Summary

PRRF20221329
Re-Roof
Closed
WAL-MART RE BUSINESS TR 2403
Alteration/Remodel
Reskin & Recover-An infrared moisture survey will need to be performed prior to installing the recovery roof, in which the results will be provided to the Contractor to indicate deficient areas and the requirement of existing roof and insulation removal. Existing wet insulation and overlying membrane should be removed as initially determined to be deficient. Additional removal shall be performed as necessary as determined at the site by the Contractor or Consultant, and approved by the Owner. Removal of membrane and insulation shall be to decking material. Contractor shall inspect the deck to identify unsuitable conditions. Unsuitable conditions (i.e. rusted or damaged metal) shall be reported to the Owner prior to subsequent work thereon, and repaired or replaced prior to installation of the new roof system. Fill void created by removal of the existing roof system with insulation that matches the existing to the level of existing adjacent roof surface. Fill voids in a manner standard with the industry and approved by the roofing manufacturer.Existing Membrane Removal: Cut and remove the top layer of EPDM membrane in its entirety, including in-seam fasteners. Remove the underlying polyisocyanurate coverboard and the original layer of EPDM membrane, with the exception of four-inch wide strip at in-seam fasteners. The base layer of 3”polyisocyanurate insulation is to remain. Wet insulation should be removed as determined to be deficient during membrane removal. Removal of wet insulation shall be to roof deck. Contractor shall inspect the deck to identify any unsuitable conditions. Unsuitable conditions (i.e. rusted or damaged metal) shall be reported to the Owner prior to subsequent work thereon, and repaired or replaced prior to installation of the new roof system. Fill void created by removal of wet insulation with insulation that matches the existing to the level of existing adjacent roof surface. Fill voids in a manner standard with the industry and approved by the roofing manufacturer. Overlay existing roof system with a new 60 mil mechanically attached TPO membrane roofing system, perpendicular to steel deck ribs, in accordance with manufacturer and current Wal-Mart specifications. Replacing existing skylights with new WA. ST. energy code compliant skylights.
08/29/2022
10/05/2022
08/02/2023
02/03/2023

Locations

Reviews

Documents Returned For Corrections

Review Type Outcome Est. Completion Date Completed
Building Review Approved 10/02/2022 10/03/2022
Building Review Failed 10/01/2022 09/27/2022

Fees

Paid Fees Amount Paid Owing Date Paid
Building Permit Fee $4,264.50 $4,264.50 Paid 10/05/2022
Building Plan Review Fee $2,771.93 $2,771.93 Paid 08/29/2022
WA State Building Code Council Fee (Commercial) $25.00 $25.00 Paid 10/05/2022
Resubmittal Fee $130.00 $130.00 Paid 09/27/2022
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


Permit(s) will not be issued until outstanding fees have been paid in full. Fee details shown above only include currently payable fees, there might be addtional fees to be paid before issuance.

$0.00

Inspections

Inspection Outcome Requested Scheduled Date Inspected
Roof Sheathing Inspection Passed 10/26/2022 10/26/2022 10/26/2022
Kevin Spruell ((253) 841-5590)
Comment Building Div Inspection Partial Pass 11/9/2022 11/9/2022 11/09/2022
Kevin Spruell ((253) 841-5590)
Re-Roof Inspection Failed 1/25/2023 1/25/2023 01/25/2023
Shannon King ((253) 840-6684)
Corrections:


Other/Miscellaneous
Carried Forward
01/25/2023
1; provide manufacturers warranty at time of final inspection. 2 ; reconnect all electrical boxes to wall or a approved location with sealed electrical conduit. 3 ; complete all condensate drain as discussed with contractor. 4 ; repair damaged termination cap at south side of roof. 5 ; complete all downspout as discussed with contractor.

