Review Type |
Outcome |
Est. Completion Date |
Completed |
Building Review
|
Comments
|
06/08/2023
|
06/09/2023
|
|
|
|
Other/Miscellaneous
Building plans will need to be complete with all building, mechanical, plumbing, energy code items and accessibility requirements that apply to project.
Effective October 28, 2023 Electric Vehicle Charging Infrastructure are required in place for charging stations per IBC section 429 Washington State amendments for occupancy R’s and will need to be shown on the plans. **Note July 1, 2023 code changes have been postponed until October 28, 2023, the EV parking requirements change to require EV parking provided for all occupancies except occupancies classified as R-3 and U.
Plans will need to be per the applicable codes 2018 adopted February 1, 2021, for all permits. Unless submitted after October 28, 2023, or when States adopts code. (Currently extended from July 1, 2023)
All electrical is permitted by the Washington State Department L & I.
Accessible parking and access to the public way will be required. For all accessible requirements the City adopted the 2018 IBC / WAC 51-50 and the ICC A117.1-2009 standard. Minimum one electric vehicle charging infrastructure is required to be accessible.
**Note if permit is applied after October 28, 2023, there are significate vehicle charging infrastructure changes that includes additional accessibility requirements with the changes in the code.
If construction includes truss specs they are required with the truss engineers’ stamps and a layout that matches at the submitted of plans.
Please reach out to me if I can answer any other questions in relationship to Building code items for this project. No other Building items at this time.
|
|
|
Planning Review
|
Comments
|
06/08/2023
|
06/08/2023
|
|
|
|
|
Engineering Review
|
Comments
|
06/08/2023
|
06/06/2023
|
|
|
|
Other/Miscellaneous
CIVIL PERMIT APPLICATION
• Civil engineering drawings will be required for this project prior to issuance of the first building permit (The city has transitioned to electronic review. Please reach out to the city permit technicians at PermitCenter@PuyallupWA.gov and they will guide you how to submit). Included within the civil design package will be a utility plan overlaid with the landscape architects landscaping design to ensure that potential conflicts between the two designs have been addressed. Engineering plans cannot be accepted until Planning Department requirements have been satisfied, including but not limited to, SEPA, Preliminary Site Plan approval, CUP, and/or Hearing Examiner conditions.
• Civil engineering plan review fee is $670.00 (plus an additional per hour rate of $180.00 in excess of 5 hours). The Civil permit inspection fee shall be 3% of the total cost of the project as calculated on the City of Puyallup Engineering Division Cost Estimate form. [City of Puyallup Resolution No. 2098]
• Civil Engineering drawings shall conform to the following City standards Sections 1.0 and 2.0:
o Engineering plans submitted for review and approval shall be on 24 x 36-inch sheets.
o Benchmark and monumentation to City of Puyallup datum (NAVD 88) will be required as a part of this project / plat.
o The scale for design plans shall be indicated directly below the north arrow and shall be only 1”=20’ or 1”=30’. The north arrow shall point up or to the right pon the plans.
o Engineering plan sheets shall be numbered sequentially in this manner: Sheet 1 of 20, Sheet 2 of 20, etc. ending in Sheet 20 of 20.
o All applicable City Standard Notes and Standard Details shall be included on the construction plans for this project. A copy of the City Standards can be found on the City’s web site under Office of the City Engineer, Engineering Services.
|
|
Other/Miscellaneous
ACCESS
• A Covenant/Easement will be required for access to allow for any of the internal parcels to be granted access through other parcels from 15th St NW.
|
|
Other/Miscellaneous
GENERAL
• At time of civils, show all existing/proposed easements. There is an easement for a storm drainage pipe within 1410 15th St NW.
|
|
Other/Miscellaneous
|
|
Other/Miscellaneous
Frontage Code:
New Commercial/Industrial Buildings or Expansion of Existing buildings:
• Any person or entity who constructs or causes to be constructed any new commercial/industrial building or expansion of an existing commercial/industrial building either of which have a structure improvement value exceeding $200,000 in valuation shall construct curb, gutters, planter strips, street trees, sidewalks, storm drainage, street lighting, and one-half street paving (only required if the existing pavement condition is poor) in accordance with the city’s Public Works Engineering and Construction Standards and Specifications. The frontage improvements shall be required along all street frontage adjoining the property upon which such building will be placed. Frontage improvements shall also be required where any reasonable access to the property connects to the public right-of-way, although the primary access is located on another parcel. There is no cap on frontage improvements for new buildings or expansion of existing buildings.
