CITY OF PUYALLUP PERMITTING PORTAL
Permit Application Status
PRCTI20230247
Paid Fees | Amount | Paid | Owing | Date Paid |
---|---|---|---|---|
Fire Review Fee (Commercial Building) | $265.00 | $265.00 | Paid | 08/04/2023 |
Building Permit Fee | $1,553.75 | $1,553.75 | Paid | 08/04/2023 |
Mechanical Permit Fee | $40.00 | $40.00 | Paid | 08/04/2023 |
Plumbing Permit Fee | $40.00 | $40.00 | Paid | 08/04/2023 |
Building Plan Review Fee | $1,009.94 | $1,009.94 | Paid | 03/07/2023 |
Mechanical Plan Review Fee | $59.93 | $59.93 | Paid | 03/07/2023 |
Plumbing Plan Review Fee | $26.00 | $26.00 | Paid | 03/07/2023 |
WA State Building Code Council Fee (Commercial) | $25.00 | $25.00 | Paid | 08/04/2023 |
Exhaust Vent Fan (Bath) Fee | $28.20 | $28.20 | Paid | 08/04/2023 |
Mechanical Duct Work Fee | $24.00 | $24.00 | Paid | 08/04/2023 |
Resubmittal Fee | $180.00 | $180.00 | Paid | 07/17/2023 |
Resubmittal Fee | $180.00 | $180.00 | Paid | 12/03/2023 |
Building Re-Inspection Fee | $180.00 | $180.00 | Paid | 12/03/2023 |
Inspection Fee - Outside Of Business Hours | $360.00 | $360.00 | Paid | 01/18/2024 |
Building Re-Inspection Fee | $180.00 | $180.00 | Paid | 01/26/2024 |
Building Inspection Fee | $360.00 | $360.00 | Paid | 01/26/2024 |
Building Division Fee (Hourly) | $180.00 | $180.00 | Paid | 01/29/2024 |
Outstanding Fees | Amount | Paid | Owing | Date Paid |
No outstanding fees. | ||||
Totals: | $4,691.82 | $4,691.82 | $0.00 |
Permit(s) will not be issued until outstanding fees have been paid in full. Fee details shown above only include currently payable fees, there might be addtional fees to be paid before issuance.
$0.00
Inspection | Outcome | Requested | Scheduled | Date Inspected |
---|---|---|---|---|
Footing/Setback Inspection | Not Ready | 10/3/2023 | 10/3/2023 | 10/04/2023 |
Kevin Spruell ((253) 841-5590) | ||||
Corrections:
Other/Miscellaneous
Resolved
02/05/2024
1. cancelled on site by contractor
|
||||
Plumbing Rough In Inspection | Partial Pass | 10/3/2023 | 10/3/2023 | 10/04/2023 |
Kevin Spruell ((253) 841-5590) | ||||
Corrections:
Other/Miscellaneous
Resolved
02/05/2024
1. no lines or floor drains installed at time of inspection that go in to grease interceptor
2.provide AS-built approval of under ground plumbing from EOR at time of slab inspection
3. DWV under slab approved pending as-built approval from EOR
|
||||
Plumbing Rough In Inspection | Failed | 10/13/2023 | 10/13/2023 | 10/13/2023 |
Monty Johnson ((253) 770-3326) | ||||
Corrections:
Other/Miscellaneous
Resolved
02/05/2024
1. no lines or floor drains installed at time of inspection that go in to grease interceptor
2.provide AS-built approval of under ground plumbing from EOR at time of slab inspection
3. DWV under slab approved pending as-built approval from EOR
|
||||
Other/Miscellaneous
Resolved
02/05/2024
provide 10 ft head test. have engineering dept approval on interceptor
|
||||
Foundation/Rebar Inspection | Partial Pass | 10/17/2023 | 10/17/2023 | 10/17/2023 |
Kevin Spruell ((253) 841-5590) | ||||
Corrections:
Other/Miscellaneous
Resolved
02/05/2024
1. bar at footing approved pending letter from EOR not requiring special inspection
2. complete vapor barrier at slab infill's as discussed with contractor
|
||||
Plumbing Rough In Inspection | Partial Pass | 10/17/2023 | 10/17/2023 | 10/17/2023 |
Kevin Spruell ((253) 841-5590) | ||||
Corrections:
Other/Miscellaneous
Resolved
02/05/2024
1. no lines or floor drains installed at time of inspection that go in to grease interceptor