Building Final Inspection Not Ready 1/31/2023 1/31/2023 01/31/2023
Shannon King ((253) 840-6684)
Corrections:


Other/Miscellaneous
Carried Forward
01/31/2023
cancel per contractor - not ready

Building Final Inspection Passed 2/3/2023 2/3/2023 02/03/2023
Kevin Spruell ((253) 841-5590)
Corrections:


Other/Miscellaneous
Resolved
02/03/2023
cancel per contractor - not ready

Comment Building Div Inspection VOID 02/03/2023
Kevin Spruell ((253) 841-5590)
Re-Roof Inspection VOID 02/03/2023
Kevin Spruell ((253) 841-5590)
Corrections:


Other/Miscellaneous
Outstanding
01/25/2023
1; provide manufacturers warranty at time of final inspection. 2 ; reconnect all electrical boxes to wall or a approved location with sealed electrical conduit. 3 ; complete all condensate drain as discussed with contractor. 4 ; repair damaged termination cap at south side of roof. 5 ; complete all downspout as discussed with contractor.

Conditions

Condition Status Category
Building Permit Standard Conditions Open Standard Conditions
* Final approval by the Building Official is required prior to use or occupancy.* Work shall not proceed until the inspector has approved the stages of construction.* Surface storm water shall be diverted from the building site and shall not drain onto adjacent properties.* I hereby acknowledge that I have read this Permit/Application, that the information given is correct; that I am the owner or the duly authorized agent of the owner; that plans submitted herewith are in compliance with all applicable city, county and state laws and that all construction will proceed in accordance with said laws. This permit shall expire if work is not commenced with 180 days or if the work is suspended for a period of 180 days. Permits expire two years from issuance. * By leaving the contractor information section blank, I hereby certify further that contractors (general or subcontractors) will not be hired to perform any work in association with this permit. I also certify that if I do choose to hire a contractor (general or subcontractor) I will only hire those contractors that are licensed by the State of Washington. If you are a property owner, contractor or permittee and you are paying for someone to perform the work, they must have a valid contractor registration and the person(s) installing plumbing inside a structure must meet the plumbing certification requirements. If you have any questions regarding these regulations, you may contact the Washington State Department of Labor and Industries or you can find more information on-line at: http://www.lni.wa.gov/TradesLicensing/Contractors/HireCon/default.asp
Re-Roof Conditions Open Standard Conditions
RE-ROOF 1) PROVIDE MANUFACTURES SPECIFICATIONS AND INSTALLATION DETAILS ON SITE FOR INSPECTION 2) CALL FOR REQUIRED INSPECTIONS PRIOR TO COVER; REQUIRED FOR SHEATHING REPLACEMENT, STRUCTURAL REPAIR OR INSULATION 3) PROVIDE INSPECTION ACCESS 4) PROVIDE A COPY OF THE PERMIT ON SITE ***MUST PROVIDE DRIP EDGE ON ALL ROOF EDGES***
Contaminated Site Remediation Open Standard Conditions
Engineering Division
The subject property has been classified as a contaminated site by the Tacoma Pierce County Health Department (TPCHD) and must be remediated per Washington Administrative Code Title 173. It is the applicant’s responsibility to coordinate cleanup with TPCHD. Visit https://www.tpchd.org/healthy-places/contaminated-property-cleanup for more information. The applicant shall request a remediation status report from TPCHD’s Rob Olsen by emailing him at rolsen@tpchd.org. Provide a copy of the status report to the City.
Miscellaneous Condition Open Submit With Building Permit Application
Development & Permitting Services
FRUITLAND W/A REQUIRED AT TIME OF SUBMITTAL. SENT EMAIL -JF 8.31.22 susan@clifford-lee.com

Related Permit & Planning Applications

There are no related items for this permit application.

Documents & Images

Date Uploaded File Type Name
08/29/2022 Receipt Receipt for transaction:2022-001693
09/27/2022 Receipt Receipt for transaction:2022-001911
10/04/2022 Other 2403 SUBMITTAL (Stamped)
10/04/2022 Other 00 WM #2403 Puyallup, WA - (PreCon Full Summary) (Stamped)
10/04/2022 Plans 04 Damaged Insulation Extents (Stamped)
10/05/2022 Permit Permit - Detailed
10/05/2022 Letter Permit Job Card
10/26/2022 Report Inspection Report (Roof Sheathing Inspection)
11/09/2022 Report Inspection Report (Comment Building Div Inspection)
01/25/2023 Report Inspection Report (Re-Roof Inspection)
01/31/2023 Report Inspection Report (Building Final Inspection)
02/03/2023 Roof system warranty page 1
02/03/2023 Roof system warranty page 2
02/03/2023 Report Inspection Report (Building Final Inspection)