CITY OF PUYALLUP PERMITTING PORTAL

Permit Application Status

PRCTI20221714


In order to request inspections, you need to be signed in.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRCTI20221714
Commercial - Tenant Improvement/Remodel
Closed
COMMUNITY HEALTH CARE
Alteration/Remodel
Remodel office space on the ground floor of an existing parking structure - COMMUNITY HEALTHCARE * REV (1) - 11/20/2023 - REVISE SIDE SEWER CONNECTION LOCATION * REV (2) - 2.22.2024 - IDENTIFY REVISION TO APPLICABLE BUILDING CODE COMPLIANCE TO 2018 INTERNATIONAL EXISTING BUILDING CODE, WITH RESPECTIVE CODE REFERENCES. *REVISION (3) - 11/1/2024 - PARTITIONS IN STORAGE AREA, ADA REQUIREMENTS FOR SINGLE-USER RESTROOMS, REVISE PARTITION FOR NEW WALLS IN STORAGE AREA, REVISE SIGNAGE FOR NON ADA RESTROMM SIGNS.
11/02/2022
05/24/2023
05/24/2025
01/23/2025

Locations

Reviews

Documents Returned For Corrections

Date Returned Name
11/15/2024 CONSTRUCTION PLAN SET - REV (3) (Stamped)
Review Type Outcome Est. Completion Date Completed
Building Review Approved 11/18/2024 11/15/2024
Building Review Approved 03/07/2024 03/06/2024
Engineering Review Approved 01/02/2024 01/02/2024
Building Review Approved 01/02/2024 12/29/2023
Building Review Failed 12/06/2023 12/04/2023
Engineering Review Failed 12/06/2023 11/29/2023
Engineering Traffic Review Approved 04/13/2023 04/24/2023
Planning Review Approved 04/13/2023 04/11/2023
Building Review Approved 04/13/2023 04/06/2023
Fire Review Approved 04/13/2023 04/06/2023
Engineering Review Approved 04/13/2023 04/03/2023
Engineering Traffic Review Failed 01/26/2023 03/16/2023
Planning Review Approved 01/26/2023 01/25/2023
Fire Review Approved 01/26/2023 01/24/2023
Building Review Approved 01/26/2023 01/18/2023
Engineering Review Approved 01/26/2023 01/17/2023
Engineering Traffic Review Failed 01/06/2023 12/27/2022
Building Review Failed 11/23/2022 11/30/2022
Planning Review Approved 11/23/2022 11/23/2022
Fire Review Approved 11/23/2022 11/21/2022
Engineering Review Failed 11/23/2022 11/15/2022

Fees

Paid Fees Amount Paid Owing Date Paid
Fire Review Fee (Commercial Building) $265.00 $265.00 Paid 04/27/2023
Air Handling Unit (Up to 10,000 cfm) Fee $98.70 $98.70 Paid 04/27/2023
Boilers & Compressors/Heat Pump (100,001 - 500,000 BTU or 3 - 15 HP) Fee $35.95 $35.95 Paid 04/27/2023
Mechanical Duct Work Fee $24.00 $24.00 Paid 04/27/2023
Building Permit Fee $7,054.15 $7,054.15 Paid 04/27/2023
Mechanical Permit Fee $40.00 $40.00 Paid 04/27/2023
Drinking Fountain, Water Cooler, Ice Machine Fee $40.25 $40.25 Paid 04/27/2023
Plumbing Permit Fee $40.00 $40.00 Paid 04/27/2023
Sump, Sewage, or Ejector Pumps Fee $156.00 $156.00 Paid 04/27/2023
Water Heater Fee $13.00 $13.00 Paid 04/27/2023
Building Plan Review Fee $4,585.20 $4,585.20 Paid 11/03/2022
Mechanical Plan Review Fee $129.12 $129.12 Paid 11/03/2022
Plumbing Plan Review Fee $162.01 $162.01 Paid 11/03/2022
WA State Building Code Council Fee (Commercial) $25.00 $25.00 Paid 04/27/2023
Sewer System Development ChargeFee - Tenant Improvment/Addition $17,363.72 $17,363.72 Paid 04/27/2023
Water System Development ChargeFee - Tenant Improvment/Addition $11,131.38 $11,131.38 Paid 04/27/2023
Resubmittal Fee $130.00 $130.00 Paid 01/11/2023
Resubmittal Fee $130.00 $130.00 Paid 03/30/2023
Traffic Impact Fee (Commercial) $59,850.00 $59,850.00 Paid 04/27/2023
Resubmittal Fee $180.00 $180.00 Paid 11/20/2023
Resubmittal Fee $180.00 $180.00 Paid 12/20/2023
Resubmittal Fee $180.00 $180.00 Paid 02/22/2024
Resubmittal Fee $180.00 $180.00 Paid 11/01/2024
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


