Permit Application Status
PRCTI20221460
Paid Fees | Amount | Paid | Owing | Date Paid |
---|---|---|---|---|
Fire Review Fee (Commercial Building) | $265.00 | $265.00 | Paid | 01/23/2023 |
Building Permit Fee | $1,553.75 | $1,553.75 | Paid | 01/23/2023 |
Building Plan Review Fee | $1,009.94 | $1,009.94 | Paid | 10/03/2022 |
WA State Building Code Council Fee (Commercial) | $25.00 | $25.00 | Paid | 01/23/2023 |
Exhaust Vent Fan (Bath) Fee | $14.10 | $14.10 | Paid | 01/23/2023 |
Drinking Fountain, Water Cooler, Ice Machine Fee | $40.25 | $40.25 | Paid | 01/23/2023 |
Plumbing Permit Fee | $40.00 | $40.00 | Paid | 01/23/2023 |
Mechanical Permit Fee | $40.00 | $40.00 | Paid | 01/23/2023 |
Plumbing Plan Review Fee | $52.16 | $52.16 | Paid | 10/03/2022 |
Mechanical Plan Review Fee | $35.17 | $35.17 | Paid | 10/03/2022 |
Sewer System Development ChargeFee - Tenant Improvment/Addition | $4,340.93 | $4,340.93 | Paid | 01/23/2023 |
Resubmittal Fee | $130.00 | $130.00 | Paid | 12/08/2022 |
Resubmittal Fee | $130.00 | $130.00 | Paid | 01/10/2023 |
Building Re-Inspection Fee | $180.00 | $180.00 | Paid | 04/06/2023 |
Resubmittal Fee | $180.00 | $180.00 | Paid | 04/17/2023 |
Resubmittal Fee | $180.00 | $180.00 | Paid | 05/24/2023 |
Resubmittal Fee | $180.00 | $180.00 | Paid | 07/25/2023 |
Resubmittal Fee | $180.00 | $180.00 | Paid | 08/02/2023 |
Resubmittal Fee | $180.00 | $180.00 | Paid | 08/15/2023 |
Outstanding Fees | Amount | Paid | Owing | Date Paid |
No outstanding fees. | ||||
Totals: | $8,756.30 | $8,756.30 | $0.00 |
Permit(s) will not be issued until outstanding fees have been paid in full. Fee details shown above only include currently payable fees, there might be addtional fees to be paid before issuance.
$0.00
Inspection | Outcome | Requested | Scheduled | Date Inspected |
---|---|---|---|---|
Plumbing Rough In Inspection | Failed with Fee | 4/4/2023 | 4/4/2023 | 04/04/2023 |
Monty Johnson ((253) 770-3326) | ||||
Corrections:
Other/Miscellaneous
Carried Forward
04/04/2023
no test on plumbing , did not open plans
|
||||
Plumbing Rough In Inspection | Failed | 4/10/2023 | 4/10/2023 | 04/10/2023 |
Shannon King ((253) 840-6684) | ||||
Corrections:
Other/Miscellaneous
Carried Forward
04/10/2023
1 ; provide complete set of City approved plans on-site at time of inspection.
2 ; test failed on plumbing rough-in test of d.w.v. and supply.( not on test at time of inspection.)
|
||||
Frame Inspection | Not Ready | 4/27/2023 | 4/27/2023 | 04/27/2023 |
Shannon King ((253) 840-6684) | ||||
Corrections:
Other/Miscellaneous
Carried Forward
04/27/2023
1 ; provide plan revision for all plumbing, framing ,and mechanical changes as discussed with contractor.
not ready
|
||||
Plumbing Rough In Inspection | Partial Pass | 4/27/2023 | 4/27/2023 | 04/27/2023 |
Shannon King ((253) 840-6684) | ||||
Corrections:
Other/Miscellaneous
Carried Forward
04/27/2023
1 ; provide complete set of City approved plans on-site at time of inspection.
2 ; test failed on plumbing rough-in test of d.w.v. and supply.( not on test at time of inspection.)
|
||||
Other/Miscellaneous
Carried Forward
04/27/2023
1 ; provide plan revision for all plumbing, framing ,and mechanical changes as discussed with contractor.
