Paid Fees | Amount | Paid | Owing | Date Paid |
---|---|---|---|---|
Fire Review Fee (Commercial Building) | $265.00 | $265.00 | Paid | 09/06/2024 |
Building Permit Fee | $3,233.75 | $3,233.75 | Paid | 09/06/2024 |
Building Plan Review Fee | $2,101.94 | $2,101.94 | Paid | 07/08/2024 |
WA State Building Code Council Fee (Commercial) | $25.00 | $25.00 | Paid | 09/06/2024 |
Gas Piping (Plumbing) Fee | $12.50 | $12.50 | Paid | 09/06/2024 |
Plumbing Permit Fee | $40.00 | $40.00 | Paid | 09/06/2024 |
Plumbing Plan Review Fee | $34.13 | $34.13 | Paid | 09/06/2024 |
Resubmittal Fee | $180.00 | $180.00 | Paid | 08/13/2024 |
Outstanding Fees | Amount | Paid | Owing | Date Paid |
Sewer System Development ChargeFee - Tenant Improvment/Addition | $0.00 | $0.00 | Not payable | Not Paid |
Water System Development ChargeFee - Tenant Improvment/Addition | $0.00 | $0.00 | Not payable | Not Paid |
Totals: | $5,892.32 | $5,892.32 | $0.00 |
Permit(s) will not be issued until outstanding fees have been paid in full. Fee details shown above only include currently payable fees, there might be addtional fees to be paid before issuance.
$0.00
Inspection | Outcome | Requested | Scheduled | Date Inspected |
---|---|---|---|---|
Frame Inspection | Failed | 9/24/2024 | 9/24/2024 | 09/24/2024 |
Monty Johnson ((253) 770-3326) | ||||
Corrections:
Other/Miscellaneous
Carried Forward
09/24/2024
provide architects rfi on wall bracing/bridging, ok to 1 side at own risk, insp for demising wall only
|
||||
Wallboard / Drywall Inspection | Partial Pass | 10/3/2024 | 10/3/2024 | 10/03/2024 |
Monty Johnson ((253) 770-3326) | ||||
Corrections:
Other/Miscellaneous
Carried Forward
10/03/2024
demising wall frame ok and drywall on south side of wall ok.
|
||||
Foundation/Rebar Inspection | Partial Pass | 10/4/2024 | 10/4/2024 | 10/04/2024 |
Monty Johnson ((253) 770-3326) | ||||
Corrections:
Other/Miscellaneous
Carried Forward
10/04/2024
store front footings ok with special inspection.
|
||||
Gas Test Inspection | Not Ready | 10/7/2024 | 10/7/2024 | 10/07/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Corrections:
Other/Miscellaneous
Carried Forward
10/07/2024
date of inspection 10/7/2024
1. provide test on gas pipe as discussed with contractor
2.provide test on DWV at time of next inspection
3.did not go on roof
4. not a complete list
|
||||
Plumbing Final Inspection | Not Ready | 10/8/2024 | 10/8/2024 | 10/08/2024 |
Shannon King ((253) 840-6684) | ||||
Erosion And Sediment Inspection | Partial Pass | 10/8/2024 | 10/08/2024 | |
Jason Little ((253) 244-0387) | ||||
Combination Frame And Rough In Inspection | Partial Pass | 10/8/2024 | 10/8/2024 | 10/08/2024 |
Shannon King ((253) 840-6684) | ||||
Energy (Insulation) Inspection | Partial Pass | 10/8/2024 | 10/8/2024 | 10/08/2024 |
Shannon King ((253) 840-6684) | ||||
Sidesewer Inspection | Failed | 10/8/2024 | 10/08/2024 | |
Jason Little ((253) 244-0387) | ||||
Corrections:
Other/Miscellaneous
Carried Forward
10/08/2024
Tie side sewer into main line upstream from the c/o and sample tee.
Install a 6" sample tee upstream from the c/o.
The c/o riser needs to be replaced.
Install cap and adaptors for the risers.
Install castings with lids that say sewer.