Fee in Lieu -> Frontage Improvements
a. The applicant may request and submit justification to pay a fee rather than constructing all or part of the required frontage improvements. Allowance of fee-in-lieu shall be at the discretion of the city and may be denied if the city engineer determines it will be more beneficial to the public to have the frontage improvements built along the street frontage adjoining the property or access to the property. The city will consider the following:
o (i) The feasibility of accurately constructing improvements both horizontally and vertically to effectively drain runoff;
o (ii) Whether constructed improvements can transition and connect smoothly with existing adjacent sites; and
o (iii) Whether other frontage improvements will likely connect into the applicant’s required improvements within a reasonable time frame.
b. The justification to allow use of the fee-in-lieu program shall not be based on cost savings to applicant in comparison with constructing required improvement adjacent to the property. The program will be administered with the following conditions:
a. (i) Fees collected will be used towards pedestrian safety improvements, which could include lighting in the vicinity, ideally within one-half mile but up to one mile, from the contributing parcel in order to ensure that the improvements maintain a sufficient nexus to the project.
b. (ii) Fees for residential infill lots and commercial tenant improvements shall be based on linear frontage of developing parcel. The fees will be posted on the city’s web page, “Fee-In-Lieu Program” and are initially set at $200.00 per linear foot of frontage where no concrete curb exists and $100.00 per linear foot with existing curb. The fees will be adjusted annually according to construction cost indices. The current prices for 2022 are $211.80 per linear foot where no concrete curb exists. $105.90 per linear foot where existing curb exists at city standard location. If use of the fee-in-lieu program is for only a portion of the required frontage improvements, the fee will be established at an adjusted rate by the city engineer. If used for required frontage improvements from land subdivisions (formal plats, short plats, or binding site plans) and new commercial/industrial developments the fee will be developed based on the costs of installing the required improvements along the frontage of the development.
c. (iii) The fees shall be capped at 15 percent of remodel or project valuation.
d. (iv) Dedication of necessary right-of-way shall not be deferred or satisfied through payment of a fee-in-lieu.
e. (v) The city shall track the collection of fees and the location of improvements funded by fees collected.
|
|
Other/Miscellaneous
RIGHT OF WAY DEDICATION
• Right of way dedication will be required along 15th St NW.
|
|
Other/Miscellaneous
WATER
Water Within City Service Area:
• The proposed water system shall be designed and constructed to current City standards. [PMC 14.02.120]
• There is a 16” Ductile Iron water main located within 15th St SE. Additionally there is a 12” Ductile Iron water main within River Rd.
• Any wells on the site must be decommissioned in accordance with Washington State requirements. Documentation of the decommissioning must be provided along with submittal of engineering drawings. If an existing well is to remain, the well protection zone shall be clearly delineated, and appropriate backflow protection (Reduced Pressure Backflow Assemblies) shall be installed at all points of connection to the public water system. [PMC 14.02.220(3)(b)]
• A new water main line shall be extended to, and through, the site sufficient to provide the necessary flows for both the domestic system and fire system. The minimum water pipe size shall be 8-inch diameter. (Exception: A 4-inch water main may be installed if either, 1) the proposed main is a dead-end line with no possibility of being expanded in the future, or; 2) that portion of the proposed main beyond the last fire hydrant for the project.) The water main may need to be looped to ensure adequate fire flow/pressure. [PMC 14.02.190, 14.20.010 & CS 301.1(1)]
• The applicant shall be responsible for the operation and maintenance of the proposed water main located on private property.
