CITY OF PUYALLUP PERMITTING PORTAL

Engineering Permit Application Status

PRUSR20221164


In order to request inspections, you need to be signed in.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRUSR20221164
Utility Service Repair/PRIVATE PROPERTY ONLY
Closed
ROSS GLEN A & REBECCA K
Repair
Water Line Repair
07/26/2022
07/26/2022
02/13/2023
08/17/2022

Locations

Reviews

There are no reviews for this permit application, or you are not authorized to view them.

Fees

Paid Fees Amount Paid Owing Date Paid
Water Line Repair Inspection Fee (Private) $130.00 $130.00 Paid 07/26/2022
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


Permit(s) will not be issued until outstanding fees have been paid in full. Fee details shown above only include currently payable fees, there might be addtional fees to be paid before issuance.

$0.00

Inspections

Inspection Outcome Requested Scheduled Date Inspected
Job Start Inspection Failed 7/27/2022 07/27/2022
Jason Little ((253) 435-3636)
Engineering Final Inspection Failed 7/27/2022 7/27/2022 07/27/2022
Jason Little ((253) 435-3636)
Comment Engineering Div Inspection Passed w/ Conditions 7/28/2022 07/28/2022
Jason Little ((253) 435-3636)
Engineering Final Inspection Failed 7/29/2022 07/29/2022
Jason Little ((253) 435-3636)
Engineering Final Inspection Passed w/ Conditions 8/15/2022 08/17/2022
Jason Little ((253) 435-3636)

Conditions

Condition Status Department Category Expiration Date Due Date
Right Of Way Permit Conditions Open Engineering Division Standard Conditions
: Development Engineering standard right-of-way conditions: Site-specific Conditions: Applicant/Contractor Responsibility: 1. The issued permit and traffic control plan(s) are always required to be available at the job site. The applicant shall be subject to a triple permit fee for failing to have a valid permit on site. 2. The applicant/contractor shall call the Utility Notification Center at 1-800-424-5555 before beginning any excavation. Call before you dig, it's the law. 3. The applicant/contractor shall notify the City 24-48 hours prior to starting work by requesting an inspection through the CityView portal. Weekend and night work require a minimum of 48 business hours’ advanced coordination with a City inspector. 4. The applicant/contractor shall notify the City prior to site restoration, immediately after all work and restoration are complete, and when the site is ready for final inspection. The applicant/contractor shall request a final inspection through the CityView portal prior to the permit expiration date. General Conditions: 1. Comply with all permit conditions and the Traffic Control Plans (TCP) issued by the City. 2. Follow the allowed work hours as listed on the issued permit or on each page of the TCP. 3. If a travel lane will be closed, the applicant/contractor shall call the Communications Center at 253-287-4456 prior to starting work on day of closure and again once the lane is reopened. 4. Spotter must be available to assist with pedestrians if needed. 5. Request all inspections through the CityView portal on the City website. Utility inspections are required prior to backfilling. 6. Please utilize the traffic control standards below in addition to the TCP: - Traffic control devices shall be 28-inch retro-reflective cones. - Taper length equals width of offset times speed limit squared divided by 60. - Sign spacing shall be 100 feet when speed limit is 30 mph or less. - Sign spacing shall be 350 feet when speed limit is greater than 30 mph. - Distance between cones equals speed limit in unit-feet. - Distance between signs is mandatory unless field conditions determine otherwise. - Travel lane width must be a minimum of 11 feet at all times. - Any and all flaggers and spotters shall remain in radio contact at all times. 7. Open cut is not permitted without prior approval from the City. 8. Do not park vehicles on City sidewalk. Any public curb, gutter, or sidewalk broken now or during construction shall be removed and replaced per City Standards. The public right-of-way shall be kept clear of dirt and debris. 9. Inspections performed during a regular 8-hour day Monday through Friday 7:00 am - 5:00 pm is included in the permit fee. Inspection time performed outside of these hours are charged to the permit holder at a rate of $130.00 per hour with a three-hour minimum. 10. The applicant/contractor shall comply with Puyallup Municipal Code Chapter 11.05 while working in the public right-of-way. 11. The applicant/contractor hereby agrees that they have read and understood the contents of this permit and I hereby state that the information they have supplied is true and correct. Indemnification / Hold Harmless: The Permittee shall defend, indemnify and hold the Public Entity, its officers, officials, employees and volunteers harmless from any and all claims, injuries, damages, losses or suits including attorney fees, arising out of or in connection with activities or operations performed by the Permittee or on the Permittee's behalf out of issuance of this Permit, except for injuries and damages caused by the sole negligence of the Public Entity. However, should a court of competent jurisdiction determine that RCW 4.24.115 applies to this Permit, then the Permittee agrees to defend, indemnify and hold the Public Entity, its officers, officials, employees and volunteers harmless to the maximum extent permitted thereunder. It is further specifically and expressly understood that the indemnification provided herein constitutes the Permittee's waiver of immunity under Industrial Insurance, Title 51 RCW, solely for the purposes of this indemnification. This waiver has been mutually negotiated by the parties. The provisions of this section shall survive the expiration or termination of this Agreement.
Utility Service Repair Standard Condition Open Standard Conditions
: Development Engineering standard utility service repair conditions: - Work between the hours of 9 AM & 3 PM. - Call communication center day(s) of lane closure at 253-287-4456. - Prior to starting site work; request inspection for erosion and sediment. - Utility inspections are required prior to backfilling. - Inspection time performed during a regular 8 hour day Monday - Friday 7:00 AM - 5:00 PM is included in the permit fee. inspection time performed outside of those hours are charged to the permit holder at a rate of $130 per hour with a three hour minimum. - Applicant/contractor shall notify the City within 48 hours prior to work start date and also to close the permit when all work and restoration are complete and ready for final inspection. - I agree to have the approved permit on site at all times. - The applicant is responsible to call the engineering inspection line at 253-435-3650 to schedule a utility inspection prior to backfilling. - No work shall be done in or on the public right of way without a licensed and bonded contractor first obtaining a right-of-way permit. - I agree to keep the existing right of way free of debris and dirt. - I agree to call the utility notification center at 1-800-424-5555 before beginning any excavation. Call before you dig, it's the law. - I agree to adhere to the approved traffic control plan. - I agree to perform all work in accordance with City's standards. Any curb, gutter or sidewalk broken now or during construction shall be removed and replaced. - I hereby acknowledge that i have read and understand the contents of this permit and I hereby state that the information I have supplied is true and correct. Indemnification / Hold Harmless: The permittee shall defend, indemnify and hold the public entity, its officers, officials, employees and volunteers harmless from any and all claims, injuries, damages, losses or suits including attorney fees, arising out of or in connection with activities or operations performed by the permittee or on the permittee's behalf out of issuance of this permit, except for injuries and damages caused by the sole negligence of the public entity. However, should a court of competent jurisdiction determine that RCW 4.24.115 applies to this permit, then the permittee agrees to defend, indemnify and hold the public entity, its officers, officials, employees and volunteers harmless to the maximum extent permitted thereunder. It is further specifically and expressly understood that the indemnification provided herein constitutes the permittee's waiver of immunity under industrial insurance, Title 51 RCW, solely for the purposes of this indemnification. This waiver has been mutually negotiated by the parties. the provisions of this section shall survive the expiration or termination of this agreement.

Related Permit & Planning Applications

There are no related items for this engineering permit application.

Documents & Images