CITY OF PUYALLUP PERMITTING PORTAL

Engineering Permit Application Status

PRROW20220920


In order to request inspections, you need to be signed in.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRROW20220920
Right-of-Way Permit
Canceled
LIT VIKING PUYALLUP LLC
Other
- SPLICE INTO EXISTING SPLICE CASE - 6.9.22 CANCELED: WRONG APPLICATION TYPE, CUSTOMER TO RESUBMIT UNDER FRANCHISE & MAKE $$-JF
06/09/2022

Locations

Reviews

There are no reviews for this permit application, or you are not authorized to view them.

Fees

Paid Fees Amount Paid Owing Date Paid
None $0.00 $0.00 $0.00
Outstanding Fees Amount Paid Owing Date Paid
General Engineering Inspection Fee $130.00 $0.00 Not payable Not Paid
ROW Permit Fee $80.00 $0.00 Not payable Not Paid
Traffic Control Permit Fee $50.00 $0.00 Not payable Not Paid
Traffic Control Plan Review Fee $40.00 $0.00 Not payable Not Paid


Permit(s) will not be issued until outstanding fees have been paid in full. Fee details shown above only include currently payable fees, there might be addtional fees to be paid before issuance.

$0.00

Inspections

There are no inspections for this engineering permit application, or you are not authorized to view them.

Conditions

Condition Status Category
Right Of Way Permit Conditions Open Standard Conditions
Engineering Division
Development Engineering standard right-of-way conditions: Standard Follow approved Traffic Control Plan (TCP). Work between the hours of 9AM & 3PM. Call Comm Center day(s) of lane closure at 253-841-5431. - Inspection time performed during a regular 8 hour day Monday - Friday 7:00 am - 5:00 pm is included in the permit fee. Inspection time performed outside of those hours are charged to the permit holder at a rate of $130 per hour with a three hour minimum. - Distance between cones equals speed limit in unit feet. - Taper length equals width of offset times speed limit squared divided by 60. L = WS² /60 where W= lane width and S = speed limit. - Sign spacing shall be 100 feet when speed limit is 30 MPH or less. - Sign spacing shall be 350 feet when speed limit is greater than 30 MPH. - Distance between signs is mandatory unless field conditions determine otherwise. - The applicant or contractor shall request a job start inspection through the CityView Portal at least 48 hours in advance of starting work and a final inspection when all work and restoration are complete. - I agree to have the approved permit on site at all times. - Utility inspections are required prior to backfilling. - No work shall be done in or on the public right of way without a licensed and bonded contractor first obtaining a right of way permit. - I agree to keep the existing right of way free of debris and dirt. - I agree to call the Utility Notification Center at 1-800-424-5555 before beginning any excavation. Call before you dig, it's the law. - I agree to adhere to the approved Traffic Control Plan. - I agree to perform all work in accordance with City's Standards. Any curb, gutter or sidewalk broken now or during construction shall be removed and replaced. - I hereby acknowledge that I have read and understand the contents of this permit and I hereby state that the information I have supplied is true and correct. Indemnification / Hold Harmless: The permittee shall defend, indemnify and hold the public entity, its officers, officials, employees and volunteers harmless from any and all claims, injuries, damages, losses or suits including attorney fees, arising out of or in connection with activities or operations performed by the permittee or on the permittee's behalf out of issuance of this permit, except for injuries and damages caused by the sole negligence of the public entity. However, should a court of competent jurisdiction determine that RCW 4.24.115 applies to this permit, then the permittee agrees to defend, indemnify and hold the public entity, its officers, officials, employees and volunteers harmless to the maximum extent permitted thereunder. It is further specifically and expressly understood that the indemnification provided herein constitutes the permittee's waiver of immunity under industrial insurance, Title 51 RCW, solely for the purposes of this indemnification. This waiver has been mutually negotiated by the parties. the provisions of this section shall survive the expiration or termination of this agreement.

Related Permit & Planning Applications

There are no related items for this engineering permit application.

Documents & Images

Date Uploaded File Type Name
06/09/2022 Letter Incomplete Application Notice


Should you need assistance, please contact the Permit Center at (253) 864-4165 option 1.