CITY OF PUYALLUP PERMITTING PORTAL

Permit Application Status

PRCA20231634


In order to request inspections, you need to be signed in.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRCA20231634
Commercial - Addition
Permit(s) Issued
KURKOV DMITRIY
Addition
Remodel of existing McDonald's including: exterior facade upgrade w/kitchen area addition, demo and construction of non-structural partitions, remodel of dropped ceiling in Dining and Customer Service areas, new order counters, new menu boards, new kitchen equipment, new seating/decor in dining and revision of existing sidewalk to accommodate door relocation. `McDONALD'S REMODEL/ADDITION
11/17/2023
08/06/2024
06/14/2025

Locations

Reviews

Review Type Outcome Est. Completion Date Completed
Fire Review Approved 05/16/2024 05/20/2024
Building Review Approved 05/16/2024 05/16/2024
Engineering Review Approved 05/16/2024 05/09/2024
Planning Review Approved 05/16/2024 05/07/2024
Planning Review Approved 12/22/2023 01/02/2024
Building Review Failed 12/22/2023 12/19/2023
Fire Review Failed 12/22/2023 12/18/2023
Engineering Review Approved 12/22/2023 11/29/2023

Fees

Paid Fees Amount Paid Owing Date Paid
Fire Review Fee (Commercial Building) $265.00 $265.00 Paid 08/06/2024
Building Permit Fee $2,393.75 $2,393.75 Paid 08/06/2024
Backflow Preventor Fee $26.00 $26.00 Paid 11/22/2023
Plumbing Permit Fee $40.00 $40.00 Paid 08/06/2024
Drinking Fountain, Water Cooler, Ice Machine Fee $40.25 $40.25 Paid 08/06/2024
Building Plan Review Fee $1,555.94 $1,555.94 Paid 11/22/2023
Plumbing Plan Review Fee $69.06 $69.06 Paid 11/22/2023
WA State Building Code Council Fee (Commercial) $25.00 $25.00 Paid 08/06/2024
Mechanical Duct Work Fee $24.00 $24.00 Paid 08/06/2024
Mechanical Permit Fee $40.00 $40.00 Paid 08/06/2024
Mechanical Plan Review Fee $41.60 $41.60 Paid 11/22/2023
Sewer System Development ChargeFee - Tenant Improvment/Addition $3,825.45 $3,825.45 Paid 08/06/2024
Water System Development ChargeFee - Tenant Improvment/Addition $349.61 $349.61 Paid 08/06/2024
Resubmittal Fee $180.00 $180.00 Paid 05/02/2024
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


Permit(s) will not be issued until outstanding fees have been paid in full. Fee details shown above only include currently payable fees, there might be addtional fees to be paid before issuance.

$0.00

Inspections

Inspection Outcome Requested Scheduled Date Inspected
Shear Wall Inspection Pending
Kevin Spruell ((253) 841-5590)
Hydronic Piping Inspection Pending
Kevin Spruell ((253) 841-5590)
Refrigeration Line Test Inspection Pending
Kevin Spruell ((253) 841-5590)
Medical Gas Inspection Pending
Kevin Spruell ((253) 841-5590)
Comment Building Div Inspection Pending
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Outstanding
09/09/2024
date of inspection 9/9/2024 1.discussed footings and energy at slab

Comment Engineering Div Inspection Pending
Foundation/Rebar Inspection Pending
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Outstanding
09/16/2024
9/16/2024 see notes in footing inspection todays date

Slab/Insulation Inspection Pending
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Outstanding
09/16/2024
9/16/2024 see notes in footing inspection todays date

Footing/Setback Inspection Pending
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Outstanding
09/26/2024
9/16/2024 1.footings, slab , insulation, vapor barrier and exterior portion of pier pad approved to pour per special inspection south east corner of building

Other/Miscellaneous
Outstanding
09/26/2024
date of inspection 9/26/2024 1.interior pier pad at drive thru approved to pour

Combination Frame And Rough In Inspection Pending
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Outstanding
10/09/2024
date of inspection 9/25/2024/ 1.underslab plumbing and walls approved as marked up on city approved plans pg A1.0 2. complete hangers at ceiling framing bathrooms 3. complete anchor bolts as discussed with contractor