2.provide AS-built approval of under ground plumbing from EOR at time of slab inspection
3. DWV under slab approved pending as-built approval from EOR
|
||||
Other/Miscellaneous
Resolved
02/05/2024
1. trench drains under slab approved inside building
2. provide approval from engineering for outside the building
|
||||
Footing/Setback Inspection | Partial Pass | 10/20/2023 | 10/20/2023 | 10/20/2023 |
Monty Johnson ((253) 770-3326) | ||||
Corrections:
Other/Miscellaneous
Resolved
02/05/2024
1. cancelled on site by contractor
|
||||
Other/Miscellaneous
Resolved
02/05/2024
thickened edge footing south wall ok
|
||||
Foundation/Rebar Inspection | Not Ready | 10/20/2023 | 10/20/2023 | 10/20/2023 |
Monty Johnson ((253) 770-3326) | ||||
Corrections:
Other/Miscellaneous
Resolved
02/05/2024
1. bar at footing approved pending letter from EOR not requiring special inspection
2. complete vapor barrier at slab infill's as discussed with contractor
|
||||
Comment Engineering Div Inspection | Partial Pass | 10/30/2023 | 10/30/2023 | |
Jeff Hill ((253) 204-5633) | ||||
Combination Frame And Rough In Inspection | Not Ready | 10/30/2023 | 10/30/2023 | 10/30/2023 |
Kevin Spruell ((253) 841-5590) | ||||
Foundation/Rebar Inspection | Not Ready | 10/30/2023 | 10/30/2023 | 10/30/2023 |
Kevin Spruell ((253) 841-5590) | ||||
Corrections:
Other/Miscellaneous
Resolved
02/05/2024
1. bar at footing approved pending letter from EOR not requiring special inspection
2. complete vapor barrier at slab infill's as discussed with contractor
|
||||
Frame Inspection | Not Ready | 10/31/2023 | 10/31/2023 | 11/01/2023 |
Kevin Spruell ((253) 841-5590) | ||||
Corrections:
Other/Miscellaneous
Resolved
02/05/2024
1.provide attachment details for demising wall as discussed with contractor
2. complete all framing requirements as discussed with contractor prior to next inspection
3.not ready
|
||||
Plumbing Rough In Inspection | Not Ready | 11/8/2023 | 11/8/2023 | 11/08/2023 |
Kevin Spruell ((253) 841-5590) | ||||
Corrections:
Other/Miscellaneous
Resolved
02/05/2024
1. no lines or floor drains installed at time of inspection that go in to grease interceptor
2.provide AS-built approval of under ground plumbing from EOR at time of slab inspection
3. DWV under slab approved pending as-built approval from EOR
|
||||
Other/Miscellaneous
Resolved
02/05/2024
1. trench drains under slab approved inside building
2. provide approval from engineering for outside the building
|
||||
Other/Miscellaneous
Resolved
02/05/2024
1. NO ONE ON SITE AT TIME OF INSPECTION 10:55 AM
|
||||
Plumbing Rough In Inspection | Not Ready | 11/13/2023 | 11/13/2023 | 11/13/2023 |
Kevin Spruell ((253) 841-5590) | ||||
Corrections:
Other/Miscellaneous
Resolved
02/05/2024
1. no lines or floor drains installed at time of inspection that go in to grease interceptor
2.provide AS-built approval of under ground plumbing from EOR at time of slab inspection
3. DWV under slab approved pending as-built approval from EOR
|
||||
Other/Miscellaneous
Resolved
02/05/2024
1. trench drains under slab approved inside building
2. provide approval from engineering for outside the building
|
||||
Other/Miscellaneous
Resolved
02/05/2024
1. NO ONE ON SITE AT TIME OF INSPECTION 10:55 AM
|
||||
Other/Miscellaneous
Resolved
02/05/2024
1. provide test on dwv as discussed with contractor
2.provide city approved plans on site at time of next inspection
|
||||
Combination Frame And Rough In Inspection | Not Ready | 11/13/2023 | 11/13/2023 | 11/13/2023 |
