CITY OF PUYALLUP PERMITTING PORTAL

Permit Application Status

PRRF20240884


In order to request inspections, you need to be signed in.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRRF20240884
Re-Roof
Closed
MERIDIAN PLACE LLC
Alteration/Remodel
Remove existing tile roofing and replace with new standing seam metal roofing to match existing adjacent roofing material. - MERIDIAN SHOPPING CENTER FACADE REMODE - PHASE II
05/30/2024
06/10/2024
08/17/2025
02/18/2025

Locations

Reviews

Documents Returned For Corrections

Date Returned Name
06/06/2024 SITE PLAN (Stamped)
06/06/2024 ROOF PANELS (Stamped)
06/06/2024 ROOFING MATERIAL DOC (Stamped)
Review Type Outcome Est. Completion Date Completed
Building Review Approved 06/10/2024 06/04/2024

Fees

Paid Fees Amount Paid Owing Date Paid
Building Permit Fee $818.75 $818.75 Paid 06/10/2024
Building Plan Review Fee $532.19 $532.19 Paid 05/30/2024
WA State Building Code Council Fee (Commercial) $25.00 $25.00 Paid 06/10/2024
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


Permit(s) will not be issued until outstanding fees have been paid in full. Fee details shown above only include currently payable fees, there might be addtional fees to be paid before issuance.

$0.00

Inspections

Inspection Outcome Requested Scheduled Date Inspected
Comment Building Div Inspection Not Ready 10/10/2024 10/10/2024 10/10/2024
Shannon King ((253) 840-6684)
Roof Sheathing Inspection Not Ready 10/14/2024 10/14/2024 10/14/2024
Shannon King ((253) 840-6684)
Re-Roof Inspection Not Ready 10/15/2024 10/15/2024 10/15/2024
Shannon King ((253) 840-6684)
Corrections:


Other/Miscellaneous
Carried Forward
10/15/2024
contractor will inspect sheathing of infill frame at phase 1 inspection.

Roof Sheathing Inspection Partial Pass 10/24/2024 10/24/2024 10/24/2024
Shannon King ((253) 840-6684)
Roof Sheathing Inspection Partial Pass 11/18/2024 11/18/2024 11/18/2024
Shannon King ((253) 840-6684)
Frame Inspection Not Ready 1/10/2025 1/10/2025 01/10/2025
Monty Johnson ((253) 770-3326)
Corrections:


Other/Miscellaneous
Carried Forward
01/10/2025
infill frame completed without inspection or plans from architect, have ladder set up for inspection.

Frame Inspection Failed 1/13/2025 1/13/2025 01/13/2025
Shannon King ((253) 840-6684)
Corrections:


Other/Miscellaneous
Carried Forward
01/13/2025
1 ;complete install of hangers as discussed with contractor.

Comment Building Div Inspection Partial Pass 1/15/2025 1/15/2025 01/15/2025
Shannon King ((253) 840-6684)
Corrections:


Other/Miscellaneous
Carried Forward
01/15/2025
1 ; complete drywall nailing at soffit in front of pet care clinic.

Comment Building Div Inspection Partial Pass 1/17/2025 1/17/2025 01/17/2025
Monty Johnson ((253) 770-3326)
Corrections:


Other/Miscellaneous
Resolved
01/17/2025
1 ; complete drywall nailing at soffit in front of pet care clinic.

Other/Miscellaneous
Carried Forward
01/17/2025
south side soffit ok

Re-Roof Inspection VOID 02/18/2025
Shannon King ((253) 840-6684)
Corrections:


Other/Miscellaneous
Outstanding
10/15/2024
contractor will inspect sheathing of infill frame at phase 1 inspection.

Roof Sheathing Inspection VOID 02/18/2025
Shannon King ((253) 840-6684)
Frame Inspection VOID 02/18/2025
Shannon King ((253) 840-6684)
Corrections:


Other/Miscellaneous
Outstanding
01/13/2025
1 ;complete install of hangers as discussed with contractor.

Conditions

Condition Status Category
Building Permit Standard Conditions Open Standard Conditions
Building Division
* Final approval by the Building Official is required prior to use or occupancy.* Work shall not proceed until the inspector has approved the stages of construction.* Surface storm water shall be diverted from the building site and shall not drain onto adjacent properties.* I hereby acknowledge that I have read this Permit/Application, that the information given is correct; that I am the owner or the duly authorized agent of the owner; that plans submitted herewith are in compliance with all applicable city, county and state laws and that all construction will proceed in accordance with said laws. This permit shall expire if work is not commenced with 180 days or if the work is suspended for a period of 180 days. Permits expire two years from issuance. * By leaving the contractor information section blank, I hereby certify further that contractors (general or subcontractors) will not be hired to perform any work in association with this permit. I also certify that if I do choose to hire a contractor (general or subcontractor) I will only hire those contractors that are licensed by the State of Washington. If you are a property owner, contractor or permittee and you are paying for someone to perform the work, they must have a valid contractor registration and the person(s) installing plumbing inside a structure must meet the plumbing certification requirements. If you have any questions regarding these regulations, you may contact the Washington State Department of Labor and Industries or you can find more information on-line at: http://www.lni.wa.gov/TradesLicensing/Contractors/HireCon/default.asp
Re-Roof Conditions Open Standard Conditions
RE-ROOF 1) PROVIDE MANUFACTURES SPECIFICATIONS AND INSTALLATION DETAILS ON SITE FOR INSPECTION 2) CALL FOR REQUIRED INSPECTIONS PRIOR TO COVER; REQUIRED FOR SHEATHING REPLACEMENT, STRUCTURAL REPAIR OR INSULATION 3) PROVIDE INSPECTION ACCESS 4) PROVIDE A COPY OF THE PERMIT ON SITE ***MUST PROVIDE DRIP EDGE ON ALL ROOF EDGES***

Related Permit & Planning Applications

Reference Number Status Type
PRFS20241764 Closed Fire Sprinklers

Documents & Images

Date Uploaded File Type Name
05/30/2024 Receipt Receipt for transaction:2024-001134
06/06/2024 Plans SITE PLAN (Stamped)
06/06/2024 Other ROOF PANELS (Stamped)
06/06/2024 Other ROOFING MATERIAL DOC (Stamped)
06/10/2024 Letter Permit - Detailed
06/10/2024 Receipt Receipt for transaction:2024-001223
10/10/2024 Report Inspection Report (Comment Building Div Inspection)
10/14/2024 Report Inspection Report (Roof Sheathing Inspection)
10/15/2024 Report Inspection Report (Re-Roof Inspection)
10/24/2024 Report Inspection Report (Roof Sheathing Inspection)
01/13/2025 Report Inspection Report (Frame Inspection)
02/18/2025 Report Inspection Report (Building Final Inspection)


Should you need assistance, please contact the Permit Center at (253) 864-4165 option 1.