Review Type |
Outcome |
Est. Completion Date |
Completed |
Planning Review
|
Approved
|
07/06/2023
|
07/11/2023
|
|
|
Building Review
|
Approved
|
07/06/2023
|
07/06/2023
|
|
|
Engineering Review
|
Approved
|
07/06/2023
|
06/29/2023
|
|
|
Engineering Traffic Review
|
VOID
|
07/06/2023
|
06/29/2023
|
|
|
Fire Review
|
Approved
|
07/06/2023
|
06/26/2023
|
|
|
Engineering Storm Review
|
Approved
|
07/06/2023
|
06/22/2023
|
|
|
|
Add Submittal Item: Misc
Additional Submittal Item Required: Stormwater Site Plan. This is the project's Stormwater Report. Use Worksheets from the City's Single Family Homes webpage or use the template provided in The 2019 Ecology Stormwater Manual for Western Washington found in Section III-3.2 Step 7.
https://www.cityofpuyallup.org/1450/Stormwater-Worksheets-for-Single-Family-
|
|
Add Submittal Item: Misc
Additional Submittal Item Required: Surveyed Site Plan. This must be stamped by a Professional Land surveyor, civil engineer, or other qualified professional. See Section III-3.2 Step 1 in the Ecology Manual for required items on this plan.
|
|
Add Submittal Item: Misc
Additional Submittal Item Required: Geotechnical Report Stamped by Licensed Geotech or other qualified professional. See Section III-3.2 Step 1 in the Ecology Manual for required items on this plan.
|
|
Other/Miscellaneous
Provide any previous stormwater reports. Include calculations in new report to determine if existing rain garden is appropriately sized to mitigate Stormwater and considered the first feasible BMP per the 2019 Ecology Manual requirements.
|
|
Add Submittal Item: Misc
Additional Submittal Item Required: Add Construction SWPPP addressing the 13 elements to pollution prevention. Use Ecology Template to ensure all requirements are met.
https://fortress.wa.gov/ecy/ezshare/wq/permits/CSWGP-SWPPP-Template.docx
|
|
Add Submittal Item: Misc
Additional Submittal Item Required: Fill out Impervious Surface table and resubmit in the Storm Report Bucket. See Provided Table in documents.
|
|
Other/Miscellaneous
2nd submittal does not address the storm requirements requested in the reveiw of the first submittal. Any project that adds more than 2,000 square feet of impervious surface (roofs, driveways, porches, decks, etc.) shall engineer the site drainage to match the requirements of the 2019 Storm Water Management Manual for Western Washington and have their site plan prepared by a civil engineer with a Washington State Engineering License. All previous comments still stand.
|
Planning Review
|
Approved
|
05/15/2023
|
05/19/2023
|
|
|
Engineering Storm Review
|
Failed
|
05/17/2023
|
05/17/2023
|
|
|
|
Add Submittal Item: Misc
Additional Submittal Item Required: Stormwater Site Plan. This is the project's Stormwater Report. Use Worksheets from the City's Single Family Homes webpage or use the template provided in The 2019 Ecology Stormwater Manual for Western Washington found in Section III-3.2 Step 7.
https://www.cityofpuyallup.org/1450/Stormwater-Worksheets-for-Single-Family-
|
|
Add Submittal Item: Misc
Additional Submittal Item Required: Surveyed Site Plan. This must be stamped by a Professional Land surveyor, civil engineer, or other qualified professional. See Section III-3.2 Step 1 in the Ecology Manual for required items on this plan.
|
|
Add Submittal Item: Misc
Additional Submittal Item Required: Geotechnical Report Stamped by Licensed Geotech or other qualified professional. See Section III-3.2 Step 1 in the Ecology Manual for required items on this plan.
|
|
Other/Miscellaneous
Provide any previous stormwater reports. Include calculations in new report to determine if existing rain garden is appropriately sized to mitigate Stormwater and considered the first feasible BMP per the 2019 Ecology Manual requirements.
|
|
Add Submittal Item: Misc
Additional Submittal Item Required: Add Construction SWPPP addressing the 13 elements to pollution prevention. Use Ecology Template to ensure all requirements are met.
https://fortress.wa.gov/ecy/ezshare/wq/permits/CSWGP-SWPPP-Template.docx
|
|
Add Submittal Item: Misc
Additional Submittal Item Required: Fill out Impervious Surface table and resubmit in the Storm Report Bucket. See Provided Table in documents.