Permit(s) will not be issued until outstanding fees have been paid in full. Fee details shown above only include currently payable fees, there might be addtional fees to be paid before issuance.

$0.00

Inspections

Inspection Outcome Requested Scheduled Date Inspected
Frame Inspection Not Ready 12/1/2023 12/1/2023 12/01/2023
Monty Johnson ((253) 770-3326)
Corrections:


Other/Miscellaneous
Carried Forward
12/01/2023
INSP FOR GARAGE TALKED ABOUT CALLING IN CORRECT PERMITS AND HAVING AREAS COMPLETE FOR INSPECTION

Combination Frame And Rough In Inspection Not Ready 12/4/2023 12/4/2023 12/04/2023
Monty Johnson ((253) 770-3326)
Corrections:


Other/Miscellaneous
Carried Forward
12/04/2023
cancelled by contractor

Frame Inspection Partial Pass 12/7/2023 12/7/2023 12/07/2023
Monty Johnson ((253) 770-3326)
Corrections:


Other/Miscellaneous
Carried Forward
12/07/2023
1: Z GIRTS ON LID LOWER LEVEL OK

Energy (Insulation) Inspection Partial Pass 12/20/2023 12/20/2023 12/20/2023
Shannon King ((253) 840-6684)
Wallboard / Drywall Inspection Partial Pass 12/28/2023 12/28/2023 12/28/2023
Monty Johnson ((253) 770-3326)
Corrections:


Other/Miscellaneous
Carried Forward
12/28/2023
electrical room drywall ok.

Wallboard / Drywall Inspection Partial Pass 1/3/2024 1/3/2024 01/03/2024
Monty Johnson ((253) 770-3326)
Corrections:


Other/Miscellaneous
Carried Forward
01/03/2024
rock on lid ok

Plumbing Below Slab Inspection Not Ready 1/10/2024 1/10/2024 01/10/2024
Monty Johnson ((253) 770-3326)
Corrections:


Other/Miscellaneous
Carried Forward
01/10/2024
below floor dwv test called in on wrong permit

Frame Inspection Not Ready 1/11/2024 1/11/2024 01/11/2024
Monty Johnson ((253) 770-3326)
Corrections:


Other/Miscellaneous
Carried Forward
01/11/2024
provide architects top and bottom track attachment details

Frame Inspection Partial Pass 1/18/2024 1/18/2024 01/18/2024
Monty Johnson ((253) 770-3326)
Corrections:


Other/Miscellaneous
Carried Forward
01/18/2024
1:ok to rock top track down 1ft, (head of wall only)

Mechanical Rough In Inspection Partial Pass 2/9/2024 2/9/2024 02/09/2024
Kevin Spruell ((253) 841-5590)
Corrections:


Other/Miscellaneous
Carried Forward
02/09/2024
1.rooms 113,112,111,110,109,108,107 approved for duct insulation

Comment Building Div Inspection Passed w/ Conditions 2/13/2024 02/13/2024
Monty Johnson ((253) 770-3326)
Plumbing Rough In Inspection Partial Pass 3/5/2024 3/5/2024 03/05/2024
Monty Johnson ((253) 770-3326)
Corrections:


Other/Miscellaneous
Carried Forward
03/05/2024
dwv, condensate and supply 1st level ok

Frame Inspection Partial Pass 3/11/2024 3/11/2024 03/11/2024
Monty Johnson ((253) 770-3326)
Corrections:


Other/Miscellaneous
Carried Forward
03/11/2024
1: frame ok minus north and south ext walls and fire walls

Wallboard / Drywall Inspection Not Ready 3/13/2024 3/13/2024 03/13/2024
Kevin Spruell ((253) 841-5590)
Corrections:


Other/Miscellaneous
Carried Forward
03/13/2024
1. cancelled on site by contractor

Wallboard / Drywall Inspection Partial Pass 3/14/2024 3/14/2024 03/14/2024
Kevin Spruell ((253) 841-5590)
Corrections:


Other/Miscellaneous
Resolved
03/14/2024
1. cancelled on site by contractor

Other/Miscellaneous
Carried Forward
03/14/2024
1. north exterior drywall nailing approved (exterior of wall)

Plumbing Below Slab Inspection Not Ready 3/18/2024 3/18/2024 03/18/2024
Kevin Spruell ((253) 841-5590)
Corrections:


Other/Miscellaneous
Carried Forward
03/18/2024
1. this was for the water service coming in to the building needs be done by engineering

Frame Inspection Not Ready 3/19/2024 3/19/2024 03/19/2024
Kevin Spruell ((253) 841-5590)
Corrections:


Other/Miscellaneous
Carried Forward
03/19/2024
ROOM 107 PHARMACY WAITING ROOM 1. complete insulation that is missing above ceiling at exterior wall (west) 2. complete framing at ceiling as discussed with contractor 3. provide cover approval for fire as discussed with contractor at time of next inspection 4.not ready

Energy (Insulation) Inspection Partial Pass 3/21/2024 3/21/2024 03/21/2024
Kevin Spruell ((253) 841-5590)
Corrections:


Other/Miscellaneous
Carried Forward
03/21/2024
1.exterior wall at east at hard lids pharmacy room 107 approved

Mechanical Rough In Inspection Partial Pass 3/21/2024 3/21/2024 03/21/2024
Kevin Spruell ((253) 841-5590)
Corrections:


Other/Miscellaneous
Resolved
03/21/2024
1.rooms 113,112,111,110,109,108,107 approved for duct insulation

Other/Miscellaneous
Carried Forward
03/21/2024
1.MECH approved at hard lids room 107 pharmacy waiting

Frame Inspection Partial Pass 3/21/2024 3/21/2024 03/21/2024
Kevin Spruell ((253) 841-5590)
Corrections:


Other/Miscellaneous
Resolved
03/21/2024
ROOM 107 PHARMACY WAITING ROOM 1. complete insulation that is missing above ceiling at exterior wall (west) 2. complete framing at ceiling as discussed with contractor 3. provide cover approval for fire as discussed with contractor at time of next inspection 4.not ready

Other/Miscellaneous
Carried Forward
03/21/2024
1.pharmacy waiting room 107 hard lids approved 2.room 109 south bathroom hard lid approved 3. north, east ,southeast exterior walls and small section in corridor remove insulation from walls clean construction debri from bottom plates and complete rigid insulation per city approved plans

Wallboard / Drywall Inspection Partial Pass 3/22/2024 3/22/2024 03/22/2024
Kevin Spruell ((253) 841-5590)
Corrections:


Other/Miscellaneous
Resolved
03/22/2024
1. north exterior drywall nailing approved (exterior of wall)

Other/Miscellaneous
Carried Forward
03/22/2024
1. no exterior walls 2. interior walls drywall nailing progression inspection approved

Energy (Insulation) Inspection Partial Pass 3/27/2024 3/27/2024 03/28/2024
Kevin Spruell ((253) 841-5590)
Corrections:


Other/Miscellaneous
Resolved
03/28/2024
1.exterior wall at east at hard lids pharmacy room 107 approved

Other/Miscellaneous
Carried Forward
03/28/2024
1. rigid insulation at north ,east, exterior walls and small wall in corridor approved

Frame Inspection Partial Pass 3/27/2024 3/27/2024 03/28/2024
Kevin Spruell ((253) 841-5590)
Corrections:


Other/Miscellaneous
Resolved
03/28/2024
1.pharmacy waiting room 107 hard lids approved 2.room 109 south bathroom hard lid approved 3. north, east ,southeast exterior walls and small section in corridor remove insulation from walls clean construction debri from bottom plates and complete rigid insulation per city approved plans

Other/Miscellaneous
Carried Forward
03/28/2024
1.north, east exteriors and small wall in corridor framing approved 2. ok to insulate

Energy (Insulation) Inspection Partial Pass 3/29/2024 3/29/2024 03/29/2024
Monty Johnson ((253) 770-3326)
Corrections:


Other/Miscellaneous
Carried Forward
03/29/2024
1. rigid insulation at north ,east, exterior walls and small wall in corridor approved

Other/Miscellaneous
Carried Forward
03/29/2024
insulation batts in ext and corridor walls ok

Energy (Insulation) Inspection Partial Pass 4/2/2024 4/2/2024 04/02/2024
Kevin Spruell ((253) 841-5590)
Corrections:


Other/Miscellaneous
Carried Forward
04/02/2024
1. exterior walls vapor barrier on north wall east wall and small wall in corridor approved

Wallboard / Drywall Inspection Partial Pass 4/8/2024 4/8/2024 04/08/2024
Kevin Spruell ((253) 841-5590)
Corrections:


Other/Miscellaneous
Resolved
04/08/2024
1. no exterior walls 2. interior walls drywall nailing progression inspection approved

Other/Miscellaneous
Carried Forward
04/08/2024
1.exterior walls north, east, and small wall in corridor approved

Gas Test Inspection Passed 4/25/2024 4/25/2024 04/25/2024
Kevin Spruell ((253) 841-5590)
Corrections:


Other/Miscellaneous
Outstanding
04/25/2024
1. gas test approved at 60 PSI

Plumbing Rough In Inspection Partial Pass 5/3/2024 5/3/2024 05/04/2024
Kevin Spruell ((253) 841-5590)
Corrections:


Other/Miscellaneous
Carried Forward
05/04/2024
1. final section of supply side of plumbing tested at 100 PSI approved

Wallboard / Drywall Inspection Partial Pass 5/22/2024 5/22/2024 05/23/2024
Kevin Spruell ((253) 841-5590)
Corrections:


Other/Miscellaneous
Carried Forward
05/23/2024
1.exterior walls north, east, and small wall in corridor approved

Other/Miscellaneous
Carried Forward
05/23/2024
inspection date 5/22/2024 1.densglass repair southside of exterior building next to garage opening approved 2.densglass repair west side of building around fire sprinkler riser door approved 3. densglass repair around elevator pent house on roof approved pending architects clarification on rated wall assembly

Wallboard / Drywall Inspection Partial Pass 6/10/2024 6/10/2024 06/11/2024
Kevin Spruell ((253) 841-5590)
Corrections:


Other/Miscellaneous
Carried Forward
06/11/2024
1.exterior walls north, east, and small wall in corridor approved

Other/Miscellaneous
Carried Forward
06/11/2024
inspection date 5/22/2024 1.densglass repair southside of exterior building next to garage opening approved 2.densglass repair west side of building around fire sprinkler riser door approved 3. densglass repair around elevator pent house on roof approved pending architects clarification on rated wall assembly

Other/Miscellaneous
Carried Forward
06/11/2024
inspection date 6/10/2024 1. west storage 1st layer approved

Wallboard / Drywall Inspection Partial Pass 6/17/2024 6/17/2024 06/17/2024
Kevin Spruell ((253) 841-5590)
Corrections:


Other/Miscellaneous
Carried Forward
06/17/2024
1.exterior walls north, east, and small wall in corridor approved

Other/Miscellaneous
Carried Forward
06/17/2024
inspection date 5/22/2024 1.densglass repair southside of exterior building next to garage opening approved 2.densglass repair west side of building around fire sprinkler riser door approved 3. densglass repair around elevator pent house on roof approved pending architects clarification on rated wall assembly

Other/Miscellaneous
Carried Forward
06/17/2024
inspection date 6/10/2024 1. west storage 1st layer approved

Other/Miscellaneous
Carried Forward
06/17/2024
date of inspection 6/17/2024 1.2nd layer at storage room 133 approved

Mechanical Rough In Inspection Not Ready 6/21/2024 6/21/2024 06/21/2024
Shannon King ((253) 840-6684)
Corrections:


Other/Miscellaneous
Carried Forward
06/21/2024
1.MECH approved at hard lids room 107 pharmacy waiting

Other/Miscellaneous
Carried Forward
06/21/2024
cancel per contractor.

