Paid Fees | Amount | Paid | Owing | Date Paid |
---|---|---|---|---|
Fire Review Fee (Commercial Building) | $265.00 | $265.00 | Paid | 07/13/2023 |
Mechanical Duct Work Fee | $14.10 | $14.10 | Paid | 07/13/2023 |
Building Permit Fee | $1,609.75 | $1,609.75 | Paid | 07/13/2023 |
Mechanical Permit Fee | $40.00 | $40.00 | Paid | 07/13/2023 |
Plumbing Fixtures Fee | $52.00 | $52.00 | Paid | 07/13/2023 |
Plumbing Permit Fee | $40.00 | $40.00 | Paid | 07/13/2023 |
Building Plan Review Fee | $1,046.34 | $1,046.34 | Paid | 05/05/2023 |
Mechanical Plan Review Fee | $35.17 | $35.17 | Paid | 05/05/2023 |
Plumbing Plan Review Fee | $59.80 | $59.80 | Paid | 05/05/2023 |
WA State Building Code Council Fee (Commercial) | $25.00 | $25.00 | Paid | 07/13/2023 |
Sewer System Development ChargeFee - Tenant Improvment/Addition | $1,700.20 | $1,700.20 | Paid | 07/13/2023 |
Water System Development ChargeFee - Tenant Improvment/Addition | $1,398.44 | $1,398.44 | Paid | 07/13/2023 |
Outstanding Fees | Amount | Paid | Owing | Date Paid |
No outstanding fees. | ||||
Totals: | $6,285.80 | $6,285.80 | $0.00 |
Permit(s) will not be issued until outstanding fees have been paid in full. Fee details shown above only include currently payable fees, there might be addtional fees to be paid before issuance.
$0.00
Inspection | Outcome | Requested | Scheduled | Date Inspected |
---|---|---|---|---|
Cover Inspection/Thrust Blocks Inspection | VOID | 8/21/2023 | 8/21/2023 | 08/21/2023 |
Jeff Hill ((253) 204-5633) | ||||
Mechanical Rough In Inspection | Partial Pass | 8/22/2023 | 8/22/2023 | 08/22/2023 |
Shannon King ((253) 840-6684) | ||||
Comment Building Div Inspection | Not Ready | 8/23/2023 | 8/23/2023 | 08/23/2023 |
Shannon King ((253) 840-6684) | ||||
Frame Inspection | Not Ready | 8/24/2023 | 8/24/2023 | 08/24/2023 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
08/24/2023
1. cancelled on site by contractor
|
||||
Plumbing Rough In Inspection | Partial Pass | 8/31/2023 | 8/31/2023 | 09/01/2023 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
09/01/2023
1. DWV and supply approved per city approved plans
2. perform run test at 3 tie in locations as discussed with contractor prior to final
|
||||
Frame Inspection | Partial Pass | 9/1/2023 (2:00 to 3:00) | 9/1/2023 | 09/01/2023 |
Ray Cockerham ((253) 841-5585) | ||||
Other/Miscellaneous
Carried Forward
09/01/2023
1. cancelled on site by contractor
|
||||
Wallboard / Drywall Inspection | Failed | 9/5/2023 | 9/5/2023 | 09/05/2023 |
Shannon King ((253) 840-6684) | ||||
Other/Miscellaneous
Carried Forward
09/05/2023
1 ; complete all drywall nailing as discussed with contractor.
not ready
|
||||
Wallboard / Drywall Inspection | Partial Pass | 9/7/2023 | 9/7/2023 | 09/07/2023 |
Shannon King ((253) 840-6684) | ||||
Other/Miscellaneous
Resolved
09/07/2023
1 ; complete all drywall nailing as discussed with contractor.