Other/Miscellaneous
Outstanding
10/09/2024
date of inspection 10/9/2024 1.provide electrical cover for second phase 2.complete anchors at bottom plate 3.complete firestop 4.provide positive connection at beam at wall by drive thru 5.2nd phase underslab plumbing and above ground DWV and supply approved 6. slab approved to pour 7.ok to insulate walls only

Frame Inspection Pending
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Outstanding
10/10/2024
date of inspection 9/26/2024 1.hangers at ceiling in bathrooms approved 2.missing anchor bolts approved 3.framing at riser room approved

Energy (Insulation) Inspection Pending
Kevin Spruell ((253) 841-5590)
Exhaust Hood Inspection Pending
Kevin Spruell ((253) 841-5590)
Exhaust/Vent Fans Inspection Pending
Shannon King ((253) 840-6684)
Other/Miscellaneous
Outstanding
11/07/2024
provide positive attachment of diffuser to main and cross tee of suspended ceiling at S.W. corner of building as discussed with contractor.

Plumbing Rough In Inspection Pending
Shannon King ((253) 840-6684)
Other/Miscellaneous
Outstanding
11/08/2024
1 ; test failed on gas pipe test. ( fix leak and retest system)

Firewall/Firestop Inspection Pending
Shannon King ((253) 840-6684)
Fire Final Inspection Pending
David Drake ((253) 864-4171)
Other/Miscellaneous
Outstanding
12/04/2024
1. Cut concrete out around both fire sprinkler risers. 2" minimum clearance. 2. Install lock on PIV and provide key for KNOX Box. 3. Install KNOX Box. 4. Install pipe bollard in front of PIV for vehicle impact protection. 5. TCO approved for Fire, Building approval required prior to opening for public and employees.

Mechanical Final Inspection Pending
Shannon King ((253) 840-6684)
Other/Miscellaneous
Outstanding
12/04/2024
1 ; provide positive attachment of mechanical equipment to roof. 2 ; seal roof jacks of refrigerant line sets on roof.

Building Final Inspection Pending
Shannon King ((253) 840-6684)
Other/Miscellaneous
Outstanding
12/05/2024
1 ; T.C.O. approved for 30 days from 12/5/2024. 2 ; provide all City Dept. final sign-off approval prior to Building final. 3 ; complete mechanical final corrections prior to building final inspection approval.

Footing/Setback Inspection Not Ready 9/6/2024 9/6/2024 09/06/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Carried Forward
09/06/2024
1.complete footings per city approved plans 2.not ready

Foundation/Rebar Inspection Not Ready 9/6/2024 9/6/2024 09/09/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Carried Forward
09/09/2024
date of inspection 9/6/2024 1.see notes on footing inspection todays date 2 provide E and S inspection approval prior to scheduling next inspection

Slab/Insulation Inspection Not Ready 9/6/2024 9/6/2024 09/09/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Carried Forward
09/09/2024
date of inspection 9/6/2024 1. see notes on footing inspection todays date

Comment Building Div Inspection Not Ready 9/9/2024 9/9/2024 09/09/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Carried Forward
09/09/2024
date of inspection 9/9/2024 1.discussed footings and energy at slab

Comment Engineering Div Inspection Partial Pass 9/10/2024 9/10/2024 09/10/2024
Michael Rosenau ((253) 344-6753)
Footing/Setback Inspection Partial Pass 9/16/2024 9/16/2024 09/16/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Resolved
09/16/2024
1.complete footings per city approved plans 2.not ready

Other/Miscellaneous
Carried Forward
09/16/2024
9/16/2024 1.footings, slab , insulation, vapor barrier and exterior portion of pier pad approved to pour per special inspection south east corner of building

Foundation/Rebar Inspection Partial Pass 9/16/2024 9/16/2024 09/16/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Resolved
09/16/2024
date of inspection 9/6/2024 1.see notes on footing inspection todays date 2 provide E and S inspection approval prior to scheduling next inspection

Other/Miscellaneous
Carried Forward
09/16/2024
9/16/2024 see notes in footing inspection todays date