Mechanical Rough In Inspection Not Ready 6/25/2024 6/25/2024 06/25/2024
Kevin Spruell ((253) 841-5590)
Corrections:


Other/Miscellaneous
Carried Forward
06/25/2024
1.MECH approved at hard lids room 107 pharmacy waiting

Other/Miscellaneous
Resolved
06/25/2024
cancel per contractor.

Other/Miscellaneous
Carried Forward
06/25/2024
date of inspection 6/25/2024 1. complete positive attachment of diffuser's as discussed with contractor

Shear Wall Inspection Not Ready 6/28/2024 6/28/2024 06/28/2024
Kevin Spruell ((253) 841-5590)
Corrections:


Other/Miscellaneous
Carried Forward
06/28/2024
1.called in in error

Refrigeration Line Test Inspection Not Ready 6/28/2024 6/28/2024 06/28/2024
Kevin Spruell ((253) 841-5590)
Corrections:


Other/Miscellaneous
Carried Forward
06/28/2024
1. cancelled on site by contractor

Mechanical Rough In Inspection Partial Pass 6/28/2024 6/28/2024 06/28/2024
Kevin Spruell ((253) 841-5590)
Corrections:


Other/Miscellaneous
Carried Forward
06/28/2024
1.MECH approved at hard lids room 107 pharmacy waiting

Other/Miscellaneous
Carried Forward
06/28/2024
date of inspection 6/25/2024 1. complete positive attachment of diffuser's as discussed with contractor

Other/Miscellaneous
Carried Forward
06/28/2024
date of inspection 6/28/2024 1. R/I mech in corridors and rooms to the north approved

Refrigeration Line Test Inspection Partial Pass 7/9/2024 7/9/2024 07/09/2024
Monty Johnson ((253) 770-3326)
Corrections:


Other/Miscellaneous
Carried Forward
07/09/2024
1. cancelled on site by contractor

Other/Miscellaneous
Carried Forward
07/09/2024
1:refer lines tested with one gauge at 625 psi to all head units and rtu, refer guy will explain how all connected at next insp.

Ceiling Grid/T-Bar Inspection Not Ready 7/11/2024 7/11/2024 07/11/2024
Monty Johnson ((253) 770-3326)
Corrections:


Other/Miscellaneous
Carried Forward
07/11/2024
1:pharmacy area) provide pods at 1000 sq ft 2:provide counter splays at perimeter wires over angled. 3: provide perimeter wires at max 8" from wall.

Ceiling Grid/T-Bar Inspection Passed 7/16/2024 7/16/2024 07/16/2024
Monty Johnson ((253) 770-3326)
Mechanical Final Inspection Partial Pass 8/29/2024 8/29/2024 08/29/2024
Monty Johnson ((253) 770-3326)
Corrections:


Other/Miscellaneous
Carried Forward
08/29/2024
final pending electrical and building final.

Plumbing Final Inspection Failed 10/16/2024 10/16/2024 10/16/2024
Monty Johnson ((253) 770-3326)
Corrections:


Other/Miscellaneous
Carried Forward
10/16/2024
provide open toilet seats and flush handles on correct side or city approved revision for non hc bathrooms

Mechanical Final Inspection Passed 10/16/2024 10/16/2024 10/16/2024
Monty Johnson ((253) 770-3326)
Exit Lighting Test Inspection Passed 12/19/2024 12/19/2024
David Drake ((253) 864-4171)
Fire Or Smoke Damper Inspection Passed 12/19/2024
David Drake ((253) 864-4171)
Hydrostatic Test 200Lbs 2Hrs VOID 12/19/2024
David Drake ((253) 864-4171)
Emergency Radio Test Review Inspection Passed 12/19/2024 12/19/2024 12/19/2024
David Drake ((253) 864-4171)
Fire Final Inspection Passed 12/19/2024 12/19/2024 12/19/2024
David Drake ((253) 864-4171)
Building Final Inspection Failed 12/20/2024 12/20/2024 12/20/2024
Monty Johnson ((253) 770-3326)
Corrections:


Other/Miscellaneous
Carried Forward
12/20/2024
1:provide storage only signs as discussed 2:complete fastening of osb at storage areas. 3:provide verification on 50 % of storage area to have 7ft head height 4:provide rfi changes for accessible bathrooms to non accessible from architect. 5:firecaulk penetrations in riser room 6:paint gas pipe. 7:remove all debris from roof.

Plumbing Final Inspection Passed 12/20/2024 12/20/2024 12/20/2024
Monty Johnson ((253) 770-3326)
Planning Final Inspection Passed 12/19/2024 12/23/2024
Chris Beale ((253) 841-5418)
Building Final Inspection Failed 12/26/2024 12/26/2024 12/26/2024
Monty Johnson ((253) 770-3326)
Comment Engineering Div Inspection Passed 01/06/2025
Jeff Hill ((253) 204-5633)
Cover Inspection/Thrust Blocks Inspection Passed 01/06/2025
Jeff Hill ((253) 204-5633)
Engineering Final Inspection Passed 01/06/2025
Jeff Hill ((253) 204-5633)
Building Final Inspection Passed 1/23/2025 1/23/2025 01/23/2025
Monty Johnson ((253) 770-3326)
Footing/Setback Inspection VOID 01/23/2025
Monty Johnson ((253) 770-3326)
Foundation/Rebar Inspection VOID 01/23/2025
Monty Johnson ((253) 770-3326)
Slab/Insulation Inspection VOID 01/23/2025
Monty Johnson ((253) 770-3326)
Roof Sheathing Inspection VOID 01/23/2025
Monty Johnson ((253) 770-3326)
Firewall/Firestop Inspection VOID 01/23/2025
Monty Johnson ((253) 770-3326)
Hydronic Piping Inspection VOID 01/23/2025
Monty Johnson ((253) 770-3326)
Exhaust Hood Inspection VOID 01/23/2025
Monty Johnson ((253) 770-3326)
Light Test For Grease Duct Inspection VOID 01/23/2025
Monty Johnson ((253) 770-3326)
Exhaust/Vent Fans Inspection VOID 01/23/2025
Monty Johnson ((253) 770-3326)
Medical Gas Inspection VOID 01/23/2025
Monty Johnson ((253) 770-3326)
Combination Frame And Rough In Inspection VOID 01/23/2025
Monty Johnson ((253) 770-3326)
Plumbing Below Slab Inspection VOID 01/23/2025
Monty Johnson ((253) 770-3326)
Corrections:


Other/Miscellaneous
Outstanding
03/18/2024
1. this was for the water service coming in to the building needs be done by engineering

Frame Inspection VOID 01/23/2025
Monty Johnson ((253) 770-3326)
Corrections:


Other/Miscellaneous
Outstanding
03/28/2024
1.north, east exteriors and small wall in corridor framing approved 2. ok to insulate

Energy (Insulation) Inspection VOID 01/23/2025
Monty Johnson ((253) 770-3326)
Corrections:


Other/Miscellaneous
Outstanding
04/02/2024
1. exterior walls vapor barrier on north wall east wall and small wall in corridor approved

Plumbing Rough In Inspection VOID 01/23/2025
Monty Johnson ((253) 770-3326)
Corrections:


Other/Miscellaneous
Outstanding
05/04/2024
1. final section of supply side of plumbing tested at 100 PSI approved

Wallboard / Drywall Inspection VOID 01/23/2025
Monty Johnson ((253) 770-3326)
Corrections:


Other/Miscellaneous
Outstanding
06/17/2024
1.exterior walls north, east, and small wall in corridor approved

