| Review Type |
Outcome |
Est. Completion Date |
Completed |
|
Building Review
|
Approved
|
03/30/2026
|
03/13/2026
|
|
|
|
|
Engineering Traffic Review
|
Approved
|
08/29/2025
|
08/21/2025
|
|
|
|
|
Building Review
|
Approved
|
08/29/2025
|
08/20/2025
|
|
|
|
|
|
See Document Markup
Verify whether the two type "1" windows near the door will need to be safety glazed. They appear to be within 24" of the vertical edge of the door in a closed position.
|
|
|
See Document Markup
Please revise the plumbing plans to conform to the 2021 editions of the Washington State Codes.
|
|
|
See Document Markup
Note #2 references the residential edition of the 2021 WSEC, which does not apply to this project. Please revise this note to conform to the commercial edition of the 2021 Washington State Energy Code.
|
|
|
See Document Markup
Please provide the (plan view) vertical dimensions for the T-shape turn arounds.
|
|
|
See Document Markup
This note has been cut off. It also references product data on this sheet; however, the correct sheet appears to be sheet A1.1
|
|
|
See Document Markup
Sheet S4.4 was not included in the plan set. Please confirm if this note is meant to reference detail 1 on sheet S4.3.
|
|
|
See Document Markup
Please correct the code edition to 2021.
|
|
Engineering Review
|
Approved
|
08/29/2025
|
08/19/2025
|
|
|
|
|
Fire Review
|
Approved
|
08/29/2025
|
08/18/2025
|
|
|
|
|
Design Review
|
Approved
|
08/29/2025
|
08/18/2025
|
|
|
|
|
Planning Review
|
Approved
|
08/29/2025
|
08/18/2025
|
|
|
|
|
Engineering Review
|
Approved
|
08/05/2025
|
08/01/2025
|
|
|
|
|
|
See Document Markup
Label the 1" water service and 1" RBPA backflow protection device installed under civil construction permit PRCCP20230970. [SITE PLAN, sheet AS1.0]
|
|
|
See Document Markup
Grease interceptor callout arrow is misplaced. Grease interceptor is faint box connected to the sanitary sewer line. Adjust the callout arrow accordingly and specify in the callout note that the gravity grease interceptor was installed under civil construction permit PRCCP20230970. [SITE PLAN, sheet AS1.0]
|
|
|
See Document Markup
On civil construction permit PRCCP20230970, a trash enclosure was depicted at the location of the sanitary sewer catch basin. Either depict the location of the trash enclosure and provide construction plans for the design that meet City standards or provide commentary on how the sanitary sewer line for the trash enclosure will be removed so as to avoid conveying stormwater to the open/uncovered sanitary sewer catch basin. [SITE PLAN, sheet AS1.0]
|
|
|
See Document Markup
The proposed building shall not be constructed above the stormwater mains constructed under civil construction permit PRCCP20230970. Either revise the utility overlay to match the civil plans or revise the building footprint to avoid conflicts with the storm mains. [SITE PLAN, sheet AS1.0]
|
|
|
See Document Markup
On the site plan, depict and label the property owners, parcel number(s), and site address(es) as assigned under PLBDJ20240103 or the jurisdiction having authority. [SITE PLAN, sheet AS1.0]
|
|
|
See Document Markup
Label Lot 3. [SITE PLAN, sheet AS1.0]
|
|
Design Review
|
Approved
|
08/05/2025
|
07/31/2025
|
|
|
|
|
Planning Review
|
Approved
|
08/05/2025
|
07/31/2025
|
|
|
|
|
Engineering Traffic Review
|
Approved
|
08/05/2025
|
07/30/2025
|
|
|
|
|
Building Review
|
Failed
|
08/05/2025
|
07/30/2025
|
|
|
|
|
|
See Document Markup
Verify whether the two type "1" windows near the door will need to be safety glazed. They appear to be within 24" of the vertical edge of the door in a closed position.
|
|
|
See Document Markup
Please revise the plumbing plans to conform to the 2021 editions of the Washington State Codes.
|
|
|
See Document Markup
Note #2 references the residential edition of the 2021 WSEC, which does not apply to this project. Please revise this note to conform to the commercial edition of the 2021 Washington State Energy Code.
|
|
|
See Document Markup
Please correct the code edition to 2021.
|
|
|
See Document Markup
Please provide the (plan view) vertical dimensions for the T-shape turn arounds.
|
|
|
See Document Markup
This note has been cut off. It also references product data on this sheet; however, the correct sheet appears to be sheet A1.1
|
|
|
See Document Markup
Sheet S4.4 was not included in the plan set. Please confirm if this note is meant to reference detail 1 on sheet S4.3.