2 ; approved test on supply and d.w.v. pending approval of plans revision of plumbing as-built and added plumbing fixtures.
not ready
|
||||
Plumbing Rough In Inspection | Partial Pass | 6/26/2023 | 6/26/2023 | 06/26/2023 |
Kevin Spruell ((253) 841-5590) | ||||
Corrections:
Other/Miscellaneous
Resolved
06/26/2023
1 ; provide complete set of City approved plans on-site at time of inspection.
2 ; test failed on plumbing rough-in test of d.w.v. and supply.( not on test at time of inspection.)
|
||||
Other/Miscellaneous
Resolved
06/26/2023
1 ; provide plan revision for all plumbing, framing ,and mechanical changes as discussed with contractor.
2 ; approved test on supply and d.w.v. pending approval of plans revision of plumbing as-built and added plumbing fixtures.
not ready
|
||||
Grease Interceptor Inspection | Not Ready | 6/27/2023 | 6/27/2023 | 06/27/2023 |
Michael Rosenau ((253) 344-6753) | ||||
Frame Inspection | Partial Pass | 6/29/2023 | 6/29/2023 | 06/29/2023 |
Shannon King ((253) 840-6684) | ||||
Corrections:
Other/Miscellaneous
Resolved
06/29/2023
1 ; provide plan revision for all plumbing, framing ,and mechanical changes as discussed with contractor.
not ready
|
||||
Other/Miscellaneous
Carried Forward
06/29/2023
1 ; approved wall framing only in room 105 family dining.
2 ; complete all other framing, plumbing ,mechanical as per city approved field revision resub plans as discussed with contractor.
|
||||
Energy (Insulation) Inspection | Partial Pass | 6/30/2023 | 6/30/2023 | 06/30/2023 |
Monty Johnson ((253) 770-3326) | ||||
Corrections:
Other/Miscellaneous
Carried Forward
06/30/2023
1: insulation in walls family dining ok
|
||||
Wallboard / Drywall Inspection | Partial Pass | 7/5/2023 | 7/5/2023 | 07/05/2023 |
Kevin Spruell ((253) 841-5590) | ||||
Shear Wall Inspection | Not Ready | 7/5/2023 | 7/5/2023 | 07/05/2023 |
Kevin Spruell ((253) 841-5590) | ||||
Corrections:
Other/Miscellaneous
Carried Forward
07/05/2023
1. provide clarification from engineer on edge nailing detail at wall above north entrance
|
||||
Frame Inspection | Partial Pass | 7/6/2023 | 7/6/2023 | 07/06/2023 |
Kevin Spruell ((253) 841-5590) | ||||
Corrections:
Other/Miscellaneous
Carried Forward
07/06/2023
1 ; approved wall framing only in room 105 family dining.
2 ; complete all other framing, plumbing ,mechanical as per city approved field revision resub plans as discussed with contractor.
|
||||
Other/Miscellaneous
Carried Forward
07/06/2023
1. wall behind bar that separates bar from kitchen both sides, hall way to restrooms and wall at old main entrance (north) to single exit door (west) ok to cover
|
||||
Wallboard / Drywall Inspection | Partial Pass | 7/11/2023 | 7/11/2023 | 07/11/2023 |
Kevin Spruell ((253) 841-5590) | ||||
Shear Wall Inspection | Passed | 7/12/2023 | 7/12/2023 | 07/12/2023 |
Kevin Spruell ((253) 841-5590) | ||||
Corrections:
Other/Miscellaneous
Resolved
07/12/2023
1. provide clarification from engineer on edge nailing detail at wall above north entrance
|
||||
Foundation/Rebar Inspection | Not Ready | 7/18/2023 | 7/18/2023 | 07/18/2023 |
Shannon King ((253) 840-6684) | ||||
Corrections:
Other/Miscellaneous
Carried Forward
07/18/2023
1 ; provide complete set of full sized City approved plans on-site at time of inspection.