The c/o and sample tee dimension may need to be adjusted to fit within excavation. Maintain separation for casting fitment.
|
||||
Plumbing Below Slab Inspection | Partial Pass | 10/9/2024 | 10/9/2024 | 10/09/2024 |
Monty Johnson ((253) 770-3326) | ||||
Corrections:
Other/Miscellaneous
Carried Forward
10/09/2024
1:4" main drain trunk at far south wall ok
|
||||
Slab/Insulation Inspection | Partial Pass | 10/14/2024 | 10/14/2024 | 10/14/2024 |
Shannon King ((253) 840-6684) | ||||
Corrections:
Other/Miscellaneous
Carried Forward
10/14/2024
Date of slab inspection 10/14/2024
1 ; vapor barrier and dowels complete at plumbing trenches.( except at restrooms )
|
||||
Firewall/Firestop Inspection | Passed | 10/16/2024 | 10/16/2024 | 10/16/2024 |
Monty Johnson ((253) 770-3326) | ||||
Corrections:
Other/Miscellaneous
Outstanding
10/16/2024
head of wall ok
|
||||
Frame Inspection | Failed | 10/23/2024 | 10/23/2024 | 10/24/2024 |
Monty Johnson ((253) 770-3326) | ||||
Corrections:
Other/Miscellaneous
Resolved
10/24/2024
provide architects rfi on wall bracing/bridging, ok to 1 side at own risk, insp for demising wall only
|
||||
Other/Miscellaneous
Carried Forward
10/24/2024
complete plumbing for hose bib and have on test, inspection for firred wall at front south corner.
|
||||
Combination Frame And Rough In Inspection | Partial Pass | 10/24/2024 | 10/24/2024 | 10/24/2024 |
Monty Johnson ((253) 770-3326) | ||||
Corrections:
Other/Miscellaneous
Carried Forward
10/24/2024
2 furred walls at front of store south side ok
|
||||
Energy (Insulation) Inspection | Partial Pass | 10/24/2024 | 10/24/2024 | 10/24/2024 |
Monty Johnson ((253) 770-3326) | ||||
Corrections:
Other/Miscellaneous
Carried Forward
10/24/2024
2 furred walls at front of store south side ok
|
||||
Foundation/Rebar Inspection | Not Ready | 11/6/2024 | 11/6/2024 | 11/06/2024 |
Monty Johnson ((253) 770-3326) | ||||
Corrections:
Other/Miscellaneous
Carried Forward
11/06/2024
insp for red iron entry
1:provide special inspectors approval for bolting and welding.
|
||||
Frame Inspection | Partial Pass | 11/20/2024 | 11/20/2024 | 11/20/2024 |
Monty Johnson ((253) 770-3326) | ||||
Corrections:
Other/Miscellaneous
Carried Forward
11/20/2024
infill frame at old entry ok.
|
||||
Frame Inspection | Partial Pass | 11/27/2024 | 11/27/2024 | 11/27/2024 |
Monty Johnson ((253) 770-3326) | ||||
Corrections:
Other/Miscellaneous
Carried Forward
11/27/2024
insp for store front facade
1:ok to sheath.
|
||||
Frame Inspection | Passed | 12/3/2024 | 12/3/2024 | 12/03/2024 |
Monty Johnson ((253) 770-3326) | ||||
Gas Test Inspection | Partial Pass | 12/12/2024 | 12/12/2024 | 12/12/2024 |
Monty Johnson ((253) 770-3326) | ||||
Corrections:
Other/Miscellaneous
Carried Forward
12/12/2024
date of inspection 10/7/2024
1. provide test on gas pipe as discussed with contractor
2.provide test on DWV at time of next inspection
3.did not go on roof
4. not a complete list
|
||||
Other/Miscellaneous
Carried Forward
12/12/2024
test at 50 psi on both lines, no access to roof to see all the gas pipe.
|
||||
Comment Engineering Div Inspection | Failed | 12/13/2024 | 12/13/2024 | |
Jason Little ((253) 244-0387) | ||||
Corrections:
Other/Miscellaneous
Carried Forward
12/13/2024
- Dilute, clean, and dry fire room floor.
- Vac and jet entire storm system along the west and north side of the building and the outlet to the swale.
|
||||
Fire Final Inspection | Not Ready | 12/16/2024 | 12/16/2024 | |
David Drake ((253) 864-4171) | ||||
Corrections:
Other/Miscellaneous
Outstanding
12/16/2024
Not Ready
Talked with Boot Barn management, Brian Bennett, and Façade contractor. Use the exterior rear door for stocking until life safety is met overhead at front entrance.
|
||||
Comment Engineering Div Inspection | Not Ready | 12/16/2024 | 12/16/2024 | |
Jason Little ((253) 244-0387) | ||||
Corrections:
Other/Miscellaneous
Resolved
12/16/2024
- Dilute, clean, and dry fire room floor.