|
|
Fire Review
|
Approved
|
08/05/2025
|
07/21/2025
|
|
|
|
|
Design Review
|
VOID
|
03/28/2025
|
03/27/2025
|
|
|
|
|
Engineering Review
|
Failed
|
03/28/2025
|
03/27/2025
|
|
|
|
|
|
See Document Markup
Label the 1" water service and 1" RBPA backflow protection device installed under civil construction permit PRCCP20230970. [SITE PLAN, sheet AS1.0]
|
|
|
See Document Markup
Grease interceptor callout arrow is misplaced. Grease interceptor is faint box connected to the sanitary sewer line. Adjust the callout arrow accordingly and specify in the callout note that the gravity grease interceptor was installed under civil construction permit PRCCP20230970. [SITE PLAN, sheet AS1.0]
|
|
|
See Document Markup
On civil construction permit PRCCP20230970, a trash enclosure was depicted at the location of the sanitary sewer catch basin. Either depict the location of the trash enclosure and provide construction plans for the design that meet City standards or provide commentary on how the sanitary sewer line for the trash enclosure will be removed so as to avoid conveying stormwater to the open/uncovered sanitary sewer catch basin. [SITE PLAN, sheet AS1.0]
|
|
|
See Document Markup
The proposed building shall not be constructed above the stormwater mains constructed under civil construction permit PRCCP20230970. Either revise the utility overlay to match the civil plans or revise the building footprint to avoid conflicts with the storm mains. [SITE PLAN, sheet AS1.0]
|
|
|
See Document Markup
On the site plan, depict and label the property owners, parcel number(s), and site address(es) as assigned under PLBDJ20240103 or the jurisdiction having authority. [SITE PLAN, sheet AS1.0]
|
|
|
See Document Markup
Label Lot 3. [SITE PLAN, sheet AS1.0]
|
|
Engineering Traffic Review
|
Failed
|
03/28/2025
|
03/25/2025
|
|
|
|
|
|
Other/Miscellaneous
Commercial bldg square footage has been increased from original proposal. Is the new configuration proposing a 2000/3000 sqft split?
Describe the expected tenant for each suite and provide ITE Land Use Code if known.
|
|
Fire Review
|
Approved
|
03/28/2025
|
03/24/2025
|
|
|
|
|
Building Review
|
Failed
|
03/28/2025
|
03/20/2025
|
|
|
|
|
|
See Document Markup
See sheet AG1.1 for EV Charging requirements. [Reference the marked-up document: SITE PLAN, sheet AS1.0]
|
|
|
See Document Markup
This project doesn't fall within the scope of the International Residential Code. [Reference the marked-up document: CONSTRUCTION PLAN SET, sheet AG1.0]
|
|
|
See Document Markup
Trusses cannot be deferred for this scope of work. [Reference the marked-up document: CONSTRUCTION PLAN SET, sheet AG1.0]
|
|
|
See Document Markup
Please verify that the correct number of EV charging infrastructure is provided. This note says 4 ready and 4 future are provided, but no mention of EV Charging Stations is included. The site plan only shows six (6) parking spaces noted as "EV" or "Future EV". [Reference the marked-up document: CONSTRUCTION PLAN SET, sheet AG1.1]
|
|
|
See Document Markup
Per the 2021 Washington State Building Code, section 429.4, additional EV charging infrastructure is required at the accessible parking spaces:
"Ten percent of the accessible parking spaces, rounded to the next whole number, shall be EV Charging Stations. Additional 10 percent of the accessible parking spaces, rounded to the next whole number, shall be EV Ready. Not fewer than one for each type of EV charging system shall be accessible.
The electric vehicle charging infrastructure may also serve adjacent parking spaces not designated as accessible parking. A maximum of 10 percent of the accessible parking spaces, rounded to the next whole number, are allowed to be included in the total number of electric vehicle parking spaces required under Section 429.2."
