|
Other/Miscellaneous
Traffic scoping worksheet will be required. City policy requires the project trips to be estimated using the Institute of Transportation Engineers’ (ITE) Trip Generation, 11th Edition. In general, trip generation regression equations shall be used when the R2 value is 0.70 or greater. For single-family units and offices smaller than 30,000 SF, use ITE’s Trip Generation, average rate. The project trips shall be rounded to the nearest tenth. Trip credits would be allowed for any existing development.
The city has adopted a City-Wide Traffic Impact Fee of $4,500 per PM peak hour trip. Final fees will be calculated and assessed by the City at the time of building permit issuance.
Park Impact Fee (Per residential dwelling Unit):
Less than 500 sqft $1,560.05
500 - 999 sqft $2,313.53
1,000 – 1,999 sqft $3,291.31
2,000 sqft or more $4,017.30
ADUs are charged 80% less for Traffic Impact Fees & Park Impact Fees.
Per Puyallup Municipal Code Section 11.08.135, the applicant/owner would be expected to construct half-street improvements including curb, gutter, planter strip, sidewalk, roadway base, pavement, and street lighting. Any existing improvements which are damaged now or during construction, or which do not meet current City Standards, shall be replaced.
o 9th St SW – old curb cuts need to be replaced – City inspector would need to go out and evaluate the existing condition of pavement & frontage. Any sidewalk panels or curb/gutter that are in poor condition would need to be replaced
o 10th St SW would need to be constructed to current City standards include new curb/gutter/sidewalk and planter strip. The existing utility pole located on the corner would need to be relocated
The City Engineer would be open to accepting fee-in-leu as an alternative to constructing frontage. As a condition, the City would still require the roadway width to be widened to 20ft with the fee-in-leu option.
|
|
Other/Miscellaneous
ENGINEERING – Lance Hollingsworth (253) 290-2126 lhollingsworth@puyallupwa.gov
Engineered plans must follow the latest regulations and standards set forth in the Puyallup Municipal Code (PMC), the City Standards for Public Works Engineering and Construction (design standards), and the current City adopted stormwater manual at the time of civil permit application [PMC 21.10.040].
The stormwater design associated with this Development Permit will be reviewed for compliance with the 2014 amended Stormwater Management Manual for Western Washington (ECY manual), which is the current adopted stormwater manual.
The comments provided below are project-specific in nature and should not be considered an exhaustive list of the requirements from the PMC, Design Standards, or the ECY manual.
CIVIL PERMIT APPLICATION
A civil permit application is required for any project required to construct frontage at a site that doesn’t have existing vertical curb, and a project proposing new connections to city.
• Civil engineering drawings will be required for this project prior to issuance of the first building permit (The city has transitioned to electronic review. Please reach out to the city permit technicians at PermitCenter@PuyallupWA.gov and they will guide you how to submit). Included within the civil design package will be a utility plan overlaid with the landscape architects landscaping design to ensure that potential conflicts between the two designs have been addressed. Engineering plans cannot be accepted until Planning Department requirements have been satisfied, including but not limited to, SEPA, Preliminary Site Plan approval, CUP, and/or Hearing Examiner conditions.
• Civil engineering plan review fee is $670.00 (plus an additional per hour rate of $130.00 in excess of 5 hours). The Civil permit shall be $300.00 and the inspection fee shall be 3% of the total cost of the project as calculated on the Engineering Division Cost Estimate form. [City of Puyallup Resolution No. 2098]
• Civil Engineering drawings shall conform to the following City standards Sections 1.0 and 2.0:
o Engineering plans submitted for review and approval shall be on 24 x 36-inch sheets.
o Benchmark and monumentation to City of Puyallup datum (NAVD 88) will be required as a part of this project / plat.
o The scale for design plans shall be indicated directly below the north arrow and shall be only 1”=20’ or 1”=30’. The north arrow shall point up or to the right on the plans.
o Engineering plan sheets shall be numbered sequentially in this manner: Sheet 1 of 20, Sheet 2 of 20, etc. ending in Sheet 20 of 20.
o All applicable City Standard Notes and Standard Details shall be included on the construction plans for this project. A copy of the City Standards can be found on the City’s web site under Office of the City Engineer, Engineering Services.