- Vac and jet entire storm system along the west and north side of the building and the outlet to the swale.
|
||||
Gas Test Inspection | Passed | 12/18/2024 | 12/18/2024 | 12/18/2024 |
Monty Johnson ((253) 770-3326) | ||||
Corrections:
Other/Miscellaneous
Outstanding
12/12/2024
date of inspection 10/7/2024
1. provide test on gas pipe as discussed with contractor
2.provide test on DWV at time of next inspection
3.did not go on roof
4. not a complete list
|
||||
Other/Miscellaneous
Outstanding
12/18/2024
gas test approved at 60 psi two lines.
|
||||
Combination Frame And Rough In Inspection | Not Ready | 12/19/2024 | 12/19/2024 | 12/19/2024 |
Monty Johnson ((253) 770-3326) | ||||
Corrections:
Other/Miscellaneous
Carried Forward
12/19/2024
1:provide architects complete plans on temp tunnel for tco
|
||||
Fire Final Inspection | Not Ready | 1/16/2025 | 1/16/2025 | 01/16/2025 |
David Drake ((253) 864-4171) | ||||
Corrections:
Other/Miscellaneous
Carried Forward
01/16/2025
Fire Alarm required to be signed off by L&i, then tested and approved prior to Building Final. Reschedule when shell space is complete.
|
||||
Building Final Inspection | Not Ready | 1/17/2025 | 1/17/2025 | 01/17/2025 |
Monty Johnson ((253) 770-3326) | ||||
Corrections:
Other/Miscellaneous
Carried Forward
01/17/2025
provide fire and engineering dept sign off prior to building final.
|
||||
Engineering Final Inspection | Passed w/ Conditions | 1/29/2025 (9:00 to 10:00) | 1/29/2025 | 01/29/2025 |
Jason Little ((253) 244-0387) | ||||
Building Final Inspection | Failed | 1/31/2025 | 1/31/2025 | 01/31/2025 |
Monty Johnson ((253) 770-3326) | ||||
Corrections:
Other/Miscellaneous
Carried Forward
01/31/2025
seal hole in 1hr demising wall and have fire sign off
|
||||
Exit Lighting Test Inspection | Passed | 1/30/2025 | 02/03/2025 | |
David Drake ((253) 864-4171) | ||||
Fire Or Smoke Damper Inspection | VOID | 02/03/2025 | ||
David Drake ((253) 864-4171) | ||||
Hydrostatic Test 200Lbs 2Hrs | VOID | 02/03/2025 | ||
David Drake ((253) 864-4171) | ||||
Emergency Radio Test Review Inspection | VOID | 02/03/2025 | ||
David Drake ((253) 864-4171) | ||||
Fire Final Inspection | Passed | 1/30/2025 | 02/03/2025 | |
David Drake ((253) 864-4171) | ||||
Corrections:
Other/Miscellaneous
Resolved
02/03/2025
Fire Alarm required to be signed off by L&i, then tested and approved prior to Building Final. Reschedule when shell space is complete.
|
||||
Building Final Inspection | Passed | 2/5/2025 | 2/5/2025 | 02/05/2025 |
Monty Johnson ((253) 770-3326) | ||||
Comment Building Div Inspection | VOID | 04/11/2025 | ||
Joyce Kennedy ((253) 841-5405) | ||||
Footing/Setback Inspection | VOID | 04/11/2025 | ||
Joyce Kennedy ((253) 841-5405) | ||||
Roof Sheathing Inspection | VOID | 04/11/2025 | ||
Joyce Kennedy ((253) 841-5405) | ||||
Shear Wall Inspection | VOID | 04/11/2025 | ||
Joyce Kennedy ((253) 841-5405) | ||||
Ceiling Grid/T-Bar Inspection | VOID | 04/11/2025 | ||
Joyce Kennedy ((253) 841-5405) | ||||
Hydronic Piping Inspection | VOID | 04/11/2025 | ||
Joyce Kennedy ((253) 841-5405) | ||||
Refrigeration Line Test Inspection | VOID | 04/11/2025 | ||
Joyce Kennedy ((253) 841-5405) | ||||
Exhaust Hood Inspection | VOID | 04/11/2025 | ||
Joyce Kennedy ((253) 841-5405) | ||||
Light Test For Grease Duct Inspection | VOID | 04/11/2025 | ||
Joyce Kennedy ((253) 841-5405) | ||||
Exhaust/Vent Fans Inspection | VOID | 04/11/2025 | ||
Joyce Kennedy ((253) 841-5405) | ||||
Medical Gas Inspection | VOID | 04/11/2025 | ||
Joyce Kennedy ((253) 841-5405) | ||||
Planning Final Inspection | VOID | 04/11/2025 | ||
Joyce Kennedy ((253) 841-5405) | ||||
Wallboard / Drywall Inspection | VOID | 04/11/2025 | ||
Joyce Kennedy ((253) 841-5405) | ||||
Plumbing Final Inspection | VOID | 04/11/2025 | ||
Joyce Kennedy ((253) 841-5405) | ||||
Erosion And Sediment Inspection | VOID | 04/11/2025 | ||
Joyce Kennedy ((253) 841-5405) | ||||
Sidesewer Inspection | VOID | 04/11/2025 | ||
Joyce Kennedy ((253) 841-5405) | ||||
Corrections:
Other/Miscellaneous
Outstanding
10/08/2024
Tie side sewer into main line upstream from the c/o and sample tee.