Kevin Spruell ((253) 841-5590) | ||||
Corrections:
Other/Miscellaneous
Resolved
02/05/2024
1. complete all requirements for framing inspection as discussed with contractor
2, not ready
|
||||
Energy (Insulation) Inspection | Failed | 11/22/2023 | 11/22/2023 | 11/22/2023 |
Monty Johnson ((253) 770-3326) | ||||
Corrections:
Other/Miscellaneous
Resolved
02/05/2024
unable to find frame approval
|
||||
Mechanical Rough In Inspection | Partial Pass | 11/22/2023 | 11/22/2023 | 11/22/2023 |
Monty Johnson ((253) 770-3326) | ||||
Corrections:
Other/Miscellaneous
Resolved
02/05/2024
exhaust fans in bathrooms ok
|
||||
Combination Frame And Rough In Inspection | Failed | 11/22/2023 | 11/22/2023 | 11/22/2023 |
Monty Johnson ((253) 770-3326) | ||||
Corrections:
Other/Miscellaneous
Resolved
02/05/2024
1. complete all requirements for framing inspection as discussed with contractor
2, not ready
|
||||
Other/Miscellaneous
Resolved
02/05/2024
most walls insulated, no test on dwv, not ready
|
||||
Fire Or Smoke Damper Inspection | Not Ready | 11/28/2023 | 11/28/2023 | 11/28/2023 |
David Drake ((253) 864-4171) | ||||
Combination Frame And Rough In Inspection | Not Ready | 11/27/2023 | 11/27/2023 | 11/28/2023 |
Kevin Spruell ((253) 841-5590) | ||||
Corrections:
Other/Miscellaneous
Resolved
02/05/2024
1. complete all requirements for framing inspection as discussed with contractor
2, not ready
|
||||
Other/Miscellaneous
Resolved
02/05/2024
1.provide fire blocking at ceiling in bathroom as discussed with contractor
2. complete duct work on mech system
3.complete duct seal
4. remove insulation from ducts to verify duct seal as discussed with contractor
5. provide clarification from MECH engineer of record on duct supports from ceiling to include seismic restraint
6.provide fire cover approval at time of next framing inspection
7. plumbing approved
8.due not insulate
|
||||
Foundation/Rebar Inspection | Not Ready | 11/28/2023 | 11/28/2023 | 11/28/2023 |
Kevin Spruell ((253) 841-5590) | ||||
Corrections:
Other/Miscellaneous
Resolved
11/28/2023
1. bar at footing approved pending letter from EOR not requiring special inspection
2. complete vapor barrier at slab infill's as discussed with contractor
|
||||
Other/Miscellaneous
Resolved
02/05/2024
1. provide all special inspection reports pertaining to wall at time of next inspection as discussed with contractor
|
||||
Energy (Insulation) Inspection | Failed | 11/30/2023 | 11/30/2023 | 11/30/2023 |
Kevin Spruell ((253) 841-5590) | ||||
Corrections:
Other/Miscellaneous
Resolved
02/05/2024
1. complete insulation at corners as discussed with contractor
2.complete insulation at hot water lines as discussed with contractor
3.complete duct work above bathrooms as discussed with contractor
|
||||
Mechanical Rough In Inspection | Failed | 12/1/2023 | 12/1/2023 | 12/01/2023 |
Kevin Spruell ((253) 841-5590) | ||||
Corrections:
Other/Miscellaneous
Resolved
02/05/2024
1. complete items from previous list
|
||||
Energy (Insulation) Inspection | Failed with Fee | 12/1/2023 | 12/1/2023 | 12/01/2023 |
Kevin Spruell ((253) 841-5590) | ||||
Corrections:
Other/Miscellaneous
Resolved
02/05/2024
1. complete insulation at corners as discussed with contractor
2.complete insulation at hot water lines as discussed with contractor
3.complete duct work above bathrooms as discussed with contractor
|
||||
Other/Miscellaneous
Resolved
02/05/2024
1. compete items from previous list
2. pay 180.00 reinspection fee prior to scheduling next inspection
|
||||
