CITY OF PUYALLUP PERMITTING PORTAL
Permit Application Status
PRCTI20250853
Paid Fees | Amount | Paid | Owing | Date Paid |
---|---|---|---|---|
Building Plan Review Fee | $2,873.81 | $2,873.81 | Paid | 06/25/2025 |
Mechanical Plan Review Fee | $26.00 | $26.00 | Paid | 06/25/2025 |
Plumbing Plan Review Fee | $69.06 | $69.06 | Paid | 06/25/2025 |
Outstanding Fees | Amount | Paid | Owing | Date Paid |
Fire Review Fee (Commercial Building) | $265.00 | $0.00 | Not payable | Not Paid |
Building Permit Fee | $4,421.25 | $0.00 | Not payable | Not Paid |
Mechanical Permit Fee | $40.00 | $0.00 | Not payable | Not Paid |
Drinking Fountain, Water Cooler, Ice Machine Fee | $40.25 | $0.00 | Not payable | Not Paid |
Plumbing Permit Fee | $40.00 | $0.00 | Not payable | Not Paid |
Water Heater Fee | $26.00 | $0.00 | Not payable | Not Paid |
WA State Building Code Council Fee (Commercial) | $25.00 | $0.00 | Not payable | Not Paid |
Sewer System Development ChargeFee - Tenant Improvment/Addition | $31,620.96 | $0.00 | Not payable | Not Paid |
Resubmittal Fee | $180.00 | $0.00 | $180.00 | Not Paid |
Totals: | $39,627.33 | $2,968.87 | $180.00 |
Permit(s) will not be issued until outstanding fees have been paid in full. Fee details shown above only include currently payable fees, there might be addtional fees to be paid before issuance.
$180.00 Add Fees to My Cart
There are no inspections for this permit application, or you are not authorized to view them.
Condition | Status | Category |
---|---|---|
Building Permit Standard Conditions | Open | Standard Conditions |
Building Division
* Final approval by the Building Official is required prior to use or occupancy.* Work shall not proceed until the inspector has approved the stages of construction.* Surface storm water shall be diverted from the building site and shall not drain onto adjacent properties.* I hereby acknowledge that I have read this Permit/Application, that the information given is correct; that I am the owner or the duly authorized agent of the owner; that plans submitted herewith are in compliance with all applicable city, county and state laws and that all construction will proceed in accordance with said laws. This permit shall expire if work is not commenced with 180 days or if the work is suspended for a period of 180 days. Permits expire two years from issuance. * By leaving the contractor information section blank, I hereby certify further that contractors (general or subcontractors) will not be hired to perform any work in association with this permit. I also certify that if I do choose to hire a contractor (general or subcontractor) I will only hire those contractors that are licensed by the State of Washington. If you are a property owner, contractor or permittee and you are paying for someone to perform the work, they must have a valid contractor registration and the person(s) installing plumbing inside a structure must meet the plumbing certification requirements. If you have any questions regarding these regulations, you may contact the Washington State Department of Labor and Industries or you can find more information on-line at: http://www.lni.wa.gov/TradesLicensing/Contractors/HireCon/default.asp
|
||
Fire Review Conditions | Open | Standard Conditions |
• Comply with 2018 IFC and 2018 IBC
• Total coverage required in the city of puyallup
• L&I Final required prior to Fire Final
• Exit lighting test required contractor to provide light meter
• Separate permits required for Fire Alarm and Fire Sprinkler
• RTU’S will be required to be tested for shut down.
• Fire extinguishers required per code
• A Knox box is required at the front entry on the exterior of the building
• PIV must have a Knox lock or approved lock with an extra key provided in Knox box
• Existing buildings will need to contact central pierce fire & rescue and update the key in the Knox box
• All above items to be completed prior to fire final. Fire final required before building final
Schedule your inspection online through the City of Puyallup online permit system. This is a request for inspection only. A date and time will be selected by Inspector depending on availability. Email prior to inspection for date and time. Fire Inspections are Monday – Thursday there will be no inspections on Fridays.
David Drake 253-864-4171 ddrake@puyallupwa.gov
|
||
Certificate of Water Availability - Fruitland Mutual Water Company | Resolved | Prior to Issuance |
Engineering Division
A certificate of water availability is required from Fruitland Mutual Water Company, the site’s water purveyor. You can initiate the certificate request by completing the application found here: http://www.fruitlandwater.com/Water_availability_letter_only.pdf and submitting it to Fruitland Mutual. (PMC 14.22.020)
|
||
Frontage Improvements - Non-Residential Tenant Improvements | Resolved | Prior to Issuance |
Engineering Division
In accordance with Puyallup Municipal Code 11.08.135, non-residential tenant improvement projects that qualify as substantial improvements (the cost of which equals or exceeds 50% of the market value of the structure before the “start of construction” of the improvement) and when the remodel valuation exceeds $500,000 are required to complete improvements along the property's street frontage. The former occupancy was retail (Group IIB, M - Mercantile).