Slab/Insulation Inspection Partial Pass 9/16/2024 9/16/2024 09/16/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Resolved
09/16/2024
date of inspection 9/6/2024 1. see notes on footing inspection todays date

Other/Miscellaneous
Carried Forward
09/16/2024
9/16/2024 see notes in footing inspection todays date

Plumbing Rough In Inspection Failed 9/20/2024 9/20/2024 09/20/2024
Monty Johnson ((253) 770-3326)
Other/Miscellaneous
Carried Forward
09/20/2024
provide test on plumbing as discussed

Frame Inspection Failed 9/20/2024 9/20/2024 09/20/2024
Monty Johnson ((253) 770-3326)
Other/Miscellaneous
Carried Forward
09/20/2024
1:complete polyseal and rough ins

Plumbing Rough In Inspection Failed 9/23/2024 9/23/2024 09/23/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Carried Forward
09/23/2024
date of inspection 9/23/2024 1.complete all plumbing R/I and put on test at time of next inspection as discussed with contractor

Frame Inspection Partial Pass 9/23/2024 9/23/2024 09/23/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Carried Forward
09/23/2024
date of inspection 9/23/2024 1.complete all R/I prior to calling in this inspection as discussed with contractor 2.complete min size of footing in interior by drive thru as discussed with contractor 3.interior footing in south east corner of building approved per special inspection

Plumbing Rough In Inspection Failed 9/24/2024 9/24/2024 09/24/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Carried Forward
09/24/2024
date of inspection 9/23/2024 1.complete all plumbing R/I and put on test at time of next inspection as discussed with contractor

Other/Miscellaneous
Carried Forward
09/24/2024
date of inspection 9/24/2024 1. provide comments from EOR on dwv running thru bearing point pier pad at drive thru area 2. provide test on dwv as discussed with contractor at time of next inspection

Wallboard / Drywall Inspection Partial Pass 9/25/2024 9/25/2024 09/26/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Carried Forward
09/26/2024
date of inspection 9/25/2024 1.north wall in kitchen area approved

Combination Frame And Rough In Inspection Partial Pass 9/25/2024 9/25/2024 09/26/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Carried Forward
09/26/2024
date of inspection 9/25/2024/ 1.underslab plumbing and walls approved as marked up on city approved plans pg A1.0 2. complete hangers at ceiling framing bathrooms 3. complete anchor bolts as discussed with contractor

Footing/Setback Inspection Partial Pass 9/26/2024 9/26/2024 09/26/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Carried Forward
09/26/2024
9/16/2024 1.footings, slab , insulation, vapor barrier and exterior portion of pier pad approved to pour per special inspection south east corner of building

Other/Miscellaneous
Carried Forward
09/26/2024
date of inspection 9/26/2024 1.interior pier pad at drive thru approved to pour

Frame Inspection Partial Pass 9/26/2024 9/26/2024 09/26/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Resolved
09/26/2024
date of inspection 9/23/2024 1.complete all R/I prior to calling in this inspection as discussed with contractor 2.complete min size of footing in interior by drive thru as discussed with contractor 3.interior footing in south east corner of building approved per special inspection

Other/Miscellaneous
Carried Forward
09/26/2024
date of inspection 9/26/2024 1.hangers at ceiling in bathrooms approved 2.missing anchor bolts approved 3.framing at riser room approved

Wallboard / Drywall Inspection Failed 10/4/2024 10/4/2024 10/05/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Carried Forward
10/05/2024
date of inspection 9/25/2024 1.north wall in kitchen area approved

Other/Miscellaneous
Carried Forward
10/05/2024
date of inspection 10/5/2024 THIS WAS EXTERIOR SHEAR WALL INSPECTION 1.complete panel edge blocking and shear nailing per city approved plans

Combination Frame And Rough In Inspection Partial Pass 10/9/2024 10/9/2024 10/09/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Carried Forward
10/09/2024
date of inspection 9/25/2024/ 1.underslab plumbing and walls approved as marked up on city approved plans pg A1.0 2. complete hangers at ceiling framing bathrooms 3. complete anchor bolts as discussed with contractor