Mechanical Rough In Inspection | Not Ready | 12/5/2023 | 12/5/2023 | 12/05/2023 |
Kevin Spruell ((253) 841-5590) | ||||
Corrections:
Other/Miscellaneous
Resolved
02/05/2024
1. complete items from previous list
|
||||
Other/Miscellaneous
Resolved
02/05/2024
1. complete items from previous list as discussed with contractor
|
||||
Energy (Insulation) Inspection | Passed | 12/5/2023 | 12/5/2023 | 12/05/2023 |
Kevin Spruell ((253) 841-5590) | ||||
Corrections:
Other/Miscellaneous
Outstanding
12/01/2023
1. complete insulation at corners as discussed with contractor
2.complete insulation at hot water lines as discussed with contractor
3.complete duct work above bathrooms as discussed with contractor
|
||||
Other/Miscellaneous
Resolved
12/05/2023
1. compete items from previous list
2. pay 180.00 reinspection fee prior to scheduling next inspection
|
||||
Wallboard / Drywall Inspection | Passed | 12/11/2023 | 12/11/2023 | 12/11/2023 |
Kevin Spruell ((253) 841-5590) | ||||
Mechanical Rough In Inspection | Passed | 12/12/2023 | 12/12/2023 | 12/12/2023 |
Kevin Spruell ((253) 841-5590) | ||||
Corrections:
Other/Miscellaneous
Resolved
12/12/2023
1. complete items from previous list
|
||||
Other/Miscellaneous
Resolved
12/12/2023
1. complete items from previous list as discussed with contractor
|
||||
Frame Inspection | Passed | 12/21/2023 | 12/21/2023 | 12/21/2023 |
Kevin Spruell ((253) 841-5590) | ||||
Corrections:
Other/Miscellaneous
Outstanding
11/01/2023
1.provide attachment details for demising wall as discussed with contractor
2. complete all framing requirements as discussed with contractor prior to next inspection
3.not ready
|
||||
Ceiling Grid/T-Bar Inspection | Not Ready | 1/3/2024 | 1/3/2024 | 01/03/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Corrections:
Other/Miscellaneous
Resolved
02/05/2024
1.complete all ceiling requirements as discussed with contractor
2.not ready
|
||||
Shear Wall Inspection | Not Ready | 1/9/2024 | 1/9/2024 | 01/09/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Corrections:
Other/Miscellaneous
Resolved
02/05/2024
1.provide special inspection reports for welding and bolting at southwest corner of building as discussed with contractor
|
||||
Ceiling Grid/T-Bar Inspection | Failed | 1/18/2024 | 1/18/2024 | 01/18/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Corrections:
Other/Miscellaneous
Resolved
01/18/2024
1.complete all ceiling requirements as discussed with contractor
2.not ready
|
||||
Other/Miscellaneous
Resolved
02/05/2024
1. provide birc clips at floating sides of ceiling as discussed with contractor
2.provide positive connection at diffusers
3. provide positive connection of perimeter wires that attach to wall
4. complete 3 turns at wire attachment at lights
|
||||
Ceiling Grid/T-Bar Inspection | Passed | 1/22/2024 | 01/22/2024 | |
Kevin Spruell ((253) 841-5590) | ||||
Corrections:
Other/Miscellaneous
Resolved
01/22/2024
1. provide birc clips at floating sides of ceiling as discussed with contractor
2.provide positive connection at diffusers
3. provide positive connection of perimeter wires that attach to wall
4. complete 3 turns at wire attachment at lights
|
||||
Cover Inspection/Thrust Blocks Inspection | VOID | 01/22/2024 | ||
Jeff Hill ((253) 204-5633) | ||||
Comment Engineering Div Inspection | Failed | 1/22/2024 | 01/22/2024 | |
Jeff Hill ((253) 204-5633) | ||||
Corrections:
Other/Miscellaneous
Carried Forward
01/22/2024
Remove and replace the new wheelchair ramp to current ADA standards.