not ready
|
||||
Other/Miscellaneous
Carried Forward
09/07/2023
1 ; all drywall nailing complete except east wall in room - 101
|
||||
Mechanical Rough In Inspection | Partial Pass | 9/27/2023 | 9/27/2023 | 09/27/2023 |
Shannon King ((253) 840-6684) | ||||
Ceiling Grid/T-Bar Inspection | Not Ready | 10/5/2023 | 10/5/2023 | 10/05/2023 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
10/05/2023
1. complete all ceiling requirements as discussed with contractor
2.provide electrical ceiling cover approval at time of next inspection
3.not ready
|
||||
Plumbing Final Inspection | Not Ready | 10/5/2023 | 10/5/2023 | 10/05/2023 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
10/05/2023
1. provide clarification from architect on eye wash added that is not on city approved plans
2. run test on 3 DWV tie ins approved
|
||||
Comment Building Div Inspection | Partial Pass | 10/5/2023 | 10/5/2023 | 10/05/2023 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
10/05/2023
1. this was a MECH diffuser at the ceiling inspection approved
|
||||
Ceiling Grid/T-Bar Inspection | Partial Pass | 10/6/2023 | 10/6/2023 | 10/06/2023 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Resolved
10/06/2023
1. complete all ceiling requirements as discussed with contractor
2.provide electrical ceiling cover approval at time of next inspection
3.not ready
|
||||
Other/Miscellaneous
Carried Forward
10/06/2023
1. complete BIRC clips in back area and complete wire attachment same area and leave tiles out to inspect as discussed with contractor
2. all other tiles can be installed
|
||||
Fire Final Inspection | Not Ready | 10/23/2023 | 10/23/2023 | 10/23/2023 |
David Drake ((253) 864-4171) | ||||
Building Final Inspection | Not Ready | 12/1/2023 | 12/1/2023 | 12/01/2023 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
12/01/2023
1.cancelled by contractor
|
||||
Comment Engineering Div Inspection | VOID | 12/05/2023 | ||
Shannon King ((253) 840-6684) | ||||
Footing/Setback Inspection | VOID | 12/05/2023 | ||
Shannon King ((253) 840-6684) | ||||
Energy (Insulation) Inspection | VOID | 12/05/2023 | ||
Shannon King ((253) 840-6684) | ||||
Shear Wall Inspection | VOID | 12/05/2023 | ||
Shannon King ((253) 840-6684) | ||||
Roof Sheathing Inspection | VOID | 12/05/2023 | ||
Shannon King ((253) 840-6684) | ||||
Slab/Insulation Inspection | VOID | 12/05/2023 | ||
Shannon King ((253) 840-6684) | ||||
Foundation/Rebar Inspection | VOID | 12/05/2023 | ||
Shannon King ((253) 840-6684) | ||||
Exhaust/Vent Fans Inspection | VOID | 12/05/2023 | ||
Shannon King ((253) 840-6684) | ||||
Light Test For Grease Duct Inspection | VOID | 12/05/2023 | ||
Shannon King ((253) 840-6684) | ||||
Exhaust Hood Inspection | VOID | 12/05/2023 | ||
Shannon King ((253) 840-6684) | ||||
Refrigeration Line Test Inspection | VOID | 12/05/2023 | ||
Shannon King ((253) 840-6684) | ||||
Hydronic Piping Inspection | VOID | 12/05/2023 | ||
Shannon King ((253) 840-6684) | ||||
Exit Lighting Test Inspection | VOID | 12/05/2023 | ||
Shannon King ((253) 840-6684) | ||||
Combination Frame And Rough In Inspection | VOID | 12/05/2023 | ||
Shannon King ((253) 840-6684) | ||||
Planning Final Inspection | VOID | 12/05/2023 | ||
Shannon King ((253) 840-6684) | ||||
Engineering Final Inspection | VOID | 12/05/2023 | ||
Shannon King ((253) 840-6684) | ||||
Emergency Radio Test Review Inspection | VOID | 12/05/2023 | ||
Shannon King ((253) 840-6684) | ||||
Hydrostatic Test 200Lbs 2Hrs | VOID | 12/05/2023 | ||
Shannon King ((253) 840-6684) | ||||
Fire Or Smoke Damper Inspection | VOID | 12/05/2023 | ||
Shannon King ((253) 840-6684) | ||||
Medical Gas Inspection | VOID | 12/05/2023 | ||
Shannon King ((253) 840-6684) | ||||
Mechanical Rough In Inspection | VOID | 12/05/2023 | ||
Shannon King ((253) 840-6684) | ||||
Frame Inspection | VOID | 12/05/2023 | ||
Shannon King ((253) 840-6684) | ||||
Other/Miscellaneous
Outstanding
09/01/2023
1. cancelled on site by contractor
|
||||
Comment Building Div Inspection | VOID | 12/05/2023 | ||
Shannon King ((253) 840-6684) | ||||
Other/Miscellaneous
Outstanding
10/05/2023
1. this was a MECH diffuser at the ceiling inspection approved
|
||||
Mechanical Final Inspection | VOID | 12/05/2023 | ||
Shannon King ((253) 840-6684) | ||||
Other/Miscellaneous
Outstanding
10/11/2023
1 ; provide balance report with O.S.A. as per city approved plans.
