CITY OF PUYALLUP PERMITTING PORTAL
Permit Application Status
PRDE20231749
In order to request inspections, you need to be signed in.
There are no fees for this permit application, or you are not authorized to view them.
Inspection | Outcome | Requested | Scheduled | Date Inspected |
---|---|---|---|---|
Erosion And Sediment Inspection | Partial Pass | 1/29/2024 | 1/29/2024 | 01/29/2024 |
Michael Rosenau ((253) 344-6753) | ||||
Job Start Inspection | Partial Pass | 1/29/2024 | 01/29/2024 | |
Michael Rosenau ((253) 344-6753) | ||||
Engineering Daily Inspection | Partial Pass | 1/30/2024 | 01/30/2024 | |
Michael Rosenau ((253) 344-6753) | ||||
Engineering Daily Inspection | Partial Pass | 1/31/2024 | 01/31/2024 | |
Michael Rosenau ((253) 344-6753) | ||||
Engineering Daily Inspection | Partial Pass | 2/1/2024 | 02/01/2024 | |
Michael Rosenau ((253) 344-6753) | ||||
Engineering Daily Inspection | Partial Pass | 2/2/2024 | 02/02/2024 | |
Michael Rosenau ((253) 344-6753) | ||||
Engineering Daily Inspection | Partial Pass | 2/5/2024 | 02/05/2024 | |
Michael Rosenau ((253) 344-6753) | ||||
Demolition Final Inspection | Not Ready | 4/24/2024 | 4/24/2024 | 04/24/2024 |
Shannon King ((253) 840-6684) | ||||
Other/Miscellaneous
Carried Forward
04/24/2024
1 ; provide engineering final prior to building final inspection. not ready
|
Condition | Status | Department | Category | Expiration Date | Due Date |
---|---|---|---|---|---|
Building Permit Standard Conditions | Open | Building Division | Standard Conditions | ||
:
* Final approval by the Building Official is required prior to use or occupancy.* Work shall not proceed until the inspector has approved the stages of construction.* Surface storm water shall be diverted from the building site and shall not drain onto adjacent properties.* I hereby acknowledge that I have read this Permit/Application, that the information given is correct; that I am the owner or the duly authorized agent of the owner; that plans submitted herewith are in compliance with all applicable city, county and state laws and that all construction will proceed in accordance with said laws. This permit shall expire if work is not commenced with 180 days or if the work is suspended for a period of 180 days. Permits expire two years from issuance. * By leaving the contractor information section blank, I hereby certify further that contractors (general or subcontractors) will not be hired to perform any work in association with this permit. I also certify that if I do choose to hire a contractor (general or subcontractor) I will only hire those contractors that are licensed by the State of Washington. If you are a property owner, contractor or permittee and you are paying for someone to perform the work, they must have a valid contractor registration and the person(s) installing plumbing inside a structure must meet the plumbing certification requirements. If you have any questions regarding these regulations, you may contact the Washington State Department of Labor and Industries or you can find more information on-line at: http://www.lni.wa.gov/TradesLicensing/Contractors/HireCon/default.asp
|
|||||
Demolition Standard Conditions | Open | Engineering Division | Standard Conditions | ||
:
Development Engineering standard demolition conditions:
** Prior to STARTING the applicant shall request an erosion and sediment control inspection using the CityView permit portal at least 48 hours in advance of job start **
** Attached in CityView you will find a document titled 01 STORMWATER FACT SHEET AND SEDIMENT & EROSION DETAIL. Methods described in this document must be implemented for sediment and erosion control during construction. Provide the City detailed information on the methods that will be used **
1. All inspections shall be requested through the CityView portal. The job start and erosion and sediment inspections shall be passed prior to starting work.
2. Sediment control and erosion procedures shall be practiced to eliminate and prevent off site damage. Stormwater runoff originating upgrade of exposed areas shall be controlled to reduce erosion and sediment loss during the period of exposure. Refer to the City standard details 02.03.02 & 05.02.01 for typical erosion and sedimentation control methods.
3. The applicant shall call the Utility Notification Center at 1-800-424-5555 before beginning any work. Call 811 before you dig, it's the law.