|
||||
Exit Lighting Test Inspection | Not Ready | 1/24/2024 | 01/24/2024 | |
David Drake ((253) 864-4171) | ||||
Hydrostatic Test 200Lbs 2Hrs | VOID | 01/24/2024 | ||
David Drake ((253) 864-4171) | ||||
Emergency Radio Test Review Inspection | VOID | 01/24/2024 | ||
David Drake ((253) 864-4171) | ||||
Fire Final Inspection | Not Ready | 1/24/2024 | 1/24/2024 | 01/24/2024 |
David Drake ((253) 864-4171) | ||||
Fire Or Smoke Damper Inspection | Not Ready | 1/24/2024 | 1/24/2024 | 01/24/2024 |
David Drake ((253) 864-4171) | ||||
Exit Lighting Test Inspection | Failed | 1/25/2024 | 1/25/2024 | 01/25/2024 |
David Drake ((253) 864-4171) | ||||
Corrections:
Exit Light Test
Carried Forward
01/25/2024
Contractor to provide light meter to determine appropriate amount of emergency lighting needed in bays.
|
||||
Fire Or Smoke Damper Inspection | Not Ready | 1/25/2024 | 1/25/2024 | 01/25/2024 |
David Drake ((253) 864-4171) | ||||
Fire Final Inspection | Failed | 1/25/2024 | 1/25/2024 | 01/25/2024 |
David Drake ((253) 864-4171) | ||||
Corrections:
Fire Final
Carried Forward
01/25/2024
1. Provide emergency lighting in garage bays.
2. NO/CO Test required prior to occupancy.
|
||||
Plumbing Final Inspection | Failed | 1/25/2024 | 1/25/2024 | 01/25/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Corrections:
Other/Miscellaneous
Carried Forward
01/25/2024
1. complete boots at plumbing valves in bath rooms
2.secure wires under sinks as discussed with contractor
|
||||
Fire Final Inspection | Failed with Fee | 1/26/2024 | 01/26/2024 | |
David Drake ((253) 864-4171) | ||||
Corrections:
Fire Final
Resolved
01/30/2024
1. Provide emergency lighting in garage bays.
2. NO/CO Test required prior to occupancy.
|
||||
Fire Final Inspection | Passed | 1/26/2024 | 01/26/2024 | |
David Drake ((253) 864-4171) | ||||
Corrections:
Fire Final
Resolved
01/30/2024
1. Provide emergency lighting in garage bays.
2. NO/CO Test required prior to occupancy.
|
||||
Fire Or Smoke Damper Inspection | Passed | 1/26/2024 | 01/26/2024 | |
David Drake ((253) 864-4171) | ||||
Exit Lighting Test Inspection | Passed | 1/26/2024 | 01/26/2024 | |
David Drake ((253) 864-4171) | ||||
Corrections:
Exit Light Test
Resolved
01/26/2024
Contractor to provide light meter to determine appropriate amount of emergency lighting needed in bays.
|
||||
Fire Or Smoke Damper Inspection | Failed with Fee | 1/26/2024 | 01/26/2024 | |
David Drake ((253) 864-4171) | ||||
Plumbing Final Inspection | Not Ready | 1/26/2024 | 1/26/2024 | 01/26/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Corrections:
Other/Miscellaneous
Resolved
02/05/2024
1. complete boots at plumbing valves in bath rooms
2.secure wires under sinks as discussed with contractor
|
||||
Other/Miscellaneous
Resolved
02/05/2024
1. talked about access at sink area at break area
2. this was a comment inspection
|
||||
Comment Engineering Div Inspection | Passed | 01/26/2024 | ||
Jeff Hill ((253) 204-5633) | ||||
Corrections:
Other/Miscellaneous
Resolved
01/26/2024
Remove and replace the new wheelchair ramp to current ADA standards.