2 ; complete all footing as per plans prior to footing inspection as discussed with contractor.
not ready
|
||||
Frame Inspection | Partial Pass | 7/21/2023 | 7/21/2023 | 07/21/2023 |
Shannon King ((253) 840-6684) | ||||
Corrections:
Other/Miscellaneous
Carried Forward
07/21/2023
1 ; approved wall framing only in room 105 family dining.
2 ; complete all other framing, plumbing ,mechanical as per city approved field revision resub plans as discussed with contractor.
|
||||
Other/Miscellaneous
Carried Forward
07/21/2023
1. wall behind bar that separates bar from kitchen both sides, hall way to restrooms and wall at old main entrance (north) to single exit door (west) ok to cover
|
||||
Ceiling Grid/T-Bar Inspection | Failed | 8/16/2023 | 8/16/2023 | 08/16/2023 |
Shannon King ((253) 840-6684) | ||||
Corrections:
Other/Miscellaneous
Carried Forward
08/16/2023
1 ; complete all ceiling grid requirements as discussed with contractor.
2 ; provide L&I electrical cover approval.
3 ; provide fire cover approval prior to ceiling grid inspection.
not ready
|
||||
Planning Final Inspection | VOID | 8/21/2023 | 08/21/2023 | |
Chris Beale ((253) 841-5418) | ||||
Ceiling Grid/T-Bar Inspection | Not Ready | 8/22/2023 | 8/22/2023 | 08/22/2023 |
Shannon King ((253) 840-6684) | ||||
Corrections:
Other/Miscellaneous
Carried Forward
08/22/2023
1 ; complete all ceiling grid requirements as discussed with contractor.
2 ; provide L&I electrical cover approval.
3 ; provide fire cover approval prior to ceiling grid inspection.
not ready
|
||||
Other/Miscellaneous
Carried Forward
08/22/2023
1 ; complete all ceiling grid requirements as discussed with contractor.
2 ; provide L&I electrical cover approval.
|
||||
Ceiling Grid/T-Bar Inspection | Passed | 8/23/2023 | 8/23/2023 | 08/23/2023 |
Shannon King ((253) 840-6684) | ||||
Corrections:
Other/Miscellaneous
Resolved
08/23/2023
1 ; complete all ceiling grid requirements as discussed with contractor.
2 ; provide L&I electrical cover approval.
3 ; provide fire cover approval prior to ceiling grid inspection.
not ready
|
||||
Other/Miscellaneous
Resolved
08/23/2023
1 ; complete all ceiling grid requirements as discussed with contractor.
2 ; provide L&I electrical cover approval.
|
||||
Frame Inspection | Passed | 8/24/2023 | 8/24/2023 | 08/24/2023 |
Shannon King ((253) 840-6684) | ||||
Corrections:
Other/Miscellaneous
Resolved
08/24/2023
1 ; approved wall framing only in room 105 family dining.
2 ; complete all other framing, plumbing ,mechanical as per city approved field revision resub plans as discussed with contractor.
|
||||
Other/Miscellaneous
Resolved
08/24/2023
1. wall behind bar that separates bar from kitchen both sides, hall way to restrooms and wall at old main entrance (north) to single exit door (west) ok to cover
|
||||
Refrigeration Line Test Inspection | Passed | 8/25/2023 | 8/25/2023 | 08/25/2023 |
Kevin Spruell ((253) 841-5590) | ||||
Wallboard / Drywall Inspection | Passed | 8/25/2023 | 8/25/2023 | 08/25/2023 |
Kevin Spruell ((253) 841-5590) | ||||
Erosion And Sediment Inspection | VOID | 09/08/2023 | ||
Michael Rosenau ((253) 344-6753) | ||||
Comment Engineering Div Inspection | Passed | 09/08/2023 | ||
Michael Rosenau ((253) 344-6753) | ||||
Cover Inspection/Thrust Blocks Inspection | VOID | 09/08/2023 | ||
Michael Rosenau ((253) 344-6753) | ||||
Grease Interceptor Inspection | Passed | 9/8/2023 | 9/8/2023 | 09/08/2023 |
Michael Rosenau ((253) 344-6753) | ||||
Engineering Final Inspection | Passed | 09/08/2023 | ||
Michael Rosenau ((253) 344-6753) | ||||
Emergency Radio Test Review Inspection | VOID | 09/11/2023 | ||
David Drake ((253) 864-4171) | ||||
Hydrostatic Test 200Lbs 2Hrs | VOID | 09/11/2023 | ||
David Drake ((253) 864-4171) | ||||
Fire Or Smoke Damper Inspection | VOID | 09/11/2023 | ||
David Drake ((253) 864-4171) | ||||
Fire Final Inspection | Not Ready | 9/11/2023 | 9/13/2023 | 09/13/2023 |
David Drake ((253) 864-4171) | ||||
Corrections:
Fire Sprinkler
Carried Forward
09/13/2023
See fire sprinkler corrections.