• The domestic service line and fire system service line shall have a separate, independent connection to the supply main. If a separate fire line is to be utilized, a Double Check Valve Assembly (DCVA) will be required near the property line at the point of connection to the public main. The fire sprinkler double detector check valve assembly (DDCVA) may be located either inside, or outside, of the building. The sprinkler supply line shall be designed, and shown on the plan, into the building to the point of connection to the interior building riser. Provide plan and elevation detail(s) where the riser enters the building with dimensions, clearances, and joint restraint in accordance with NFPA 24. A post indicator valve (PIV) shall be provided for the fire sprinkler system in advance of the DDCVA. [PMC 14.02, CS 302.3, & CS 303]
• Based on the city’s mapping system, this area has greater than 1,950 GPM. If more fire flow information is necessary to complete the design, a hydraulic modeling permit will be required. The cost of this permit is currently $600.
• Fire hydrants shall be placed so that there is a minimum of 50-feet and a maximum 150-feet of separation from hydrants to any building walls. [PMC 16.08.080 & CS 301.2, 302.3]
• The Fire Department Connection (FDC) shall be located no closer than 10-feet and no further than 15-feet from a fire hydrant. [CS 302.3]
• Applicant shall provide backflow protection on the domestic line with the installation of a double check valve assembly (DCVA) on the domestic connection to the public water main. A plumbing permit is required for this work to be completed; and the unit should be located outside the building, immediately downstream of the existing water meter if possible. [PMC 14.02.220(3) & CS 302.2]
|
|
Other/Miscellaneous
SEWER
• The proposed sewer system shall be designed and constructed to current City standards. [PMC 14.08.070]
• There is an 8” PVC sewer main south of the manhole located at the southwest corner of 1410 15th St NW which is approximately 6.5’ deep. Additionally there is a 15” concrete main in the southern lane of River Rd.
• The project will need to utilize city standard 04.02.01 Sewer Main Tap for a connection to the City sewer main.
• The applicant shall connect into the existing public system located within River Rd If a proposed connection is to occur elsewhere, the applicant shall confirm that the system is located within a 40-foot easement dedicated to the City for maintenance purposes [PMC 14.08.070, PMC17.42 & CS 401(14)]
• The sewer main in River Rd varies in depth, but appears to be about 10’ deep.
• A separate and independent side sewer will be required from the public main to all building sites for each proposed lot. Side sewers shall be extended from the main 15-feet beyond the property line at the building site and shall be 6-inch minimum diameter with a 0.02 foot per foot slope. [PMC 14.08.110 & CS 401(7)]
• Side sewers shall have a cleanout at the property line, at the building, and every 100 feet between the two points. [PMC 14.08.120 & CS 401(6)]
• The construction of an area drain for the trash enclosure, if proposed, will require the enclosure to be covered to prevent stormwater infiltration into the sewer system.
|
|
Other/Miscellaneous
STORMWATER
• Design shall occur pursuant to the 2019 Stormwater Management Manual for Western Washington (The 2019 SWMMWW).
• Preliminary feasibility/infeasibility testing for infiltration facilities shall be in accordance with the site analysis requirements of the Ecology Manual, Volume I, Chapter 3, specifically:
- Groundwater evaluation, either instantaneous (MR1-5) or continuous monitoring well (MR1-9) during the wet weather months (December 21 through April 1).
- Hydraulic conductivity testing:
o If the development triggers Minimum Requirement #7 (flow control), if the site soils are consolidated, or is encumbered by a critical area a Small Scale Pilot Infiltration Tests (PIT) during the wet weather months (December 21 through April 1) is required.
o If the development does not trigger Minimum Requirement #7, is not encumbered by a critical area, and is located on soils unconsolidated by glacial advance, grain size analyses may be substituted for the Small Scale PIT test at the discretion of the review engineer.