|
|
Other/Miscellaneous
2nd submittal does not address the storm requirements requested in the reveiw of the first submittal. Any project that adds more than 2,000 square feet of impervious surface (roofs, driveways, porches, decks, etc.) shall engineer the site drainage to match the requirements of the 2019 Storm Water Management Manual for Western Washington and have their site plan prepared by a civil engineer with a Washington State Engineering License. All previous comments still stand.
|
Building Review
|
Approved
|
05/15/2023
|
05/16/2023
|
|
|
|
See Document Markup
Page 9 - 11: Provide structural engineer seal on all sheets to support structural calculations.
|
|
See Document Markup
Page 9: Provide location of required 14 vents in foundation plan per R408.1 IRC.
|
|
See Document Markup
Page 9: Provide plan on how new foundation will tie into existing. Identify if any existing vents will be affected.
|
|
See Document Markup
SEE STRUCTURAL PLANS FOR ALL REQUIRED ENGINEER DESIGN OR HAVE ENGINEER SEAL DETAIL SHEET.
|
|
Other/Miscellaneous
Provide resubmittal form with response letter how comments were addressed.
Markups on the plans are available to reference in the Documents & Images Portal that are associated with comment letter.
|
Fire Review
|
Approved
|
05/15/2023
|
05/05/2023
|
|
|
Engineering Traffic Review
|
VOID
|
05/15/2023
|
05/03/2023
|
|
|
Engineering Review
|
Approved
|
05/15/2023
|
05/03/2023
|
|
|
|
See Document Markup
Correct parcel numbers to tax parcels 0420355039 & 0420355043. [SITE PLAN, sheet 1 of 1]
|
|
See Document Markup
Label tax parcel 0420355043. [SITE PLAN, sheet 1 of 1]
|
|
See Document Markup
Depict and label the 1' Wide No Access Easement and the 10' Private Utility Easement per AFN 201111095001. [SITE PLAN, sheet 1 of 1]
|
|
Other/Miscellaneous
The applicant shall contact Williams Gas' Matthew Kautzman at matt.kautzman@williams.com or (253) 377-6146 to schedule a survey of the gas pipeline easement adjacent to the property before permit issuance. Matthew may need access to neighbors' property to complete the survey. The applicant shall submit a copy of Matthew's survey approval to the City before proceeding.
|
|
Other/Miscellaneous
If a fire sprinkler protection system is required to be installed, as determined by the Fire Reviewer, a new 1" fire service and a double detector check valve assembly (DDCVA) backflow device will be required to supply the property's fire sprinkler system. Please callout the water size and material on the development plans.
|
|
Other/Miscellaneous
Refer to the CoP Site Plan Requirements attached in the CityView portal to make sure you have all the necessary information depicted on your project’s site plan.
|
|
See Document Markup
An approved reduced pressure backflow assembly (RPBA) device is required to be installed on the domestic water service per City Standard Detail 03.04.02 since the subject property abuts Upper Deer Creek. Depict and label the RPBA on the site plan. [SITE PLAN, sheet 1 of 1]
|
Engineering Storm Review
|
Failed
|
11/18/2022
|
11/22/2022
|
|
|
|
Add Submittal Item: Misc
Additional Submittal Item Required: Stormwater Site Plan. This is the project's Stormwater Report. Use Worksheets from the City's Single Family Homes webpage or use the template provided in The 2019 Ecology Stormwater Manual for Western Washington found in Section III-3.2 Step 7.
https://www.cityofpuyallup.org/1450/Stormwater-Worksheets-for-Single-Family-
|
|
Add Submittal Item: Misc
Additional Submittal Item Required: Surveyed Site Plan. This must be stamped by a Professional Land surveyor, civil engineer, or other qualified professional. See Section III-3.2 Step 1 in the Ecology Manual for required items on this plan.
|
|
Add Submittal Item: Misc
Additional Submittal Item Required: Geotechnical Report Stamped by Licensed Geotech or other qualified professional. See Section III-3.2 Step 1 in the Ecology Manual for required items on this plan.
|
|
Other/Miscellaneous
Provide any previous stormwater reports. Use to include calculations in new report to determine if existing rain garden is appropriately sized to mitigate Stormwater and considered the first feasible BMP per the 2019 Ecology Manual requirements.
|
|
Add Submittal Item: Misc
Additional Submittal Item Required: Add Construction SWPP addressing the 13 elements to pollution prevention. Use Ecology Template to ensure all requirements are met.
