CITY OF PUYALLUP PERMITTING PORTAL
Permit Application Status
PRSG20221018
Paid Fees | Amount | Paid | Owing | Date Paid |
---|---|---|---|---|
Building Permit Fee | $40.25 | $40.25 | Paid | 07/14/2022 |
Building Plan Review Fee | $26.16 | $26.16 | Paid | 06/28/2022 |
WA State Building Code Council Fee (Commercial) | $25.00 | $25.00 | Paid | 07/14/2022 |
Outstanding Fees | Amount | Paid | Owing | Date Paid |
No outstanding fees. | ||||
Totals: | $91.41 | $91.41 | $0.00 |
Permit(s) will not be issued until outstanding fees have been paid in full. Fee details shown above only include currently payable fees, there might be addtional fees to be paid before issuance.
$0.00
Inspection | Outcome | Requested | Scheduled | Date Inspected |
---|---|---|---|---|
Sign Final Inspection | Pending | |||
Shannon King ((253) 840-6684) | ||||
Corrections:
Other/Miscellaneous
Outstanding
01/11/2023
1: provide sign attachment inspection approval prior to sign final.
2: contractor will need to remove sign face to inspect fasteners.
|
||||
Sign Attachment Inspection | Pending | |||
Shannon King ((253) 840-6684) | ||||
Corrections:
Other/Miscellaneous
Outstanding
01/11/2023
1: provide sign attachment inspection approval prior to sign final.
2: contractor will need to remove sign face to inspect fasteners.
|
||||
Sign Final Inspection | Failed | 11/30/2022 | 11/30/2022 | 11/30/2022 |
Shannon King ((253) 840-6684) | ||||
Corrections:
Other/Miscellaneous
Carried Forward
11/30/2022
1;provide City approved plans on-site at time of inspection.
2 ; provide L&I electrical final at time of sign final.
not ready
|
||||
Sign Attachment Inspection | Failed | 11/30/2022 | 11/30/2022 | 11/30/2022 |
Shannon King ((253) 840-6684) | ||||
Corrections:
Other/Miscellaneous
Carried Forward
11/30/2022
1;provide City approved plans on-site at time of inspection.
2 ; provide L&I electrical final at time of sign final.
not ready
|
||||
Sign Final Inspection | Failed | 1/11/2023 | 1/11/2023 | 01/11/2023 |
Shannon King ((253) 840-6684) | ||||
Corrections:
Other/Miscellaneous
Resolved
01/11/2023
1;provide City approved plans on-site at time of inspection.
2 ; provide L&I electrical final at time of sign final.
not ready
|
||||
Other/Miscellaneous
Carried Forward
01/11/2023
1: provide sign attachment inspection approval prior to sign final.
2: contractor will need to remove sign face to inspect fasteners.
|
||||
Sign Attachment Inspection | Failed | 1/11/2023 | 1/11/2023 | 01/11/2023 |
Shannon King ((253) 840-6684) | ||||
Corrections:
Other/Miscellaneous
Resolved
01/11/2023
1;provide City approved plans on-site at time of inspection.
2 ; provide L&I electrical final at time of sign final.
not ready
|
||||
Other/Miscellaneous
Carried Forward
01/11/2023
1: provide sign attachment inspection approval prior to sign final.
2: contractor will need to remove sign face to inspect fasteners.
|
Condition | Status | Category |
---|---|---|
Building Permit Standard Conditions | Open | Standard Conditions |
* Final approval by the Building Official is required prior to use or occupancy.* Work shall not proceed until the inspector has approved the stages of construction.* Surface storm water shall be diverted from the building site and shall not drain onto adjacent properties.* I hereby acknowledge that I have read this Permit/Application, that the information given is correct; that I am the owner or the duly authorized agent of the owner; that plans submitted herewith are in compliance with all applicable city, county and state laws and that all construction will proceed in accordance with said laws. This permit shall expire if work is not commenced with 180 days or if the work is suspended for a period of 180 days. Permits expire two years from issuance. * By leaving the contractor information section blank, I hereby certify further that contractors (general or subcontractors) will not be hired to perform any work in association with this permit. I also certify that if I do choose to hire a contractor (general or subcontractor) I will only hire those contractors that are licensed by the State of Washington. If you are a property owner, contractor or permittee and you are paying for someone to perform the work, they must have a valid contractor registration and the person(s) installing plumbing inside a structure must meet the plumbing certification requirements. If you have any questions regarding these regulations, you may contact the Washington State Department of Labor and Industries or you can find more information on-line at: http://www.lni.wa.gov/TradesLicensing/Contractors/HireCon/default.asp
|
There are no related items for this permit application.
Date Uploaded | File Type | Name |
---|---|---|
06/28/2022 | Receipt | Receipt for transaction:2022-001207 |
07/14/2022 | Form | Puyallup Papa Murphys WA146 application1 (Flattened) |
07/14/2022 | Other | Puyallup Papa Murphys Wa146 plan set and site plan (Stamped) |
07/14/2022 | Letter | Permit - Detailed |
07/14/2022 | Receipt | Receipt for transaction:2022-001359 |
11/30/2022 | Report | Inspection Report (Sign Final Inspection) |
11/30/2022 | Report | Inspection Report (Sign Attachment Inspection) |
01/11/2023 | Report | Inspection Report (Sign Final Inspection) |
06/07/2023 | Letter | Permit Expiration Notice |
Should you need assistance, please contact the Permit Center at (253) 864-4165 option 1.
Powered by CityView