- Testing to determine the hydraulic restriction layer.
- Mounding analysis may be required in accordance with Ecology Volume III Section 3.3.8.
• The Puyallup River is deemed a flow control exempt water body. The project will be required to meet the LID performance standard or List #3
• Include applicable flow charts per the Ecology Manual
• A survey prepared by a registered surveyor, showing the following is necessary for projects exceeding 2,000SF or more of new plus replace hard surfaces as defined by the 2019 Ecology Manual:
o Existing public and private development, including utility infrastructure on and adjacent to the site if publicly available
o Major hydrologic features with a streams, wetland, and water body survey and classification report showing wetland and buffer boundaries consistent with the requirements of the jurisdiction
o Minor hydrologic features, including seeps, springs, closed depression areas, drainage swales.
• Contours requirements for the survey are as follows:
o Up to 10 percent slopes, two-foot contours.
o Over 10 percent to less than 20 percent slopes, five-foot contours.
o Twenty percent or greater slopes, 10-foot contours.
o Elevations shall be at 25-foot intervals.
• Public right-of-way runoff shall be detained and treated independently from proposed private stormwater facilities. This shall be accomplished by providing separate publicly maintained storm facilities within a tract or dedicated right-of-way; enlarging the private facilities to account for bypass runoff; or other methods as approved by the City Engineer. [PMC 21.10.190(3)]
• The applicant is responsible for submitting a preliminary stormwater management site plan which meets the design requirements provided by PMC Section 21.10 and Ecology Manual Volume I, Section 2.5.1. The preliminary stormwater site plan (PSSP) shall be submitted prior to Preliminary Site Plan approval to ensure that adequate stormwater facilities are anticipated prior to development of the individual lot(s). The preliminary stormwater site plan shall reasonably estimate the quantity of roof and driveway stormwater runoff and the application of On-site Stormwater Management BMPs for the proposed development.
• A Construction Stormwater General Permit shall be obtained from the Department of Ecology if any land disturbing activities such as clearing, grading, excavating and/or demolition will disturb one or more acres of land, or are part of larger common plan of development or sale that will ultimately disturb one or more acres of land. The link below may be used to obtain information to apply for this permit:
http://www.ecy.wa.gov/programs/wq/stormwater/construction/
Stormwater Retention/Detention Facilities:
• Any above-ground stormwater facility shall be screened in accordance with planning requirements.
• Stormwater R/D facilities shall be a minimum of 20-feet from any public right-of-way, tract, vegetative buffer, and/or property line measured from the toe of the exterior slope/embankment of the facility. [PMC 21.10 & DOE Manual, Vol. V, Pg 10-39 and Pg 10-9]
• A minimum of 5-feet clearance shall be provided from the toe of the exterior slope/embankment to any tract, property line, fence, or any required vegetative buffer. [PMC 21.10 & CS 206]
|
|
Other/Miscellaneous
FEES
• Water and sewer connection fees and systems development charges are due at the time of building permit issuance and do not vest until time of permit issuance. Fees are increased annually on February 1st. To obtain credit towards water and sewer System Development Fees for existing facilities, the applicant shall provide the City evidence of the existing plumbing fixtures prior to demolition or removal. A written breakdown of the removed fixture types, quantities, and associated fixture units shall accompany the building permit application and be subject to review and approval by the City. [PMC 14.02.040, 14.10.030, PMC 14.02.040]
• Stormwater system development fees are due at the time of civil permit issuance for commercial projects and at the time of building permit issuance for single family or duplex developments and do not vest until time of permit issuance. Fees are increased annually on February 1st. The City will assess the amount of existing credits applied to the project based on how many credits the property is currently being billed for. [PMC 14.26.070]
Water
• A water system development charge (SDC) will be assessed for each new single-family residence and is due at the time of building permit issuance for the individual lot(s). The current amount of the SDC as of this writing is $5,218.00. [PMC 14.02.040, 14.10.030]
Sewer
• A sanitary sewer system development charge (SDC) will be assessed for each new single-family residence and is due at the time of building permit issuance for the individual lot(s). The current amount of the SDC as of this writing is $6,344.00 [PMC 14.10.010, 14.10.030]
Stormwater
• A Stormwater Systems Development Charge (SDC) will be assessed for each new single-family residence. The current SDC as of this writing is $4,013.00 per unit.