Site-specific Conditions:
** The city has no record of sewer or water connection. At the issuance of this permit no fees have been assessed for the removal and inspection water or sewer disconnect. Fees will need to be assessed and paid if there is a water or sewer connection prior to granting a final inspection **
The application states this site is being served by City sewer: However, the City of Puyallup has no record of a sanitary sewer connection. As a result one or both of the following conditions must be completed and approved prior to a final inspection of the demolition is provided:
** The applicant shall cut and cap the sanitary sewer lateral on the customer's side of the cleanout located at the property line, under the supervision of a City Inspector, prior to any demolition. The existing sewer lateral shall not be reused. The applicant shall request an inspection through the CityView portal. Utility inspections are required prior to backfilling **
OR
** The applicant is responsible to demolish the existing septic system per Tacoma Pierce County Health Department standards. A septic decommissioning certificate is required to be filed with Pierce County and a copy submitted to the City of Puyallup **
The application states this site is being served by City water. The City of Puyallup has no record of a water service connection. As a result one or both of the following conditions must be completed and approved prior to a final inspection of the demolition is provided:
** The applicant is responsible to cut and cap the water service at the property line while under the supervision of a city inspector. Schedule an inspection by calling 1-877-232-6456, code #2925. The City Water Division shall perform the water meter removal. Contact Jeff Daschofsky at 253-841-5512 to schedule the water meter removal **
OR
** The applicant is responsible to demolish the existing private well per Pierce County Health Department Requirements. A well decommissioning certificate is required to be filed with Pierce County and a copy shall be provided to the City of Puyallup. If the well is to remain for irrigation purposes a Reduced Pressure Backflow Assembly is required. See the attached City of Puyallup Standard Detail 03.04.02 **
I hereby acknowledge that I have read and understand the contents of this permit and I hereby state that the information I have supplied is true and correct.
Indemnification / Hold Harmless
The Permittee shall defend, indemnify and hold the Public Entity, its officers, officials, employees and volunteers harmless from any and all claims, injuries, damages, losses or suits including attorney fees, arising out of or in connection with activities or operations performed by the Permittee or on the Permittee's behalf out of issuance of this Permit, except for injuries and damages caused by the sole negligence of the Public Entity.
However, should a court of competent jurisdiction determine that RCW 4.24.115 applies to this Permit, then the Permittee agrees to defend, indemnify and hold the Public Entity, its officers, officials, employees and volunteers harmless to the maximum extent permitted thereunder. It is further specifically and expressly understood that the indemnification provided herein constitutes the Permittee's waiver of immunity under Industrial Insurance, Title 51 RCW, solely for the purposes of this indemnification. This waiver has been mutually negotiated by the parties. The provisions of this section shall survive the expiration or termination of this Agreement.
|
|||||
Miscellaneous Condition | Resolved | Engineering Division | Prior to Completion | ||
:
Engineering Inspector please let an engineer reviewer know if this property was connected to city water and/or sewer. After speaking with PW and utility billing there are no records of water or sewer connection. At the issuance of this permit no fees have been assessed for water or sewer. Fees will need to be assessed and paid if there is a water or sewer connection prior to granting a final inspection. LL 01/10/204
SFR served by private well and was on septic. MR 4/26/24.
|
|||||
Miscellaneous Condition | Open | Planning Division | |||
:
Limited to within 5' of all structures and a high visibility fence must be erected along this perimeter.
|
|||||
Miscellaneous Condition | Open | Planning Division | |||
:
No vegetation may be removed as part of the demolition.
|
There are no related items for this permit application.
Date Uploaded | File Type | Name |
---|---|---|
01/12/2024 | Plans | 1749 SITE PLAN (Stamped) |
01/12/2024 | Form | 2007 Shaw Demo App (Flattened) |
01/12/2024 | Permit | Permit - Detailed |
01/12/2024 | Letter | Permit Job Card |
01/12/2024 | Plans | PRDE20231749 STORMWATER FACT SHEET AND SEDIMENT & EROSION DETAIL (Flattened) |
01/12/2024 | Other | PSAN (Stamped) |
01/29/2024 | Report | Inspection Report (Erosion And Sediment Inspection) |
04/24/2024 | Report | Inspection Report (Demolition Final Inspection) |
04/26/2024 | Report | Inspection Report (Engineering Daily Inspection) |
04/26/2024 | Septic Decom_ 2007 Approved Certificate 20240425 | |
04/26/2024 | Well Decomm Bond | |
12/18/2023 | Letter | Incomplete Application Notice |
12/19/2023 | Letter | Incomplete Application Notice |
Should you need assistance, please contact the Permit Center at (253) 864-4165 option 1.