|
||||
Plumbing Rough In Inspection | VOID | 12/05/2023 | ||
Shannon King ((253) 840-6684) | ||||
Other/Miscellaneous
Outstanding
09/01/2023
1. DWV and supply approved per city approved plans
2. perform run test at 3 tie in locations as discussed with contractor prior to final
|
Condition | Status | Department | Category | Expiration Date | Due Date |
---|---|---|---|---|---|
Building Permit Standard Conditions | Open | Building Division | Standard Conditions | ||
:
* Final approval by the Building Official is required prior to use or occupancy.* Work shall not proceed until the inspector has approved the stages of construction.* Surface storm water shall be diverted from the building site and shall not drain onto adjacent properties.* I hereby acknowledge that I have read this Permit/Application, that the information given is correct; that I am the owner or the duly authorized agent of the owner; that plans submitted herewith are in compliance with all applicable city, county and state laws and that all construction will proceed in accordance with said laws. This permit shall expire if work is not commenced with 180 days or if the work is suspended for a period of 180 days. Permits expire two years from issuance. * By leaving the contractor information section blank, I hereby certify further that contractors (general or subcontractors) will not be hired to perform any work in association with this permit. I also certify that if I do choose to hire a contractor (general or subcontractor) I will only hire those contractors that are licensed by the State of Washington. If you are a property owner, contractor or permittee and you are paying for someone to perform the work, they must have a valid contractor registration and the person(s) installing plumbing inside a structure must meet the plumbing certification requirements. If you have any questions regarding these regulations, you may contact the Washington State Department of Labor and Industries or you can find more information on-line at: http://www.lni.wa.gov/TradesLicensing/Contractors/HireCon/default.asp
|
|||||
Fire Review Conditions | Open | Standard Conditions | |||
:
• Comply with 2018 IFC and 2018 IBC
• Total coverage required in the city of puyallup
• L&I Final required prior to Fire Final
• Exit lighting test required, contractor to provide light meter
• Separate permits required for Fire Alarm and Fire Sprinkler
• Smoke and Fire dampeners will be tested with Fire Alarm. Access doors are required for maintenance and visual inspection.
• Fire extinguishers required per code
• Existing buildings will need to contact central pierce fire & rescue and update the key in the Knox box
• All above items to be completed prior to fire final. Fire final required before building final
Schedule your inspection online through the City of Puyallup online permit system. This is a request for inspection only. A date and time will be selected by Inspector depending on availability. Email prior to inspection for date and time. Fire Inspections are Monday – Thursday there will be no inspections on Fridays.
David Drake 253-864-4171 ddrake@puyallupwa.gov
|
Reference Number | Status | Type |
---|---|---|
PRFS20231199 | Closed | Fire Sprinklers |
Should you need assistance, please contact the Permit Center at (253) 864-4165 option 1.