Summary

PRRF20221113
Re-Roof
Permit(s) Issued
Alteration/Remodel
WORK SCOPE: • Clean existing roof of all loose dirt and debris prior to reroofing. • Remove and dispose of all existing damaged walk-pads. • Remove “Non-used” penetrations, add metal decking as needed and fill area with new insulation to bring to current roof level. • Remove existing cap flashing along parapet walls and set aside for reuse. • Supply and install new skirt flashing around applicable roof perimeters and all existing HVAC units. • Supply and install new GAF EnergyGuard 1/2" (20psi) rigid insulation over the existing roof. (mechanically attached) • Supply and install new GAF EverGuard 60mil TPO membrane roof system over the entire roof section. (mechanically attached) • Detail all existing pipes, vents, drains and HVAC units with new GAF EverGuard 60mil TPO membrane or GAF TPO Pitch Pockets. • Supply and install new GAF TPO walk pads around all HVAC units. • Remove and replace rotten/damaged existing treated support blocks for piping on this roof section with new 6"x6" treated wood blocks on protective pads. • Reinstall existing cap flashing along parapet walls. • Clean up and haul away any related roofing debris from job site.
07/13/2022
07/19/2022
07/14/2023

Locations

Property
6021010051

6021010051
South Hill Mall - Sears, 3500 South Meridian, Puyallup WA 98373

Reviews

Review Type Outcome Est. Completion Date Completed
Building Review Approved 07/19/2022 07/18/2022

Fees

Paid Fees Amount Paid Owing Date Paid
Building Permit Fee $2,264.95 $2,264.95 Paid 07/19/2022
Building Plan Review Fee $1,472.22 $1,472.22 Paid 07/13/2022
WA State Building Code Council Fee (Commercial) $25.00 $25.00 Paid 07/19/2022
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


Permit(s) will not be issued until outstanding fees have been paid in full. Fee details shown above only include currently payable fees, there might be addtional fees to be paid before issuance.

$0.00

Inspections

Inspection Outcome Requested Scheduled Date Inspected
Comment Building Div Inspection Pending
Monty Johnson ((253) 770-3326)
Roof Sheathing Inspection Pending
Monty Johnson ((253) 770-3326)
Re-Roof Inspection Pending
Monty Johnson ((253) 770-3326)
Building Final Inspection VOID 01/15/2023
CityView System Manger

Conditions

Condition Status Department Category Expiration Date Due Date
Building Permit Standard Conditions Open Standard Conditions
: * Final approval by the Building Official is required prior to use or occupancy.* Work shall not proceed until the inspector has approved the stages of construction.* Surface storm water shall be diverted from the building site and shall not drain onto adjacent properties.* I hereby acknowledge that I have read this Permit/Application, that the information given is correct; that I am the owner or the duly authorized agent of the owner; that plans submitted herewith are in compliance with all applicable city, county and state laws and that all construction will proceed in accordance with said laws. This permit shall expire if work is not commenced with 180 days or if the work is suspended for a period of 180 days. Permits expire two years from issuance. * By leaving the contractor information section blank, I hereby certify further that contractors (general or subcontractors) will not be hired to perform any work in association with this permit. I also certify that if I do choose to hire a contractor (general or subcontractor) I will only hire those contractors that are licensed by the State of Washington. If you are a property owner, contractor or permittee and you are paying for someone to perform the work, they must have a valid contractor registration and the person(s) installing plumbing inside a structure must meet the plumbing certification requirements. If you have any questions regarding these regulations, you may contact the Washington State Department of Labor and Industries or you can find more information on-line at: http://www.lni.wa.gov/TradesLicensing/Contractors/HireCon/default.asp
Re-Roof Conditions Open Standard Conditions
: RE-ROOF 1) PROVIDE MANUFACTURES SPECIFICATIONS AND INSTALLATION DETAILS ON SITE FOR INSPECTION 2) CALL FOR REQUIRED INSPECTIONS PRIOR TO COVER; REQUIRED FOR SHEATHING REPLACEMENT, STRUCTURAL REPAIR OR INSULATION 3) PROVIDE INSPECTION ACCESS 4) PROVIDE A COPY OF THE PERMIT ON SITE ***MUST PROVIDE DRIP EDGE ON ALL ROOF EDGES***

Related Permit & Planning Applications

There are no related items for this permit application.

Documents & Images

Date Uploaded File Type Name
07/18/2022 Form SHM Sears 2022 permit app1 (Flattened)
07/13/2022 Receipt Receipt for transaction:2022-001354
07/19/2022 Letter Permit - Detailed
07/19/2022 Receipt Receipt for transaction:2022-001390
12/16/2022 Letter Permit Expiration Notice