|
||||
Building Final Inspection | Not Ready | 1/29/2024 | 1/29/2024 | 01/29/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Corrections:
Other/Miscellaneous
Resolved
02/05/2024
1.cancelled on site per contractor
|
||||
Fire Final Inspection | VOID | 01/30/2024 | ||
David Drake ((253) 864-4171) | ||||
Engineering Final Inspection | Passed | 2/2/2024 | 01/30/2024 | |
Robyn Buck ((253) 435-3617) | ||||
Building Final Inspection | Failed | 1/30/2024 | 1/30/2024 | 01/30/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Corrections:
Other/Miscellaneous
Resolved
01/30/2024
1.cancelled on site per contractor
|
||||
Other/Miscellaneous
Resolved
02/05/2024
LIFE SAFETY
1. complete install of garage roll-up door west side of building
2.provide landing at back door that does not exceed 2%
3. complete grab bars in employee bathroom
4. complete door hardware at offices
5.complete ada signage at parking stall as per city approved plans
NON LIFE SAFETY
1.insulate main water line in unconditioned space
2.complete vapor barrier at ceiling in storage room
3.provide balance report
4. complete grill in ceiling in employee bathroom
5.complete threshold and door seal at employee bathroom
6.provide occupancy signage at front door
7. complete awnings at west side of building
|
||||
Building Final Inspection | Partial Pass | 1/31/2024 | 1/31/2024 | 01/31/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Corrections:
Other/Miscellaneous
Resolved
01/31/2024
LIFE SAFETY
1. complete install of garage roll-up door west side of building
2.provide landing at back door that does not exceed 2%
3. complete grab bars in employee bathroom
4. complete door hardware at offices
5.complete ada signage at parking stall as per city approved plans
NON LIFE SAFETY
1.insulate main water line in unconditioned space
2.complete vapor barrier at ceiling in storage room
3.provide balance report
4. complete grill in ceiling in employee bathroom
5.complete threshold and door seal at employee bathroom
6.provide occupancy signage at front door
7. complete awnings at west side of building
|
||||
Other/Miscellaneous
Resolved
02/05/2024
1.provide balance report
2.complete grill in employee bathroom
3.complete awnings on west and north side of building
4. TCO approved from today's date 10 working day's
|
||||
Building Final Inspection | Passed | 2/1/2024 | 2/1/2024 | 02/02/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Corrections:
Other/Miscellaneous
Resolved
02/02/2024
1.provide balance report
2.complete grill in employee bathroom
3.complete awnings on west and north side of building
4. TCO approved from today's date 10 working day's
|
||||
Comment Building Div Inspection | VOID | 02/05/2024 | ||
Kevin Spruell ((253) 841-5590) | ||||
Slab/Insulation Inspection | VOID | 02/05/2024 | ||
Kevin Spruell ((253) 841-5590) | ||||
Roof Sheathing Inspection | VOID | 02/05/2024 | ||
Kevin Spruell ((253) 841-5590) | ||||
Firewall/Firestop Inspection | VOID | 02/05/2024 | ||
Kevin Spruell ((253) 841-5590) | ||||
Hydronic Piping Inspection | VOID | 02/05/2024 | ||
Kevin Spruell ((253) 841-5590) | ||||
Refrigeration Line Test Inspection | VOID | 02/05/2024 | ||
Kevin Spruell ((253) 841-5590) | ||||
Exhaust Hood Inspection | VOID | 02/05/2024 | ||
Kevin Spruell ((253) 841-5590) | ||||
Light Test For Grease Duct Inspection | VOID | 02/05/2024 | ||
Kevin Spruell ((253) 841-5590) | ||||
Exhaust/Vent Fans Inspection | VOID | 02/05/2024 | ||
Kevin Spruell ((253) 841-5590) | ||||
Medical Gas Inspection | VOID | 02/05/2024 | ||
Kevin Spruell ((253) 841-5590) | ||||
Planning Final Inspection | VOID | 02/05/2024 | ||
Kevin Spruell ((253) 841-5590) | ||||
Mechanical Final Inspection | VOID | 02/05/2024 | ||
Kevin Spruell ((253) 841-5590) | ||||
Footing/Setback Inspection | VOID | 02/05/2024 | ||
Kevin Spruell ((253) 841-5590) | ||||
Corrections:
Other/Miscellaneous
Outstanding
10/20/2023
1. cancelled on site by contractor
|
||||
Plumbing Rough In Inspection | VOID | 02/05/2024 | ||
Kevin Spruell ((253) 841-5590) | ||||
Corrections:
Other/Miscellaneous
Outstanding
11/13/2023
1. no lines or floor drains installed at time of inspection that go in to grease interceptor
2.provide AS-built approval of under ground plumbing from EOR at time of slab inspection
3. DWV under slab approved pending as-built approval from EOR
|
||||