|
||||
Exit Lighting Test Inspection | Passed | 9/13/2023 | 09/13/2023 | |
David Drake ((253) 864-4171) | ||||
Fire Final Inspection | Passed | 9/19/2023 | 09/19/2023 | |
David Drake ((253) 864-4171) | ||||
Corrections:
Fire Sprinkler
Outstanding
09/13/2023
See fire sprinkler corrections.
|
||||
Building Final Inspection | Failed | 9/19/2023 | 9/19/2023 | 09/19/2023 |
Shannon King ((253) 840-6684) | ||||
Corrections:
Other/Miscellaneous
Carried Forward
09/19/2023
1 ; complete all exterior caulking as discussed with Brian.
2 ; complete all door sweeps at exterior doors.
3 ; complete accessible signage as both restrooms .
4 ; fix plumbing leak at hammer arrestors at dishwasher and icemaker.
5 ; provide 1'' airgap at floor sink next to icemaker.
6 ; complete all sink drains as per code as discussed with Brian.
7 ; complete exit door at exterior storage area.
8 ; paint gas pipe on roof.
9 ; seal doghouse penetration at mechanical on roof.
10 ; remove abandoned gas pipe on roof.
11 ; complete accessible table at outdoor patio area.
12 ; complete ceiling tile at mechanical room.
13 ; complete mechanical above kitchen ceiling.
14 ; remove debris from roof prior to final.
15 ; complete panic hardware at exit doors as per code.
|
||||
Mechanical Final Inspection | Failed | 9/19/2023 | 9/19/2023 | 09/19/2023 |
Shannon King ((253) 840-6684) | ||||
Corrections:
Other/Miscellaneous
Carried Forward
09/19/2023
1 ; complete all exterior caulking as discussed with Brian.
2 ; complete all door sweeps at exterior doors.
3 ; complete accessible signage as both restrooms .
4 ; fix plumbing leak at hammer arrestors at dishwasher and icemaker.
5 ; provide 1'' airgap at floor sink next to icemaker.
6 ; complete all sink drains as per code as discussed with Brian.
7 ; complete exit door at exterior storage area.
8 ; paint gas pipe on roof.
9 ; seal doghouse penetration at mechanical on roof.
10 ; remove abandoned gas pipe on roof.
11 ; complete accessible table at outdoor patio area.
12 ; complete ceiling tile at mechanical room.
13 ; complete mechanical above kitchen ceiling.
14 ; remove debris from roof prior to final.
15 ; complete panic hardware at exit doors as per code
|
||||
Plumbing Final Inspection | Failed | 9/19/2023 | 9/19/2023 | 09/19/2023 |
Shannon King ((253) 840-6684) | ||||
Corrections:
Other/Miscellaneous
Carried Forward
09/19/2023
1 ; complete all exterior caulking as discussed with Brian.
2 ; complete all door sweeps at exterior doors.
3 ; complete accessible signage as both restrooms .
4 ; fix plumbing leak at hammer arrestors at dishwasher and icemaker.
5 ; provide 1'' airgap at floor sink next to icemaker.
6 ; complete all sink drains as per code as discussed with Brian.
7 ; complete exit door at exterior storage area.
8 ; paint gas pipe on roof.
9 ; seal doghouse penetration at mechanical on roof.
10 ; remove abandoned gas pipe on roof.
11 ; complete accessible table at outdoor patio area.