Other/Miscellaneous
Resolved
10/10/2024
date of inspection 10/9/2024 1.provide electrical cover for second phase 2.complete anchors at bottom plate 3.complete firestop 4.provide positive connection at beam at wall by drive thru 5.2nd phase underslab plumbing and above ground DWV and supply approved 6. slab approved to pour 7.ok to insulate walls only

Frame Inspection Partial Pass 10/10/2024 10/10/2024 10/10/2024
Shannon King ((253) 840-6684)
Other/Miscellaneous
Carried Forward
10/10/2024
date of inspection 9/26/2024 1.hangers at ceiling in bathrooms approved 2.missing anchor bolts approved 3.framing at riser room approved

Energy (Insulation) Inspection Partial Pass 10/15/2024 10/15/2024 10/15/2024
Shannon King ((253) 840-6684)
Exhaust Hood Inspection Not Ready 10/22/2024 10/22/2024 10/22/2024
Shannon King ((253) 840-6684)
Other/Miscellaneous
Carried Forward
10/22/2024
provide install instructions and access to inspect overlap of duct wrap as per install instructions.

Exhaust Hood Inspection Partial Pass 10/24/2024 10/24/2024 10/24/2024
Shannon King ((253) 840-6684)
Other/Miscellaneous
Resolved
10/24/2024
provide install instructions and access to inspect overlap of duct wrap as per install instructions.

Plumbing Rough In Inspection Failed 11/7/2024 11/7/2024 11/07/2024
Shannon King ((253) 840-6684)
Other/Miscellaneous
Resolved
11/07/2024
date of inspection 9/23/2024 1.complete all plumbing R/I and put on test at time of next inspection as discussed with contractor

Other/Miscellaneous
Resolved
11/07/2024
date of inspection 9/24/2024 1. provide comments from EOR on dwv running thru bearing point pier pad at drive thru area 2. provide test on dwv as discussed with contractor at time of next inspection

Other/Miscellaneous
Carried Forward
11/07/2024
1 ; test failed on gas pipe test. ( fix leak and retest system)

Exhaust/Vent Fans Inspection Failed 11/7/2024 11/7/2024 11/07/2024
Shannon King ((253) 840-6684)
Other/Miscellaneous
Carried Forward
11/07/2024
provide positive attachment of diffuser to main and cross tee of suspended ceiling at S.W. corner of building as discussed with contractor.

Ceiling Grid/T-Bar Inspection Failed 11/7/2024 11/7/2024 11/07/2024
Shannon King ((253) 840-6684)
Other/Miscellaneous
Carried Forward
11/07/2024
1 ; complete all ceiling grid requirements as discussed with contractor at time of inspection. 2 , complete all insulation and vapor barrier at walls and ceiling . 3 ; provide gas pipe test approval prior to ceiling grid inspection. 4 ; provide fire cover approval of ceiling grid prior to next inspection. 5 ; remove abandoned mechanical equipment and plumbing vents above ceiling as discussed with contractor. 6 ; provide 1'' clearance to combustibles at b-vent of hot water heater. 7 ; provide min. 3 turns on tie wires of lights. not ready

Plumbing Rough In Inspection Partial Pass 11/8/2024 11/8/2024 11/08/2024
Shannon King ((253) 840-6684)
Other/Miscellaneous
Resolved
11/08/2024
1 ; test failed on gas pipe test. ( fix leak and retest system)

Firewall/Firestop Inspection Partial Pass 11/13/2024 11/13/2024 11/13/2024
Shannon King ((253) 840-6684)
Ceiling Grid/T-Bar Inspection Partial Pass 11/13/2024 11/13/2024 11/13/2024
Shannon King ((253) 840-6684)
Other/Miscellaneous
Resolved
11/13/2024
1 ; complete all ceiling grid requirements as discussed with contractor at time of inspection. 2 , complete all insulation and vapor barrier at walls and ceiling . 3 ; provide gas pipe test approval prior to ceiling grid inspection. 4 ; provide fire cover approval of ceiling grid prior to next inspection. 5 ; remove abandoned mechanical equipment and plumbing vents above ceiling as discussed with contractor. 6 ; provide 1'' clearance to combustibles at b-vent of hot water heater. 7 ; provide min. 3 turns on tie wires of lights. not ready

Other/Miscellaneous
Carried Forward
11/13/2024
1 ; complete install of speaker with min. 1 support wire as discussed with contractor. 2 ; complete ceiling grid in riser room. 3 ; complete grease line in kitchen.