Existing Valuation = [Mercantile (M), Construction Type IIB] $175.31/SF x 19,781 SF = $3,467,807.1. Project valuation per application = $750,000. The project does not qualify as a substantial improvement, and, therefore, frontage improvements are not required.
|
||
Plumbing FUW Utility Service Credit | Open | Standard Conditions |
Engineering Division
14.5 of the 26.5 available sewer credits from PRDE20240877 were redeemed on Boot Barn's tenant improvement permit PRCTI20240669. The 12 remaining sewer credits are hereby redeemed on permit PRCTI20250853. [Yianni Charitou @ 07/08/2025 8:33 AM]
|
||
Fire Sprinkler System (New) Conditions | Open | Standard Conditions |
Development & Permitting Services
• Provide plans and permit on site for inspection.
• Cover and final inspections are required.
• Fire watch is required when sprinkler system is out of service in existing buildings.
• Contractor required at all inspections.
• Hydro test will be required on all new and existing buildings. Appointment required.
• Hydro test, two inspections will be required 2hrs apart. Call to schedule times. Am/pm is not guaranteed without appointment
• Fire pumps will be required to be tested and witnessed by inspector.
• Tool kit required at time of final.
• NFPA placards required
• In existing buildings all upright fire sprinklers to remain, do not remove.
• In existing buildings all required service and maintenance to be updated prior to inspection.
• Due to unforeseeable construction design, all head locations to be field verified for compliance.
Schedule your inspection online through the city of puyallup online permit system after requesting appointment from inspector. Fire Inspections are Monday – Thursday there will be no inspections on Fridays.
David Drake 253-864-4171 ddrake@puyallupwa.gov
|
||
New Fire Alarm System Conditions | Open | Standard Conditions |
Fire Prevention
• Appointment required for all inspections am/pm is not guaranteed without appointment. Larger systems taking more than 1 hour will require 48-72hr notice prior to scheduling. Inspections are Monday - Thursday, no friday inspections
• Provide plans and permit on site for inspection.
• Complete labor and industries inspections prior to requesting city inspection.
• A remote annunciator located at the main entrance is required. If there is an existing annunciator on the exterior of the building it will need to be moved inside the main entrance. Please contact fire inspector for further information.
• Exterior fire bell required outside fire sprinkler room.
• Above ceiling detection is required.
• Device maps required at the annunciator and fire alarm panel prior to calling in final. The annunciator map will need to be weatherproof.
• Total coverage is required, subject to field inspection. Comply with NFPA 72, 2019
• Fire alarm system shall be placarded per NFPA 72. The UL certificate shall be posted at time of final inspection. The system will need to be UL certified.
• A pre-test shall be conducted and a printout of the location of the device, point number and descriptor shall be furnished to the inspector at final. Labeling of all devices above and below ceiling required.
• Fire sprinkler tamper valves and PIV will be required to be tested at inspection. Fire sprinkler contractor to be onsite.
• RTU’S and smoke dampeners will be required to be tested during inspection.
• The city of Puyallup allows one FACP per building. The panel will need to be large enough to handle multiple tenants if applicable.
• In existing buildings all above ceiling detection is to remain. Do not remove.
• Due to unforeseeable construction design, all device locations to be field verified for compliance.
Schedule your inspection online through the city of puyallup online permit system after requesting appointment from inspector. Fire Inspections are Monday – Thursday there will be no inspections on Fridays.
David Drake 253-864-4171 ddrake@puyallupwa.gov
|
Reference Number | Status | Type |
---|---|---|
PRCTI20250870 | Ready for Issuance | Commercial - Tenant Improvement/Remodel |
Date Uploaded | File Type | Name |
---|---|---|
06/25/2025 | Receipt | Receipt for transaction:2025-001240 |
07/02/2025 | Form | 0853 WA SITE PLAN |
07/14/2025 | Letter | Permit Review Correction Letter |
07/14/2025 | Form | Electrical Compliance Summary (Flattened) |
07/14/2025 | Form | Mechanical Compliance Summary (Flattened) |
07/14/2025 | Form | 20250853 APPLICATION (Flattened) |
07/14/2025 | Plans | 2025-06-02 PF Puyallup (Permit Set) (Flattened) |
07/14/2025 | Form | PLUMBING FIXTURE WORKSHEET (Flattened) |
Should you need assistance, please contact the Permit Center at (253) 864-4165 option 1.
Powered by CityView