12 ; complete ceiling tile at mechanical room.
13 ; complete mechanical above kitchen ceiling.
14 ; remove debris from roof prior to final.
15 ; complete panic hardware at exit doors as per code
|
||||
Building Final Inspection | Partial Pass | 9/21/2023 | 9/21/2023 | 09/21/2023 |
Shannon King ((253) 840-6684) | ||||
Corrections:
Other/Miscellaneous
Resolved
09/21/2023
1 ; complete all exterior caulking as discussed with Brian.
2 ; complete all door sweeps at exterior doors.
3 ; complete accessible signage as both restrooms .
4 ; fix plumbing leak at hammer arrestors at dishwasher and icemaker.
5 ; provide 1'' airgap at floor sink next to icemaker.
6 ; complete all sink drains as per code as discussed with Brian.
7 ; complete exit door at exterior storage area.
8 ; paint gas pipe on roof.
9 ; seal doghouse penetration at mechanical on roof.
10 ; remove abandoned gas pipe on roof.
11 ; complete accessible table at outdoor patio area.
12 ; complete ceiling tile at mechanical room.
13 ; complete mechanical above kitchen ceiling.
14 ; remove debris from roof prior to final.
15 ; complete panic hardware on exit doors as per code.
|
||||
Other/Miscellaneous
Carried Forward
09/21/2023
1; complete exit door at exterior storage area.
2 ; paint gas pipe on roof.
3 ; seal doghouse penetration at mechanical on roof.
4 ; remove abandoned gas pipe on roof.
5 ; remove debris from roof prior to final.
|
||||
Mechanical Final Inspection | Passed | 9/21/2023 | 9/21/2023 | 09/21/2023 |
Shannon King ((253) 840-6684) | ||||
Corrections:
Other/Miscellaneous
Resolved
09/21/2023
1 ; complete all exterior caulking as discussed with Brian.
2 ; complete all door sweeps at exterior doors.
3 ; complete accessible signage as both restrooms .
4 ; fix plumbing leak at hammer arrestors at dishwasher and icemaker.
5 ; provide 1'' airgap at floor sink next to icemaker.
6 ; complete all sink drains as per code as discussed with Brian.
7 ; complete exit door at exterior storage area.
8 ; paint gas pipe on roof.
9 ; seal doghouse penetration at mechanical on roof.
10 ; remove abandoned gas pipe on roof.
11 ; complete accessible table at outdoor patio area.
12 ; complete ceiling tile at mechanical room.
13 ; complete mechanical above kitchen ceiling.
14 ; remove debris from roof prior to final.
15 ; complete panic hardware at exit doors as per code
|
||||
Plumbing Final Inspection | Passed | 9/21/2023 | 9/21/2023 | 09/21/2023 |
Shannon King ((253) 840-6684) | ||||
Building Final Inspection | Failed | 10/12/2023 | 10/12/2023 | 10/12/2023 |
Shannon King ((253) 840-6684) | ||||
Corrections:
Other/Miscellaneous
Resolved
10/12/2023
1 ; complete all exterior caulking as discussed with Brian.
2 ; complete all door sweeps at exterior doors.
3 ; complete accessible signage as both restrooms .
4 ; fix plumbing leak at hammer arrestors at dishwasher and icemaker.
5 ; provide 1'' airgap at floor sink next to icemaker.
6 ; complete all sink drains as per code as discussed with Brian.
7 ; complete exit door at exterior storage area.
8 ; paint gas pipe on roof.
9 ; seal doghouse penetration at mechanical on roof.
10 ; remove abandoned gas pipe on roof.
11 ; complete accessible table at outdoor patio area.
12 ; complete ceiling tile at mechanical room.
13 ; complete mechanical above kitchen ceiling.
14 ; remove debris from roof prior to final.
15 ; complete panic hardware on exit doors as per code.
|
||||
Other/Miscellaneous
Resolved
10/12/2023
1; complete exit door at exterior storage area.
2 ; paint gas pipe on roof.
3 ; seal doghouse penetration at mechanical on roof.
4 ; remove abandoned gas pipe on roof.