Plumbing Final Inspection Not Ready 11/20/2024 11/20/2024 11/20/2024
Shannon King ((253) 840-6684)
Other/Miscellaneous
Carried Forward
11/20/2024
1 ; complete install of all equipment as discussed with contractor. 2 ; provide hammer arrestors at ice machine and dishwasher supply lines. 3 ; provide 1'' clearance at b-vent of hot water heater. 4 ; provide health dept. pre-walk inspection prior to plumbing final inspection. 5 ; provide 17'' max. to Urinal rim above finish floor as per city approved plans. 6 ; provide back flow cert. at time of plumbing final. 7 ; provide manual for ice maker to check air gap of water supply. 8 ; not ready (complete all items as discussed with contractor)

Ceiling Grid/T-Bar Inspection Failed 12/2/2024 12/2/2024 12/02/2024
Shannon King ((253) 840-6684)
Other/Miscellaneous
Resolved
12/02/2024

Other/Miscellaneous
Carried Forward
12/02/2024
1 ; complete tie wires at light in riser room. 2 ; provide fire cover approval at riser room.

Plumbing Final Inspection Not Ready 12/2/2024 12/2/2024 12/02/2024
Shannon King ((253) 840-6684)
Other/Miscellaneous
Carried Forward
12/02/2024
1 ; complete install of all equipment as discussed with contractor. 2 ; provide hammer arrestors at ice machine and dishwasher supply lines. 3 ; provide 1'' clearance at b-vent of hot water heater. 4 ; provide health dept. pre-walk inspection prior to plumbing final inspection. 5 ; provide 17'' max. to Urinal rim above finish floor as per city approved plans. 6 ; provide back flow cert. at time of plumbing final. 7 ; provide manual for ice maker to check air gap of water supply. 8 ; not ready (complete all items as discussed with contractor)

Engineering Final Inspection Failed 12/4/2024 12/3/2024 12/03/2024
Jason Little ((253) 244-0387)
Fire Or Smoke Damper Inspection VOID 12/04/2024
David Drake ((253) 864-4171)
Hydrostatic Test 200Lbs 2Hrs VOID 12/04/2024
David Drake ((253) 864-4171)
Emergency Radio Test Review Inspection VOID 12/04/2024
David Drake ((253) 864-4171)
Fire Final Inspection Partial Pass 12/4/2024 12/4/2024 12/04/2024
David Drake ((253) 864-4171)
Other/Miscellaneous
Carried Forward
12/04/2024
1. Cut concrete out around both fire sprinkler risers. 2" minimum clearance. 2. Install lock on PIV and provide key for KNOX Box. 3. Install KNOX Box. 4. Install pipe bollard in front of PIV for vehicle impact protection. 5. TCO approved for Fire, Building approval required prior to opening for public and employees.

Mechanical Final Inspection Failed 12/4/2024 12/4/2024 12/04/2024
Shannon King ((253) 840-6684)
Other/Miscellaneous
Carried Forward
12/04/2024
1 ; provide positive attachment of mechanical equipment to roof. 2 ; seal roof jacks of refrigerant line sets on roof.

Building Final Inspection Partial Pass 12/5/2024 12/5/2024 12/05/2024
Shannon King ((253) 840-6684)
Other/Miscellaneous
Carried Forward
12/05/2024
1 ; T.C.O. approved for 30 days from 12/5/2024. 2 ; provide all City Dept. final sign-off approval prior to Building final. 3 ; complete mechanical final corrections prior to building final inspection approval.