Other/Miscellaneous
Outstanding
11/13/2023
1. trench drains under slab approved inside building
2. provide approval from engineering for outside the building
|
||||
Other/Miscellaneous
Outstanding
11/13/2023
1. NO ONE ON SITE AT TIME OF INSPECTION 10:55 AM
|
||||
Other/Miscellaneous
Outstanding
11/13/2023
1. provide test on dwv as discussed with contractor
2.provide city approved plans on site at time of next inspection
|
||||
Combination Frame And Rough In Inspection | VOID | 02/05/2024 | ||
Kevin Spruell ((253) 841-5590) | ||||
Corrections:
Other/Miscellaneous
Outstanding
11/28/2023
1. complete all requirements for framing inspection as discussed with contractor
2, not ready
|
||||
Other/Miscellaneous
Outstanding
11/28/2023
1.provide fire blocking at ceiling in bathroom as discussed with contractor
2. complete duct work on mech system
3.complete duct seal
4. remove insulation from ducts to verify duct seal as discussed with contractor
5. provide clarification from MECH engineer of record on duct supports from ceiling to include seismic restraint
6.provide fire cover approval at time of next framing inspection
7. plumbing approved
8.due not insulate
|
||||
Foundation/Rebar Inspection | VOID | 02/05/2024 | ||
Kevin Spruell ((253) 841-5590) | ||||
Corrections:
Other/Miscellaneous
Outstanding
11/28/2023
1. provide all special inspection reports pertaining to wall at time of next inspection as discussed with contractor
|
||||
Shear Wall Inspection | VOID | 02/05/2024 | ||
Kevin Spruell ((253) 841-5590) | ||||
Corrections:
Other/Miscellaneous
Outstanding
01/09/2024
1.provide special inspection reports for welding and bolting at southwest corner of building as discussed with contractor
|
||||
Plumbing Final Inspection | VOID | 02/05/2024 | ||
Kevin Spruell ((253) 841-5590) | ||||
Corrections:
Other/Miscellaneous
Resolved
02/05/2024
1. complete boots at plumbing valves in bath rooms
2.secure wires under sinks as discussed with contractor
|
||||
Other/Miscellaneous
Resolved
02/05/2024
1. talked about access at sink area at break area
2. this was a comment inspection
|
Condition | Status | Category |
---|---|---|
Building Permit Standard Conditions | Open | Standard Conditions |
Building Division
* Final approval by the Building Official is required prior to use or occupancy.* Work shall not proceed until the inspector has approved the stages of construction.* Surface storm water shall be diverted from the building site and shall not drain onto adjacent properties.* I hereby acknowledge that I have read this Permit/Application, that the information given is correct; that I am the owner or the duly authorized agent of the owner; that plans submitted herewith are in compliance with all applicable city, county and state laws and that all construction will proceed in accordance with said laws. This permit shall expire if work is not commenced with 180 days or if the work is suspended for a period of 180 days. Permits expire two years from issuance. * By leaving the contractor information section blank, I hereby certify further that contractors (general or subcontractors) will not be hired to perform any work in association with this permit. I also certify that if I do choose to hire a contractor (general or subcontractor) I will only hire those contractors that are licensed by the State of Washington. If you are a property owner, contractor or permittee and you are paying for someone to perform the work, they must have a valid contractor registration and the person(s) installing plumbing inside a structure must meet the plumbing certification requirements. If you have any questions regarding these regulations, you may contact the Washington State Department of Labor and Industries or you can find more information on-line at: http://www.lni.wa.gov/TradesLicensing/Contractors/HireCon/default.asp
|
||
Fire Review Conditions | Open | Standard Conditions |
• Comply with 2018 IFC and 2018 IBC
• Total coverage required in the city of puyallup
• L&I Final required prior to Fire Final
• Exit lighting test required, contractor to provide light meter
• Separate permits required for Fire Alarm and Fire Sprinkler
• RTU’S will be required to be tested for shut down
• Smoke and Fire dampeners will be tested with Fire Alarm. Access doors are required for maintenance and visual inspection.