• A Stormwater Systems Development fee will be assessed for each new equivalent service unit (ESU) in accordance with PMC Chapter 14.26. Each ESU is equal to 2,800 square feet of ‘hard’ surface. The current SDC as of this writing is $4,013.00 per ESU.
|
|
|
Engineering Traffic Review
|
Comments
|
06/08/2023
|
06/06/2023
|
|
|
|
Other/Miscellaneous
Traffic scoping worksheet will be required. The City policy requires the project trips to be estimated using the Institute of Transportation Engineers’ (ITE) Trip Generation, 11th Edition. In general, trip generation regression equations shall be used when the R2 value is 0.70 or greater. The project trips shall be rounded to the nearest tenth.
Once the traffic scoping worksheet is reviewed, a written response would be sent to the applicant’s traffic engineer outlining the scope of the project’s Traffic Access and Impact Study
The city has adopted a City-Wide Traffic Impact Fee. The project’s proportionate share to this fee program would be determined when the traffic scoping worksheet has been submitted. The $4,500 traffic impact fee per PM peak hour trip shall be paid prior to building permit issuance.
Park impact fee was established by Ordinance 3142 dated July 3, 2017 and shall be charged per new dwelling unit based on its size:
Park Impact Fee (Per residential dwelling Unit):
Less than 500 sqft $1,560.05
500 - 999 sqft $2,313.53
1,000 – 1,999 sqft $3,291.31
2,000 sqft or more $4,017.30
Per Puyallup Municipal Code Section 11.08.135, the applicant/owner would be expected to construct half-street improvements including curb, gutter, planter strip, sidewalk, roadway base, pavement, and street lighting. The extent of paving would be determined based on current condition. Any existing improvements which are damaged now or during construction, or which do not meet current City Standards, shall be replaced.
Access for this development must utilize proposed internal commercial driveways access
-Access road tract is over 400ft long. Current City standards allow a maximum 200ft tract for 3-4 dwelling units.
-Additional vehicle trips not allowed for existing easement/tract (City standard driveway spacing not met)
22ft minimum driveway length to avoid impacting internal access/pedestrian paths.
AutoTurn analysis required for the largest anticipated design vehicle.
|
|
|
Fire Review
|
Comments
|
06/08/2023
|
06/06/2023
|
|
|
|
Other/Miscellaneous
• Provide full site dimensions for layout. Not enough details for a full review.
• Provide Riser rooms, F.D.C, and P.I.V locations to determine code compliance.
• Fire sprinkler system per NFPA 13 is required.
• Fire Hydrants shall be at least 50’ from the structure and the FDC supporting the fire sprinkler system shall be no closer than 10’ and no greater than 15’ from the hydrant.
• Provide Fire Hydrant locations, Fire Hydrants are required to reach the building within 400’.
• The fire access road (lane) shall be a minimum of 24’, 26’ in front of hydrants and 26’ if the building is over 30’ in height. An aerial fire apparatus access road may be required.
• Fire access road shall be no greater than 150’ from the furthest point of the structure per PMC 16.04.025 (4) 503.1.1.
• Fire lane striping and No Parking signs will be addressed at Civils.
• Auto-turn or equivalent program required to demonstrate code compliance.
• Maximum road grade shell be 10%
• Storm vaults in the fire lane are required to be fire apparatus rated to 75,000lbs.
• With the access being moved, a new site plan will be required for full review.
|
|
|
External Agency Review
|
No Comments
|
06/08/2023
|
05/31/2023
|
|
|
|
|