Conditions

Condition Status Department Category Expiration Date Due Date
Building Permit Standard Conditions Open Building Division Standard Conditions
: * Final approval by the Building Official is required prior to use or occupancy.* Work shall not proceed until the inspector has approved the stages of construction.* Surface storm water shall be diverted from the building site and shall not drain onto adjacent properties.* I hereby acknowledge that I have read this Permit/Application, that the information given is correct; that I am the owner or the duly authorized agent of the owner; that plans submitted herewith are in compliance with all applicable city, county and state laws and that all construction will proceed in accordance with said laws. This permit shall expire if work is not commenced with 180 days or if the work is suspended for a period of 180 days. Permits expire two years from issuance. * By leaving the contractor information section blank, I hereby certify further that contractors (general or subcontractors) will not be hired to perform any work in association with this permit. I also certify that if I do choose to hire a contractor (general or subcontractor) I will only hire those contractors that are licensed by the State of Washington. If you are a property owner, contractor or permittee and you are paying for someone to perform the work, they must have a valid contractor registration and the person(s) installing plumbing inside a structure must meet the plumbing certification requirements. If you have any questions regarding these regulations, you may contact the Washington State Department of Labor and Industries or you can find more information on-line at: http://www.lni.wa.gov/TradesLicensing/Contractors/HireCon/default.asp
Fire Review Conditions Open Standard Conditions
: 1. INSTALL ADDRESS NUMBERS PER THE FOLLOWING DISTANCES:0-50FOOT SETBACK FROM STREET NUMBERS SHALL BE 6 INCHES IN HEIGHT; 51-100 FEET 12 INCHES IN HEIGHT. ALL NUMBERS SHALL CONTRAST WITH THEIR BACKGROUND. ADDITIONAL NUMBERS MAY BE NEEDED AT DRIVEWAY ENTRANCE IF BUILDING NUMBERS ARE NOT VISIBLE FROM THE STREET. REAR DOORS OF SUITES OR UNITS SHALL ALSO BE LABELED WITH MINIMUM 4 INCH NUMBERS. 2. FIRE HYDRANTS REQUIRED FOR CONSTRUCTION AND FIRE DEPARTMENT ACCESS SHALL BE INSTALLED AND APPROVED BY THE FIRE CODE OFFICIAL PRIOR TO THE STORAGE OR INSTALLATION OF ANY COMBUSTIBLE FRAMING MATERIAL. ACCESS ROADWAY SURFACES SHALL BE DESIGNED TO CITY STANDARDS AND BE DESIGNED TO MAINTAIN THE IMPOSED LOADS OF A 80,000 POUND FIRE APPARATUS. ASPHALT TREATED BASE, ASPHALT OR CONCRETE PAVEMENT CAN BE USED TO PROVIDE THE REQUIRED ALL-WEATHER DRIVING SURFACE. 3. ANY REQUIRED FIRE LANE MARKINGS SHALL BE INSTALLED PRIOR TO FINAL INSPECTION AND PER CITY ORDINANCE. 4. KNOX BOXES, WHEN REQUIRED, SHALL BE INSTALLED USUALLY TO THE RIGHT OF THE MAIN FRONT DOOR AND NO HIGHER THAN 6 FEET OFF OF THE GROUND. ONLY HINGED KNOX BOXES SHALL BE USED. KNOX BOXES AND KEY SWITCHES CAN BE ORDERED ONLINE AT THE "KNOX COMPANY" 5. FIRE EXTINGUISHERS WILL BE REQUIRED PER CHAPTER 9 OF THE INTERNATIONAL FIRE CODE. GENERALLY, 1 FIRE EXTINGUISHER WITH A MINIMUM RATING OF 2A 10BC SHALL BE INSTALLED PER EVERY 3,000 SQUARE FEET OF FLOOR AREA. THE LOCATION OF THE FIRE EXTINGUISHERS SHALL BE NEAR THE EXIT DOORS AND TRAVEL DISTANCE TO AN EXTINGUISHER SHALL NOT EXCEED 75 FEET. ADDITIONAL SIGNAGE MAY BE NECESSARY TO INDICATE THE FIRE EXTINGUISHER LOCATION.
Engineering Commercial Standard Conditions Open Engineering Division Standard Conditions
: Development Engineering standard commercial conditions: ** All new kitchen plumbing must be directed to the existing grease interceptor. See the Puyallup McDonald's Utility Plan Drawing C1.1 Sheet: 2 of 4 ** ** Civil Sheets C-1 through C-5 have not been reviewed or approved under building permit PRCTI20231634. Please submit all civil plans for review via a Civil Construction permit application ** - Prior to starting site work request an inspection for erosion and sediment. - Occupancy will not be granted until all civil work associated with prccpxxxx has been completed and approval has been provided. - Sediment control and erosion procedures shall be practice to eliminate and prevent off site damage. Stormwater runoff originating upgrade of exposed areas shall be controlled to reduce erosion and sediment loss during the period of exposure. Attached to the site plan is the city of puyallup’s