5 ; remove debris from roof prior to final.
|
||||
Other/Miscellaneous
Carried Forward
10/12/2023
1; complete exit door at exterior storage area as discussed with contractor.
|
||||
Comment Building Div Inspection | VOID | 11/17/2023 | ||
Joyce Kennedy ((253) 841-5405) | ||||
Footing/Setback Inspection | VOID | 11/17/2023 | ||
Joyce Kennedy ((253) 841-5405) | ||||
Underfloor Inspection | VOID | 11/17/2023 | ||
Joyce Kennedy ((253) 841-5405) | ||||
Slab/Insulation Inspection | VOID | 11/17/2023 | ||
Joyce Kennedy ((253) 841-5405) | ||||
Block Wall Rebar Inspection | VOID | 11/17/2023 | ||
Joyce Kennedy ((253) 841-5405) | ||||
Firewall/Firestop Inspection | VOID | 11/17/2023 | ||
Joyce Kennedy ((253) 841-5405) | ||||
Re-Roof Inspection | VOID | 11/17/2023 | ||
Joyce Kennedy ((253) 841-5405) | ||||
Mechanical Rough In Inspection | VOID | 11/17/2023 | ||
Joyce Kennedy ((253) 841-5405) | ||||
Exhaust/Vent Fans Inspection | VOID | 11/17/2023 | ||
Joyce Kennedy ((253) 841-5405) | ||||
Plumbing Rough In Inspection | VOID | 11/17/2023 | ||
Joyce Kennedy ((253) 841-5405) | ||||
Energy (Insulation) Inspection | VOID | 11/17/2023 | ||
Joyce Kennedy ((253) 841-5405) | ||||
Foundation/Rebar Inspection | VOID | 11/17/2023 | ||
Joyce Kennedy ((253) 841-5405) | ||||
Corrections:
Other/Miscellaneous
Outstanding
07/18/2023
1 ; provide complete set of full sized City approved plans on-site at time of inspection.
2 ; complete all footing as per plans prior to footing inspection as discussed with contractor.
not ready
|
||||
Building Final Inspection | VOID | 11/17/2023 | ||
Joyce Kennedy ((253) 841-5405) | ||||
Building Final Inspection | VOID | 11/17/2023 | 11/17/2023 | 11/17/2023 |
Joyce Kennedy ((253) 841-5405) | ||||
Corrections:
Other/Miscellaneous
Outstanding
10/12/2023
1; complete exit door at exterior storage area as discussed with contractor.
|
Condition | Status | Category |
---|---|---|
Building Permit Standard Conditions | Open | Standard Conditions |
* Final approval by the Building Official is required prior to use or occupancy.* Work shall not proceed until the inspector has approved the stages of construction.* Surface storm water shall be diverted from the building site and shall not drain onto adjacent properties.* I hereby acknowledge that I have read this Permit/Application, that the information given is correct; that I am the owner or the duly authorized agent of the owner; that plans submitted herewith are in compliance with all applicable city, county and state laws and that all construction will proceed in accordance with said laws. This permit shall expire if work is not commenced with 180 days or if the work is suspended for a period of 180 days. Permits expire two years from issuance. * By leaving the contractor information section blank, I hereby certify further that contractors (general or subcontractors) will not be hired to perform any work in association with this permit. I also certify that if I do choose to hire a contractor (general or subcontractor) I will only hire those contractors that are licensed by the State of Washington. If you are a property owner, contractor or permittee and you are paying for someone to perform the work, they must have a valid contractor registration and the person(s) installing plumbing inside a structure must meet the plumbing certification requirements. If you have any questions regarding these regulations, you may contact the Washington State Department of Labor and Industries or you can find more information on-line at: http://www.lni.wa.gov/TradesLicensing/Contractors/HireCon/default.asp
|
||
Fire Review Conditions | Open | Standard Conditions |
• Comply with 2018 IFC and 2018 IBC
• L&I Final required prior to Fire Final
• Exit lighting test required, contractor to provide light meter. Exterior lighting required at all Exterior EXIT doors. Most lights have been removed.