Install a 6" sample tee upstream from the c/o.
The c/o riser needs to be replaced.
Install cap and adaptors for the risers.
Install castings with lids that say sewer.
The c/o and sample tee dimension may need to be adjusted to fit within excavation. Maintain separation for casting fitment.
|
||||
Plumbing Below Slab Inspection | VOID | 04/11/2025 | ||
Joyce Kennedy ((253) 841-5405) | ||||
Slab/Insulation Inspection | VOID | 04/11/2025 | ||
Joyce Kennedy ((253) 841-5405) | ||||
Corrections:
Other/Miscellaneous
Outstanding
10/14/2024
Date of slab inspection 10/14/2024
1 ; vapor barrier and dowels complete at plumbing trenches.( except at restrooms )
|
||||
Energy (Insulation) Inspection | VOID | 04/11/2025 | ||
Joyce Kennedy ((253) 841-5405) | ||||
Foundation/Rebar Inspection | VOID | 04/11/2025 | ||
Joyce Kennedy ((253) 841-5405) | ||||
Comment Engineering Div Inspection | VOID | 04/11/2025 | ||
Joyce Kennedy ((253) 841-5405) | ||||
Combination Frame And Rough In Inspection | VOID | 04/11/2025 | ||
Joyce Kennedy ((253) 841-5405) |
Condition | Status | Category |
---|---|---|
Building Permit Standard Conditions | Open | Standard Conditions |
Building Division
* Final approval by the Building Official is required prior to use or occupancy.* Work shall not proceed until the inspector has approved the stages of construction.* Surface storm water shall be diverted from the building site and shall not drain onto adjacent properties.* I hereby acknowledge that I have read this Permit/Application, that the information given is correct; that I am the owner or the duly authorized agent of the owner; that plans submitted herewith are in compliance with all applicable city, county and state laws and that all construction will proceed in accordance with said laws. This permit shall expire if work is not commenced with 180 days or if the work is suspended for a period of 180 days. Permits expire two years from issuance. * By leaving the contractor information section blank, I hereby certify further that contractors (general or subcontractors) will not be hired to perform any work in association with this permit. I also certify that if I do choose to hire a contractor (general or subcontractor) I will only hire those contractors that are licensed by the State of Washington. If you are a property owner, contractor or permittee and you are paying for someone to perform the work, they must have a valid contractor registration and the person(s) installing plumbing inside a structure must meet the plumbing certification requirements. If you have any questions regarding these regulations, you may contact the Washington State Department of Labor and Industries or you can find more information on-line at: http://www.lni.wa.gov/TradesLicensing/Contractors/HireCon/default.asp
|
||
Fire Review Conditions | Open | Standard Conditions |
1. Address and Suite numbers required to be installed prior to Final.
2. Separate Fire Alarm and Fire Sprinkler permits required.
3. In existing buildings all required service and maintenance to be completed prior to inspection for the Fire Alarm, and Fire Sprinkler Systems.
4. Fire Alarm and Fire Sprinkler System to be redesigned for new demising wall.
|
Reference Number | Status | Type |
---|---|---|
PRDE20240877 | Closed | Demolition |
PRFA20241499 | Closed | Fire Alarms |
Should you need assistance, please contact the Permit Center at (253) 864-4165 option 1.