stormwater fact sheet. or See approved civil plan PRCCPXXX for approved method of control. - Stormwater control of roof downspouts required. Attached to the site plan is a typical infiltration system you may choose to follow. - All commercial development, multi-family, mixed use facility,or irrigation systems water service connections must have installed an approved backflow prevention assembly installed as directed by the Puyallup Municipal Code 14.02.220(3) and conforming to city standard section 03.04 - backflow installation. A double detector check valve assembly (DDCVA) is required or A reduced pressure backflow assembly (RPBA) is required as directed by the City of Puyallup, Fruitland Mutual Water Company, Tacoma City Water or Valley Water District. - Due to the proximity of this property to a secondary water source (i.e. clarks creek, meeker ditch, etc.) the applicant shall install a reduced pressure backflow assembly per city standards. - A commercial development must have installed a side sewer sampling tee installed in conformance to city standard section 04.03 – side sewer. - The applicant is responsible to schedule all utility inspections prior to backfilling - Curb, gutter, sidewalk and approach must be poured per city standards. - Driveway approach must be a minimum of 30' wide. - The builder/owner shall be responsible for keeping the existing right-of-way free of debris and dirt. Any violation of PMC chapter 21.14 pertaining to clearing, filling and grading, erosion and sediment control, and storm water discharges shall be prosecuted to the fullest extent of the law.- Any addition/expansion to the footprint of the building including decks and porches not originally shown on the approved set of plans must obtain proper permits prior to construction. - The applicant is responsible to call the utility notification center at 1-800-424-5555 before beginning any excavation. Call before you dig, it's the law. - No work shall be done in or on the public right of way without a licensed and bonded contractor first obtaining a right of way permit. - A separate right of way permit must be obtained is required by a licensed and bonded contractor to make the sanitary sewer main tap and or a water service connection. - Water meter box grade may have to be adjusted, at owners expense, due to the grade of the proposed driveway. - Any code requirement that may have been overlooked in this plan review does not imply that the requirements have been waived. - This property lies within a regulated flood zone. both residential and non-residential must meet the following requirements in accordance with PMC 21.07: (For AE Zone): New construction and substantial improvement of any structure will require that the lowest floor, including the basement, shall be elevated to a minimum of one foot or more above the base flood elevation. Please note additional freeboard increases safety and can reduce insurance premiums. (For AO Zone): New construction and substantial improvement of any structure will require that the lowest floor, including the basement, shall be elevated 1-foot or more above the depth number on the firm (minimum of 2-feet above the highest natural grade). - Crawlspace openings are required to allow the entry and exit of floodwaters. A minimum of two openings having a total net area of net less than 1 square inch for every square foot of enclosed area subject to flooding shall be provided. the bottom of openings shall be no higher than 1 foot above grade (PMC 21.07.060(2)). - If fill is proposed on the lot, the applicant shall provide compensatory storage in accordance with the requirements of PMC 21.07.060(1)f. If less than 1:1 compensatory storage is proposed, the applicant will be required to provide a hydrologic and hydraulic analysis to determine any effects on floodplain storage capacity, increased flood heights, or increased velocities. - No fill shall be placed unless specifically shown on the approved site plan. after site plan approval, any additional fill shall be submitted on a revised site plan to the city and shall propose mitigation in accordance with PMC 21.07.060(1)(f). - Steps shall be taken to prevent drainage onto adjacent lots. - No occupancy permit shall be issued until such time as a federal emergency management agency flood elevation certificate is completed based on "finished construction" and reviewed and accepted by the City of Puyallup.