UTILITIES:
The utilities requirements in the notes below applies to the scenario the project becomes a Duplex with an ADU.
WATER
Water Within City Service Area:
• There is a 6” Cast Iron Public water main on the opposite side of 9th St SW and a 6” Ductile Iron public water main ending approximately 90 feet west of the subject parcel on the parcel side of 10th Ave SW.
• A water meter box serving this parcel exists at the time the GIS imagery was taken in the frontage of 9th ST SW. This is not verification of the presence of an existing meter.
• Any proposed water system shall be designed and constructed to current City standards. [PMC 14.02.120]
Water Meter Options
Option 1
Provide 2 meters to provide water to the Owner Unit/ADU and the tenant unit. This method charges each owner individually for water consumption.
Option 2
Provide a single water meter and split water costs among tenants.
• Any wells on the site must be decommissioned in accordance with Washington State requirements. Documentation of the decommissioning must be provided along with submittal of engineering drawings. If an existing well is to remain, the well protection zone shall be clearly delineated and appropriate backflow protection (Reduced Pressure Backflow Assemblies) shall be installed at all points of connection to the public water system. [PMC 14.02.220(3)(b)]
• The City will provide and install the water meters required to service the site. Note: a 1” minimum water meter is required for buildings requiring a sprinkler system [PMC 14.02.120(f) & CS 301.3]
• To demo a private well: The applicant is responsible to demolish the existing private well per Tacoma Pierce County Health Department requirements. A decommissioning certificate shall be filed with Pierce County and a copy submitted to the City of Puyallup.
• Any existing services that are to be abandoned at this site shall be disconnected at the main, the corp. stop removed, and the service plugged to city standards. [PMC 14.02.120(f)]
Backflow Protection:
• If a Fire Sprinkler system is required, a reduced pressure backflow assembly (RPBA) will be required on the domestic line at each location where the proposed water main connects to the public system. [PMC 14.02.220(3) & CS 302]
• If an RPBA is not appropriate then the applicant shall provide backflow protection with the installation of a double check valve assembly (DCVA) on the domestic connection to the public water main. A plumbing permit is required for this work to be completed; and the unit should be located outside the building, immediately downstream of the existing water meter if possible. If an irrigation system is also proposed, a DCVA is required on that line as well. [PMC 14.02.220(3) & CS 302.2]
SEWER
• There appears to be a sewer cleanout on the property connected to an 8” concrete sewer Main in 9th St SW.
• There is also an 8” concrete sewer main in 10th Ave SW.
• The proposed sewer system shall be designed and constructed to current City standards. [PMC 14.08.070]
• Side sewers shall have a cleanout at the property line, at the building, and every 100 feet between the two points. [PMC 14.08.120 & CS 401(6)]
• The applicant may need to provide a new connection into the existing public system located within 9th St SW.
• The City Sewer Department must conduct a visual inspection of a previously used side sewer to determine if that side sewer can be used again. Existing laterals must meet current standards to be used again. It is the responsibility of the property owner to expose the line as necessary for that inspection. The City reserves the right to request video inspection of the side sewer to assist in its determination. Redevelopment projects shall utilize the existing trench where possible. CS 401(15) and CS 401(16)
STORMWATER
• There is currently a 24” Storm Main in 9th SW and a drainage ditch on the opposite side of 10th Ave SW.
• Design shall occur pursuant to the 2012 Stormwater Management Manual for Western Washington as amended in December, 2014 (The 2014 SWMMWW). Note that the city is adopting the 2019 Ecology manual in June of 2022. Vesting to an Ecology manual is granted with an approved permanent stormwater plan as part of a City of Puyallup permit.
• Preliminary feasibility/infeasibility testing for infiltration facilities shall be in accordance with the site analysis requirements of the Ecology Manual, Volume I, Chapter 3, specifically:
- Groundwater evaluation, either instantaneous (MR1-5) or continuous monitoring well (MR1-9) during the wet weather months (December 21 through April 1).
- Hydraulic conductivity testing:
o If the development triggers Minimum Requirement #7 (flow control), if the site soils are consolidated, or is encumbered by a critical area a Small Scale Pilot Infiltration Tests (PIT) during the wet weather months (December 21 through April 1) is required.
o If the development does not trigger Minimum Requirement #7, is not encumbered by a critical area, and is located on soils unconsolidated by glacial advance, grain size analyses may be substituted for the Small Scale PIT test at the discretion of the review engineer.