[Reference the marked-up document: CONSTRUCTION PLAN SET, sheet AG1.1]
|
|
|
See Document Markup
Please confirm if this area will be Mercantile (Occupancy Group M) or Assembly (Occupancy Group A2) as noted in the Building Summary on this sheet. [Reference the marked-up document: CONSTRUCTION PLAN SET, sheet AG1.1]
|
|
|
See Document Markup
Please correct the wording on this note. Tenant #1 Gross Area. [Reference the marked-up document: CONSTRUCTION PLAN SET, sheet A1.0]
|
|
|
See Document Markup
Please revise the accessibility notes to conform to the 2017 edition of the Washington State Accessibility Code (ICC A117.1-2017). [Reference the marked-up document: CONSTRUCTION PLAN SET, sheet A4.0]
|
|
|
See Document Markup
Manufactured joists, beams, and trusses cannot be deferred. [Reference the marked-up document: CONSTRUCTION PLAN SET, sheet S1.0]
|
|
|
See Document Markup
Interior S.O.G. specifications are under Note #2. [Reference the marked-up document: CONSTRUCTION PLAN SET, sheet S3.1]
|
|
|
See Document Markup
Please provide the truss manufacturer's roof truss calculations (stamped and signed) and layout. Truss engineer to include the required structural elements noted on this sheet. Truss engineering and layout must be reviewed and approved by the structural engineer of record prior to permit issuance. [Reference the marked-up document: CONSTRUCTION PLAN SET, sheet S3.2]
|
|
|
See Document Markup
Please revise the plumbing plans to conform to the 2021 editions of the Washington State Codes. [Reference the marked-up document: CONSTRUCTION PLAN SET, sheet P0.00]
|
|
|
See Document Markup
Note #2 references the residential edition of the 2021 WSEC, which does not apply to this project. Please revise this note to conform to the commercial edition of the 2021 Washington State Energy Code. [Reference the marked-up document: CONSTRUCTION PLAN SET, sheet P0.01]
|
|
|
See Document Markup
Please designate the wall types on the floor plan. [Reference the marked-up document: CONSTRUCTION PLAN SET, sheet A1.0]
|
|
|
See Document Markup
Verify placement of downspout and scupper notes, typical. [Reference the marked-up document: CONSTRUCTION PLAN SET, sheet A1.1]
|
|
|
See Document Markup
The placement of the rooftop units differ between this sheet and the mechanical sheets (M2.1 and P2.02). [Reference the marked-up document: CONSTRUCTION PLAN SET, sheet A1.1]
|
|
|
See Document Markup
Please correct the cut-off text. [Reference the marked-up document: CONSTRUCTION PLAN SET, sheet A2.0]
|
|
|
See Document Markup
Please correct the cut-off text. [Reference the marked-up document: CONSTRUCTION PLAN SET, sheet A2.1]
|
|
|
See Document Markup
Detail 1 was not provided on sheet A6.0. [Reference the marked-up document: CONSTRUCTION PLAN SET, sheet A3.0]
|
|
|
See Document Markup
Detail 1 was not provided on sheet A6.0. Ensure the parapet meets minimum guard requirements per section 304.11 of the 2021 Washington State Mechanical Code, or fall protection is provided. [Reference the marked-up document: CONSTRUCTION PLAN SET, sheet A3.2]
|
|
|
See Document Markup
Ensure the parapet meets minimum guard requirements per section 304.11 of the 2021 Washington State Mechanical Code, or fall protection is provided, typical. [Reference the marked-up document: CONSTRUCTION PLAN SET, sheet A3.3]
|
|
|
See Document Markup
Please review downspout and scupper locations, typical. [Reference the marked-up document: CONSTRUCTION PLAN SET, sheet P2.02]
|
|
|
See Document Markup
Please locate and specify the secondary roof drainage per the 2021 Washington State Plumbing Code, section 1101.12.2. [Reference the marked-up document: CONSTRUCTION PLAN SET, sheet P2.02]
|
|
|
See Document Markup
Signage per detail #3. [Reference the marked-up document: SITE PLAN, sheet AS1.0]
|
|
|
See Document Markup
Please clarify how access to the roof, and mechanical units, provided. Please locate the roof access hatch or ladder on the plan. [Reference the marked-up document: CONSTRUCTION PLAN SET, sheet A1.1]
|
|
|
See Document Markup
Please designate the windows adjacent to the door as requiring safety glazing. [Reference the marked-up document: CONSTRUCTION PLAN SET, sheet A1.0]
|
|
Planning Review
|
Failed
|
03/28/2025
|
02/25/2025
|
|
|
|
|
|
Miscellaneous Planning Correction
See comments under Design Review.
|
|
Design Review
|
Failed
|
03/28/2025
|
02/25/2025
|
|
|
|
|
|
Miscellaneous Planning Correction
Review PMC 20.26.300. Please confirm on the drawings the building meets the horizontal and roofline modulation standards and building wall articulation. Please provide calcs that show: "No less than 60 percent of the surface area of any street-facing wall located in the pedestrian view plane, defined as the horizontal area between two and eight feet above the exterior grade, shall consist of windows and/or transparent doorways." Please detail what pedestrian oriented features will be in the plaza areas (north and west elevations) (see .300 (3)(b)(i)), Consider moving the bike racks to the west elevation plaza area, adjacent to the shared use path on Shaw Road.
|