Paid Fees | Amount | Paid | Owing | Date Paid |
---|---|---|---|---|
Automatic Fire Sprinkler System Alteration Fee | $230.00 | $230.00 | Paid | 04/14/2023 |
Outstanding Fees | Amount | Paid | Owing | Date Paid |
No outstanding fees. | ||||
Totals: | $230.00 | $230.00 | $0.00 |
Permit(s) will not be issued until outstanding fees have been paid in full. Fee details shown above only include currently payable fees, there might be addtional fees to be paid before issuance.
$0.00
Inspection | Outcome | Requested | Scheduled | Date Inspected |
---|---|---|---|---|
Hydrostatic Test 200Lbs 2Hrs | Failed | 8/3/2023 | 8/3/2023 | 08/03/2023 |
David Drake ((253) 864-4171) | ||||
Corrections:
Fire Sprinkler
Carried Forward
08/03/2023
1. Awning is not installed to verify clearances.
2. Out of the two sprinkler pipes, the south pipe was at an angle coming through the wall improperly installed or not attached at all.
3. No plans onsite.
4. Next available inspection is Monday.
|
||||
Hydrostatic Test 200Lbs 2Hrs | Failed | 8/7/2023 | 8/7/2023 | 08/07/2023 |
David Drake ((253) 864-4171) | ||||
Corrections:
Fire Sprinkler
Carried Forward
08/07/2023
1. Awning is not installed to verify clearances.
2. Out of the two sprinkler pipes, the south pipe was at an angle coming through the wall
improperly installed or not attached at all.
3. No plans onsite.
4. Next available inspection is Monday.
|
||||
Fire Sprinkler
Carried Forward
08/07/2023
Complete previous corrections
Hydro not on test, Fire sprinkler contractor was still filling the system at time of appointment
|
||||
Fire Sprinkler Dry System Trip Test | VOID | 08/16/2023 | ||
David Drake ((253) 864-4171) | ||||
Fire Sprinkler Cover Inspection | Passed | 8/16/2023 | 08/16/2023 | |
David Drake ((253) 864-4171) | ||||
Hydrostatic Test 200Lbs 2Hrs | Failed | 8/16/2023 | 8/16/2023 | 08/16/2023 |
David Drake ((253) 864-4171) | ||||
Corrections:
Fire Sprinkler
Carried Forward
08/17/2023
1. Awning is not installed to verify clearances.
2. Out of the two sprinkler pipes, the south pipe was at an angle coming through the wall
improperly installed or not attached at all.
3. No plans onsite.
4. Next available inspection is Monday.
|
||||
Fire Sprinkler
Carried Forward
08/17/2023
Complete previous corrections
|
||||
Comment
Carried Forward
08/17/2023
Onsite discussion with Superintendent, owner, and fire sprinkler contractor.
1. First inspection - corrections written.
2. Second inspection - corrections not complete.
3. Third inspection - corrections not complete, superintendent wanted a meeting to discuss corrections and project.
4. Awning is now installed, one sprinkler head follows the rake of the awning. The other sprinkler head is vertical and goes directly into the new awning. NFPA states the fire sprinkler head should be parallel with the rake of the roof.
5. System is not on test.
6. Provide As-built for unpermitted work of Northside ceiling.
Owner has stated corrections will be completed ASAP
|
||||
Hydrostatic Test 200Lbs 2Hrs | VOID | 09/13/2023 | ||
David Drake ((253) 864-4171) | ||||
Corrections:
Fire Sprinkler
Outstanding
08/17/2023
1. Awning is not installed to verify clearances.
2. Out of the two sprinkler pipes, the south pipe was at an angle coming through the wall
improperly installed or not attached at all.
3. No plans onsite.
4. Next available inspection is Monday.
|
||||
Fire Sprinkler
Outstanding
08/17/2023
Complete previous corrections
|
||||
Comment
Outstanding
08/17/2023
Onsite discussion with Superintendent, owner, and fire sprinkler contractor.
1. First inspection - corrections written
2. Second inspection - corrections not complete
3. Third inspection - corrections not complete, superintendent wanted a meeting to discuss corrections and project.
4. Owner has stated corrections will be completed ASAP
|
||||
Fire Sprinkler Final Inspection | Failed | 9/13/2023 | 09/13/2023 | |
David Drake ((253) 864-4171) | ||||
Corrections:
Fire Sprinkler
Carried Forward
09/13/2023
1. Complete required maintenance for fire sprinkler system.
2. Provide as-builts of extra work that was performed.
3. Move fire sprinkler head in mechanical room since new mechanical was added.
|
||||
Fire Sprinkler Final Inspection | Passed | 09/19/2023 | ||
David Drake ((253) 864-4171) | ||||
Corrections:
Fire Sprinkler
Outstanding
09/13/2023
1. Complete required maintenance for fire sprinkler system.
2. Provide as-builts of extra work that was performed.
3. Move fire sprinkler head in mechanical room since new mechanical was added.
|
Condition | Status | Category |
---|---|---|
Fire Sprinkler System (New) Conditions | Open | Standard Conditions |
• Provide plans and permit on site for inspection.
• Cover and final inspections are required.
• Fire watch is required when sprinkler system is out of service in existing buildings.
• Contractor required at all inspections.
• Hydro test will be required on all new and existing buildings. Appointment required.
• Hydro test, two inspections will be required 2hrs apart. Call to schedule times. Am/pm is not guaranteed without appointment
• Tool kit required at time of final.
• NFPA placards required
• In existing buildings all upright fire sprinklers to remain, do not remove.
• In existing buildings all required service and maintenance to be updated prior to inspection.
• Due to unforeseeable construction design, all head locations to be field verified for compliance.
Schedule your inspection online through the city of puyallup online permit system after requesting appointment from inspector. Fire Inspections are Monday – Thursday there will be no inspections on Fridays.
David Drake 253-864-4171 ddrake@puyallupwa.gov
|
Reference Number | Status | Type |
---|---|---|
PRCTI20221460 | Closed | Commercial - Tenant Improvement/Remodel |
PRSG20230334 | Permit(s) Issued | Sign/Awning |
PRSG20230449 | Closed | Sign/Awning |
PRFA20231086 | Closed | Fire Alarms |
Date Uploaded | File Type | Name |
---|---|---|
03/31/2023 | Letter | Incomplete Application Notice |
04/14/2023 | Receipt | Receipt for transaction:2023-000628 |
04/14/2023 | Letter | Incomplete Application Notice |
04/24/2023 | Letter | Incomplete Application Notice |
06/15/2023 | Form | Cheers puyallup submittal (Flattened) |
06/15/2023 | Plans | Cheers puyallup (Stamped) |
06/15/2023 | Plans | cheer puyallup horizontal (Stamped) |
06/15/2023 | Plans | Cheers puyallup (Stamped) |
06/15/2023 | Permit | Permit - Detailed |
08/07/2023 | Report | Inspection Report (Hydrostatic Test 200Lbs 2Hrs) |
08/07/2023 | Report | Inspection Report (Hydrostatic Test 200Lbs 2Hrs) |
Should you need assistance, please contact the Permit Center at (253) 864-4165 option 1.