- Testing to determine the hydraulic restriction layer.
- Mounding analysis may be required in accordance with Ecology Volume III Section 3.3.8.
• The applicant shall include a completed stormwater flowchart, Figure 3.1, contained in Ecology’s Phase II Municipal Stormwater Permit, Appendix I with the stormwater site plan. The link below may be used to obtain the flowchart:
https://ecology.wa.gov/DOE/files/7a/7a6940d4-db41-4e00-85fe-7d0497102dfd.pdf
• The following items shall be included at the time of Civil permit submittal:
o A permanent storm water management plan which meets the design requirements provided by PMC Section 21.10. The plan and accompanying information shall provide sufficient information to evaluate the environmental characteristics of the affected areas, the potential impacts of the proposed development on surface water resources, and the effectiveness and acceptability of measures proposed for managing storm water runoff. The findings, existing and proposed impervious area, facility sizing, and overflow control shall be summarized in a written report. [PMC 21.10.190, 21.10.060]
o A written technical report that clearly delineates any offsite basins tributary to the project site and includes the following information: [PMC 21.10.060]
o the quantity of the offsite runoff;
o the location(s) where the offsite runoff enters the project site;
o how the offsite runoff will be routed through the project site.
o the location of proposed retention/detention facilities
o and, the location of proposed treatment facilities
• All private storm drainage facilities shall be covered by a Stormwater Management & BMP Facilities Agreement provided by the City and recorded with Pierce County. Under this agreement if the owner fails to properly maintain the facilities, the City, after giving the owner proper notice, may perform necessary maintenance at the owner’s expense.
For Properties in the Floodplain (PMC 21.07.050)
AE Zone
• This site is within a Special Flood Hazard Area as determined by the National Flood Insurance Program Community Panel Number 53053C0341E , dated March 7, 2017. Development of the property shall adhere to the regulations contained in PMC Chapter 20.49 and Chapter 21.07. Specifically:
- The applicant shall submit a habitat assessment prepared by a qualified professional evaluating the effects and/or indirect effects of the proposed development (during both construction and post-construction) on floodplain functions and documenting that the proposed development will not result in “take” of any species listed as threatened or endangered under the Endangered Species Act (ESA).
- If less than 1:1 compensatory storage is proposed, the written assessment shall include a hydrologic and hydraulic analysis to determine any effects on floodplain storage capacity, increased flood heights, or increased velocities.
- If it is determined that the proposed project will impact any listed species or their habitat, the applicant shall provide a mitigation plan to achieve equivalent or greater biologic functions as those lost prior to development of the site.
- New construction and substantial improvement of any structure will require that the lowest floor, including the basement, shall be elevated 1-foot above the base flood. This can best be done with Stem walls and flood vents.
- The Garage may be within the floodplain, but any electronic equipment inside the garage shall be placed 1 foot above the flood plain.
FEES
• Water and sewer connection fees and system development charges are due at the time of building permit issuance and do not vest until time of permit issuance. Fees are increased annually on February 1st.
• Stormwater system development fees are due at the time of civil permit issuance for commercial projects and at the time of building permit issuance for single family or duplex developments and do not vest until time of permit issuance. Fees are increased annually on February 1st.
New Development
Water
• For each building, a water system development charge (SDC) will be assessed based on the number of “residential” units in the facility. Current SDC’s as of this writing are $4,260.00 for the first residential unit and $3,195.00 for each additional unit per building. [PMC 14.02.040, 14.10.030]
Sewer
• For each building, a sanitary sewer system development charge (SDC) will be assessed based on the number of “residential” units in the facility. Current SDC’s as of this writing are $5,890.00 for the first residential unit and $4,417.50 for each additional unit. [PMC 14.10.010, 14.10.030]
Stormwater
• A Stormwater Systems Development fee will be assessed for each new equivalent service unit (ESU) in accordance with PMC Chapter 14.26. Each ESU is equal to 2,800 square feet of ‘hard’ surface. The current SDC as of this writing is $3,560.00 per ESU.
|