• Fire extinguishers required per code
• Existing buildings will need to contact central pierce fire & rescue and update the key in the Knox box
• All above items to be completed prior to fire final. Fire final required before building final
Schedule your inspection online through the City of Puyallup online permit system. This is a request for inspection only. A date and time will be selected by Inspector depending on availability. Email prior to inspection for date and time. Fire Inspections are Monday – Thursday there will be no inspections on Fridays.
David Drake 253-864-4171 ddrake@puyallupwa.gov
|
||
Engineering Commercial Standard Conditions | Open | Standard Conditions |
Engineering Division
Development Engineering standard commercial conditions:
** Prior to STARTING the applicant shall request an erosion and sediment control inspection using the CityView permit portal at least 48 hours in advance of job start **
- Prior to starting site work request an inspection for erosion and sediment.
- Occupancy will not be granted until all civil work associated with PRCCP20230248 has been completed and approval has been provided.
- Sediment control and erosion procedures shall be practice to eliminate and prevent off site damage. Stormwater runoff originating upgrade of exposed areas shall be controlled to reduce erosion and sediment loss during the period of exposure. Attached to the site plan is the city of puyallup’s stormwater fact sheet. or See approved civil plan PRCCP20230248 for approved method of control.
- Stormwater control of roof downspouts required. Attached to the site plan is a typical infiltration system you may choose to follow.
- All commercial development, multi-family, mixed use facility,or irrigation systems water service connections must have installed an approved backflow prevention assembly installed as directed by the Puyallup Municipal Code 14.02.220(3) and conforming to city standard section 03.04 - backflow installation. A double detector check valve assembly (DDCVA) is required or A reduced pressure backflow assembly (RPBA) is required as directed by the City of Puyallup, Fruitland Mutual Water Company, Tacoma City Water or Valley Water District.
- Due to the proximity of this property to a secondary water source (i.e. clarks creek, meeker ditch, etc.) the applicant shall install a reduced pressure backflow assembly per city standards.
- A commercial development must have installed a side sewer sampling tee installed in conformance to city standard section 04.03 – side sewer.
- Any code requirement that may have been overlooked in this plan review does not imply that the requirements have been waived.
- This property lies within a regulated flood zone. both residential and non-residential must meet the following requirements in accordance with PMC 21.07:
|
||
Miscellaneous Condition | Open | Prior to Occupancy |
Engineering Division
All work associated with civil permit PRCCP20230248 must be completed and a final approval given. Including, but not limited to a sewer sampling tee and a RPBA backflow protection. LL 07/25/2023
|
||
Miscellaneous Condition | Resolved | Prior to Issuance |
Engineering Division
Civil permit PRCCP20230248 must be issued prior to this permit issued
CIVIL PERMIT HAS BEEN ISSUED [Robyn Buck @ 09/07/2023 10:06 AM]
|
Reference Number | Status | Type |
---|---|---|
PRCCP20230248 | Closed | Civil Construction Permit |
PRFS20231452 | Closed | Fire Sprinklers |
PRSG20231517 | Closed | Sign/Awning |
PLPRE20220043 | File Closed | Pre-Application |
Should you need assistance, please contact the Permit Center at (253) 864-4165 option 1.
Powered by CityView