https://fortress.wa.gov/ecy/ezshare/wq/permits/CSWGP-SWPPP-Template.docx
|
|
Add Submittal Item: Misc
Additional Submittal Item Required: Fill out Impervious Surface table and resubmit in the Storm Report Bucket. See Provided Table in documents.
|
Fire Review
|
Approved
|
11/17/2022
|
11/21/2022
|
|
|
Engineering Review
|
Failed
|
11/17/2022
|
11/16/2022
|
|
|
|
See Document Markup
Correct parcel numbers to tax parcels 0420355039 & 0420355043. [SITE PLAN, sheet 1 of 1]
|
|
See Document Markup
Label tax parcel 0420355043. [SITE PLAN, sheet 1 of 1]
|
|
See Document Markup
Depict and label the 1' Wide No Access Easement and the 10' Private Utility Easement per AFN 201111095001. [SITE PLAN, sheet 1 of 1]
|
|
Other/Miscellaneous
The applicant shall contact Williams Gas' Matthew Kautzman at matt.kautzman@williams.com or (253) 377-6146 to schedule a survey of the gas pipeline easement adjacent to the property before permit issuance. Matthew may need access to neighbors' property to complete the survey. The applicant shall submit a copy of Matthew's survey approval to the City before proceeding.
|
|
Other/Miscellaneous
If a fire sprinkler protection system is required to be installed, as determined by the Fire Reviewer, a new 1" fire service and a double detector check valve assembly (DDCVA) backflow device will be required to supply the property's fire sprinkler system. Please callout the water size and material on the development plans.
|
|
Other/Miscellaneous
Refer to the CoP Site Plan Requirements attached in the CityView portal to make sure you have all the necessary information depicted on your project’s site plan.
|
|
See Document Markup
An approved reduced pressure backflow assembly (RPBA) device is required to be installed on the domestic water service per City Standard Detail 03.04.02 since the subject property abuts Upper Deer Creek. Depict and label the RPBA on the site plan. [SITE PLAN, sheet 1 of 1]
|
|
Other/Miscellaneous
In accordance with Puyallup Municipal Code 11.08.135, residential infill lot projects that qualify as substantial improvements (the cost of which equals or exceeds 50% of the market value of the structure before the “start of construction” of the improvement) are required to complete improvements along the property's street frontage. Your project will be required to complete frontage improvements which may include curb, gutter, planter strips, street trees, sidewalks, storm drainage, street lighting, and one-half street paving (only required if the existing pavement condition is poor) as determined by Development Engineering. The building permit shall not be issued until the frontage improvement designs have been approved by the City and a right-of-way or civil construction permit issued. A right-of-way permit is required if there is existing vertical curb in good condition and a civil construction permit is required if there is no existing vertical curbing. The building permit shall be conditioned in such a manner that building occupancy will not be granted until the frontage improvements are completed and approved.
The subject site may qualify for the fee-in-lieu program in which the applicant may request and submit justification to pay a fee rather than constructing all or part of the required frontage improvements. Allowance of fee-in-lieu shall be at the discretion of the City and may be denied if the City Engineer determines it will be more beneficial to the public to have frontage improvements built along the street frontage adjoining the property or access to the property. The justification to allow use of the fee-in-lieu program shall not be based on cost savings to the applicant in comparison with constructing required improvement adjacent to the property. If you would like to pursue the fee-in-lieu program, please email a justification letter as outlined above to ycharitou@puyallupwa.gov.
|
Planning Review
|
Approved
|
11/17/2022
|
11/15/2022
|
|
|
Building Review
|
Failed
|
11/17/2022
|
11/10/2022
|
|
|
|
See Document Markup
Page 9 - 11: Provide structural engineer seal on all sheets to support structural calculations.
|
|
See Document Markup
Page 9: Provide location of required 14 vents in foundation plan per R408.1 IRC.
|
|
See Document Markup
Page 9: Provide plan on how new foundation will tie into existing. Identify if any existing vents will be affected.
|
|
See Document Markup
SEE STRUCTURAL PLANS FOR ALL REQUIRED ENGINEER DESIGN OR HAVE ENGINEER SEAL DETAIL SHEET.
|
|
Other/Miscellaneous
Provide resubmittal form with response letter how comments were addressed.
Markups on the plans are available to reference in the Documents & Images Portal that are associated with comment letter.
|
Engineering Traffic Review
|
VOID
|
11/17/2022
|
11/03/2022
|
|
|