | 08/24/2023 | ||
Monty Johnson ((253) 770-3326) | ||||
Cover Inspection/Thrust Blocks Inspection | VOID | 08/24/2023 | ||
Monty Johnson ((253) 770-3326) | ||||
Hydrostatic Test 200Lbs 2Hrs | VOID | 08/24/2023 | ||
Monty Johnson ((253) 770-3326) | ||||
Emergency Radio Test Review Inspection | VOID | 08/24/2023 | ||
Monty Johnson ((253) 770-3326) | ||||
Engineering Final Inspection | VOID | 08/24/2023 | ||
Monty Johnson ((253) 770-3326) | ||||
Fire Final Inspection | VOID | 08/24/2023 | ||
Monty Johnson ((253) 770-3326) |
Condition | Status | Category |
---|---|---|
Building Permit Standard Conditions | Open | Standard Conditions |
* Final approval by the Building Official is required prior to use or occupancy.* Work shall not proceed until the inspector has approved the stages of construction.* Surface storm water shall be diverted from the building site and shall not drain onto adjacent properties.* I hereby acknowledge that I have read this Permit/Application, that the information given is correct; that I am the owner or the duly authorized agent of the owner; that plans submitted herewith are in compliance with all applicable city, county and state laws and that all construction will proceed in accordance with said laws. This permit shall expire if work is not commenced with 180 days or if the work is suspended for a period of 180 days. Permits expire two years from issuance. * By leaving the contractor information section blank, I hereby certify further that contractors (general or subcontractors) will not be hired to perform any work in association with this permit. I also certify that if I do choose to hire a contractor (general or subcontractor) I will only hire those contractors that are licensed by the State of Washington. If you are a property owner, contractor or permittee and you are paying for someone to perform the work, they must have a valid contractor registration and the person(s) installing plumbing inside a structure must meet the plumbing certification requirements. If you have any questions regarding these regulations, you may contact the Washington State Department of Labor and Industries or you can find more information on-line at: http://www.lni.wa.gov/TradesLicensing/Contractors/HireCon/default.asp
|
||
Fire Review Conditions | Open | Standard Conditions |
1. INSTALL ADDRESS NUMBERS PER THE FOLLOWING DISTANCES:0-50FOOT SETBACK FROM STREET NUMBERS SHALL BE 6 INCHES IN HEIGHT; 51-100 FEET 12 INCHES IN HEIGHT. ALL NUMBERS SHALL CONTRAST WITH THEIR BACKGROUND. ADDITIONAL NUMBERS MAY BE NEEDED AT DRIVEWAY ENTRANCE IF BUILDING NUMBERS ARE NOT VISIBLE FROM THE STREET. REAR DOORS OF SUITES OR UNITS SHALL ALSO BE LABELED WITH MINIMUM 4 INCH NUMBERS.
2. FIRE HYDRANTS REQUIRED FOR CONSTRUCTION AND FIRE DEPARTMENT ACCESS SHALL BE INSTALLED AND APPROVED BY THE FIRE CODE OFFICIAL PRIOR TO THE STORAGE OR INSTALLATION OF ANY COMBUSTIBLE FRAMING MATERIAL. ACCESS ROADWAY SURFACES SHALL BE DESIGNED TO CITY STANDARDS AND BE DESIGNED TO MAINTAIN THE IMPOSED LOADS OF A 80,000 POUND FIRE APPARATUS. ASPHALT TREATED BASE, ASPHALT OR CONCRETE PAVEMENT CAN BE USED TO PROVIDE THE REQUIRED ALL-WEATHER DRIVING SURFACE.
3. ANY REQUIRED FIRE LANE MARKINGS SHALL BE INSTALLED PRIOR TO FINAL INSPECTION AND PER CITY ORDINANCE.
4. KNOX BOXES, WHEN REQUIRED, SHALL BE INSTALLED USUALLY TO THE RIGHT OF THE MAIN FRONT DOOR AND NO HIGHER THAN 6 FEET OFF OF THE GROUND. ONLY HINGED KNOX BOXES SHALL BE USED. KNOX BOXES AND KEY SWITCHES CAN BE ORDERED ONLINE AT THE "KNOX COMPANY"
5. FIRE EXTINGUISHERS WILL BE REQUIRED PER CHAPTER 9 OF THE INTERNATIONAL FIRE CODE. GENERALLY, 1 FIRE EXTINGUISHER WITH A MINIMUM RATING OF 2A 10BC SHALL BE INSTALLED PER EVERY 3,000 SQUARE FEET OF FLOOR AREA. THE LOCATION OF THE FIRE EXTINGUISHERS SHALL BE NEAR THE EXIT DOORS AND TRAVEL DISTANCE TO AN EXTINGUISHER SHALL NOT EXCEED 75 FEET. ADDITIONAL SIGNAGE MAY BE NECESSARY TO INDICATE THE FIRE EXTINGUISHER LOCATION.
|
||
Engineering Commercial Standard Conditions | Open | Standard Conditions |
Development & Permitting Services
* Prior to STARTING site work; request inspection for Erosion and Sediment
** SEDIMENT CONTROL AND EROSION PROCEDURES SHALL BE PRACTICE TO ELIMINATE AND PREVENT OFF SITE DAMAGE. STORMWATER RUNOFF ORIGINATING UPGRADE OF EXPOSED AREAS SHALL BE CONTROLLED TO REDUCE EROSION AND SEDIMENT LOSS DURING THE PERIOD OF EXPOSURE.
* The applicant is responsible to call the Utility Notification Center at 1-800-424-5555 before beginning any excavation. Call before you dig, it's the law.
* Any code requirement that may have been overlooked in this plan review does not imply that the requirements have been waived.
* By leaving the contractor information section blank, I hereby certify further that contractors (general or subcontractors) will not be hired to perform any work in association with this permit. I also certify that if I do choose to hire a contractor (general or subcontractor) I will only hire those contractors that are licensed by the State of Washington.
Effective January 1, 2013 RCW 19.122 Before conducting any construction or excavation within 100 feet of a right of way or utility easement containing a transmission pipeline a person must notify the pipeline companies of the scheduled excavation through the one number locator service 811. Notification must occur in a window of not less than 2 business days but not more than 10 business days before beginning the excavation. If a transmission pipeline company is notified that excavation work will occur near a pipeline, a representative of the company must consult with the excavator on site prior to excavation.
|
There are no related items for this permit application.
Date Uploaded | File Type | Name |
---|---|---|
12/16/2021 | Receipt | Receipt for transaction:2021-000029 |
01/19/2022 | Receipt | Receipt for transaction:2022-000087 |
02/06/2022 | Plans | Construction Drawings (Stamped) |
02/06/2022 | Plans | Mount Analysis (Stamped) |
02/06/2022 | Report | Structural Analysis (Stamped) |
02/07/2022 | Permit | Permit - Detailed |
02/07/2022 | Letter | Permit Job Card |
07/08/2022 | Letter | Permit Expiration Notice |
01/11/2023 | Letter | Permit Expiration Notice |
07/05/2023 | Letter | Permit Expiration Notice |
08/24/2023 | Report | Inspection Report (Building Final Inspection) |
Should you need assistance, please contact the Permit Center at (253) 864-4165 option 1.