• Fire Alarm exterior remote Annunciator needs to be removed and placed inside the vestibule. This will require a separate Fire Alarm permit.
• In existing buildings all required service and maintenance for the fire sprinkler system and fire alarm system to be updated prior to Final inspection. Documentation required.
• Fire sprinklers required to be installed under new entry addition.
• K-fire extinguishers required to be installed prior to inspection.
• Hood suppression service and maintenance required prior to Final.
• RTU’S will be required to be tested for shut down.
• Fire extinguishers required per code.
• Riser Room and FACP need to have signage posted.
• PIV must have a Knox lock or approved lock with an extra key provided in Knox box.
• Existing buildings will need to contact central pierce fire & rescue and update the key in the Knox box.
• All above items to be completed prior to fire final. Fire final required before building final.
|
||
Engineering Commercial Standard Conditions | Resolved | Standard Conditions |
Engineering Division
Development Engineering standard commercial conditions:
** Prior to occupancy the existing grease interceptor must be cleaned and inspected **
- A commercial development must have installed a side sewer sampling tee installed in conformance to city standard section 04.03 – side sewer.
- No work shall be done in or on the public right of way without a licensed and bonded contractor first obtaining a right of way permit.
- Any code requirement that may have been overlooked in this plan review does not imply that the requirements have been waived.
|
||
Miscellaneous Condition | Resolved | Prior to Occupancy |
Engineering Division
** Prior to occupancy the existing grease interceptor must be cleaned and inspected **
|
||
Building Permit Standard Conditions | Open | Prior to Occupancy |
Development & Permitting Services
Email to architect - Provided for contractor reference.
Justin,
Thank you for the advanced questions. Some of these answers will vary based on the scope, I have made some assumptions noted in the replies below, please let me know if you have any questions.
We have a restaurant TI in an existing restaurant (Famous Dave's by the South Hill Mall), and I am wondering what all would be required for submission.
Complete plans for the scope of work, assuming this will be maintain as a restaurant.
The original design had some unique floor plans and dedicated layouts when that space originally opened. Revisions to the these areas may require changes in floor elevations/transitions to work with the new layout.
We are planning on leaving the existing hood and since this is not a change of use there is no part of the scope that impacts mechanical. Would we need engineered drawings for mechanical in this case?
Generally the existing mechanical equipment may remain. The hood may or may not work depending on the equipment, size and air flow requirements. If unchanged we would need certification (by a qualified mechanical contractor) that the mechanical equipment is in working order and functions per design (this can be done during inspection, but may be helpful to your customer in advance). Due to the time out of service, at the final inspection, we would likely require a preliminary commission report to ensure outdoor ventilation rates are up to standard. Replaced equipment needs to comply with the mechanical and energy codes.
https://codes.iccsafe.org/content/WAMC2018P1/chapter-1-scope-and-administration#WAMC2018P1_Ch01_SubCh02_Sec105.5
We do intend to add some plumbing fixtures to the build, would an engineered plumbing design be required for this as well, or could we defer to the licensed plumber to submit prior to construction?
We prefer (strongly insist) a single permit package be submitted, coordinating the plumbing, mechanical, building along with the TPCHD reviews for efficiency of review and inspections. As this is a single story restaurant, a plan by a licensed and qualified plumber generally would work. Unless there is a unique design element that cannot be done prescriptively. We look for layout, pipe size, and isometric (fittings as needed) for DWV and supply. New fixtures may require addition of circulation pumps or instant-hots for energy code standards.
|
||
Miscellaneous Condition | Resolved | Prior to Issuance |
Development & Permitting Services
SENT EMAIL TO JUSTIN & CASSIE (WEDDERMANN), ND TO PROVIDE CURRENT CONTRACTOR STATE & BUSINESS LIC. PER L & I CONTRACTOR HAS NOT RENEWED SINCE 2018; $$ TO BE PAID -JF
|
Reference Number | Status | Type |
---|---|---|
PRSG20230334 | Permit(s) Issued | Sign/Awning |
PRFS20230412 | Closed | Fire Sprinklers |
PRSG20230449 | Closed | Sign/Awning |
PRFA20231086 | Closed | Fire Alarms |