Related Permit & Planning Applications

Reference Number Status Type
PRSG20240635 Closed Sign/Awning
PRHM20240695 Closed Hydraulic Modeling
PRCCP20240864 Permit(s) Issued Civil Construction Permit
PRFS20241391 Closed Fire Sprinklers
PRFA20241433 Closed Fire Alarms
PRFS20241670 Closed Fire Sprinklers

Documents & Images

Date Uploaded File Type Name
05/02/2024 Receipt Receipt for transaction:2024-000900
05/20/2024 Plans CONSTRUCTION PLANS - RESUB (Stamped)
05/20/2024 Form PLUMBING FIXTURE WORKSHEET (Stamped)
05/20/2024 Plans STORMWATER FACT SHEET AND SEDIMENT & EROSION DETAIL (Stamped)
05/20/2024 Report STRUCTURAL CALCS - (Stamped)
08/06/2024 Letter Permit - Detailed
08/06/2024 Receipt Receipt for transaction:2024-001623
09/06/2024 Report Inspection Report (Footing/Setback Inspection)
09/09/2024 Report Inspection Report (Comment Building Div Inspection)
09/09/2024 Report Inspection Report (Slab/Insulation Inspection)
09/16/2024 Report Inspection Report (Footing/Setback Inspection)
09/16/2024 Report Inspection Report (Foundation/Rebar Inspection)
09/16/2024 Report Inspection Report (Slab/Insulation Inspection)
09/23/2024 Report Inspection Report (Frame Inspection)
09/23/2024 Report Inspection Report (Plumbing Rough In Inspection)
09/24/2024 Report Inspection Report (Plumbing Rough In Inspection)
09/26/2024 Report Inspection Report (Combination Frame And Rough In Inspection)
09/26/2024 Report Inspection Report (Footing/Setback Inspection)
09/26/2024 Report Inspection Report (Frame Inspection)
09/26/2024 Report Inspection Report (Wallboard / Drywall Inspection)
09/27/2024 Report Inspection Report (Frame Inspection)
10/05/2024 Report Inspection Report (Wallboard / Drywall Inspection)
10/09/2024 Report Inspection Report (Combination Frame And Rough In Inspection)
10/10/2024 Report Inspection Report (Frame Inspection)
10/15/2024 Report Inspection Report (Energy (Insulation) Inspection)
10/15/2024 Report Inspection Report (Light Test For Grease Duct Inspection)
10/16/2024 Report Inspection Report (Wallboard / Drywall Inspection)
10/16/2024 Plans MCD Puyallup - TCP
10/22/2024 Report Inspection Report (Exhaust Hood Inspection)
10/24/2024 Report Inspection Report (Exhaust Hood Inspection)
11/07/2024 Report Inspection Report (Ceiling Grid/T-Bar Inspection)
11/07/2024 Report Inspection Report (Exhaust/Vent Fans Inspection)
11/07/2024 Report Inspection Report (Plumbing Rough In Inspection)
11/13/2024 Report Inspection Report (Ceiling Grid/T-Bar Inspection)
11/13/2024 Report Inspection Report (Firewall/Firestop Inspection)
11/20/2024 Report Inspection Report (Plumbing Final Inspection)
11/22/2023 Receipt Receipt for transaction:2023-002225
12/02/2024 Report Inspection Report (Ceiling Grid/T-Bar Inspection)
12/02/2024 Report Inspection Report (Plumbing Rough In Inspection)
12/03/2024 Report Inspection Report (Engineering Final Inspection)
12/04/2024 Report Inspection Report (Ceiling Grid/T-Bar Inspection)
12/04/2024 Report Inspection Report (Mechanical Final Inspection)
12/04/2024 Report Inspection Report (Plumbing Final Inspection)
12/05/2024 Report Inspection Report (Building Final Inspection)
12/05/2024 Report Inspection Report (Engineering Final Inspection)
12/06/2024 Report Inspection Report (Plumbing Final Inspection)


Should you need assistance, please contact the Permit Center at (253) 864-4165 option 1.