Other/Miscellaneous
Outstanding
06/17/2024
inspection date 5/22/2024 1.densglass repair southside of exterior building next to garage opening approved 2.densglass repair west side of building around fire sprinkler riser door approved 3. densglass repair around elevator pent house on roof approved pending architects clarification on rated wall assembly

Other/Miscellaneous
Outstanding
06/17/2024
inspection date 6/10/2024 1. west storage 1st layer approved

Other/Miscellaneous
Outstanding
06/17/2024
date of inspection 6/17/2024 1.2nd layer at storage room 133 approved

Shear Wall Inspection VOID 01/23/2025
Monty Johnson ((253) 770-3326)
Corrections:


Other/Miscellaneous
Outstanding
06/28/2024
1.called in in error

Mechanical Rough In Inspection VOID 01/23/2025
Monty Johnson ((253) 770-3326)
Corrections:


Other/Miscellaneous
Outstanding
06/28/2024
1.MECH approved at hard lids room 107 pharmacy waiting

Other/Miscellaneous
Outstanding
06/28/2024
date of inspection 6/25/2024 1. complete positive attachment of diffuser's as discussed with contractor

Other/Miscellaneous
Outstanding
06/28/2024
date of inspection 6/28/2024 1. R/I mech in corridors and rooms to the north approved

Refrigeration Line Test Inspection VOID 01/23/2025
Monty Johnson ((253) 770-3326)

Conditions

Condition Status Category
Building Permit Standard Conditions Open Standard Conditions
* Final approval by the Building Official is required prior to use or occupancy.* Work shall not proceed until the inspector has approved the stages of construction.* Surface storm water shall be diverted from the building site and shall not drain onto adjacent properties.* I hereby acknowledge that I have read this Permit/Application, that the information given is correct; that I am the owner or the duly authorized agent of the owner; that plans submitted herewith are in compliance with all applicable city, county and state laws and that all construction will proceed in accordance with said laws. This permit shall expire if work is not commenced with 180 days or if the work is suspended for a period of 180 days. Permits expire two years from issuance. * By leaving the contractor information section blank, I hereby certify further that contractors (general or subcontractors) will not be hired to perform any work in association with this permit. I also certify that if I do choose to hire a contractor (general or subcontractor) I will only hire those contractors that are licensed by the State of Washington. If you are a property owner, contractor or permittee and you are paying for someone to perform the work, they must have a valid contractor registration and the person(s) installing plumbing inside a structure must meet the plumbing certification requirements. If you have any questions regarding these regulations, you may contact the Washington State Department of Labor and Industries or you can find more information on-line at: http://www.lni.wa.gov/TradesLicensing/Contractors/HireCon/default.asp
Fire Review Conditions Open Standard Conditions
• Comply with 2018 IFC and 2018 IBC • Total coverage required in the city of puyallup • L&I Final required prior to Fire Final • Exit lighting test required, contractor to provide light meter • Emergency radio test required comply with IFC section 510. Fire final approval upon completed test results • All elevator maintenance and inspections required to be updated prior to Final • Separate permits required for Fire Alarm and Fire Sprinkler • Fire Sprinkler system maintenance and inspections required to be updated prior to Final • RTU’S will be required to be tested for shut down • Smoke and Fire dampeners will be tested with Fire Alarm. Access doors are required for maintenance and visual inspection. • Fire extinguishers required per code • Fire Lane painting and stenciling required to be updated prior to Final. • A Knox box is required at the front entry on the exterior of the building if equipped with a Fire Alarm System or Fire Sprinkler System. • PIV must have a Knox lock or approved lock with an extra key provided in Knox box • Existing buildings will need to contact central pierce fire & rescue and update the key in the Knox box • All above items to be completed prior to fire final. Fire final required before building final Schedule your inspection online through the City of Puyallup online permit system. This is a request for inspection only. A date and time will be selected by Inspector depending on availability. Email prior to inspection for date and time. Fire Inspections are Monday – Thursday there will be no inspections on Fridays. David Drake 253-864-4171 ddrake@puyallupwa.gov
Frontage Improvements - New Commercial/Industrial Buildings or Expansion of Existing Buildings Resolved Prior to Issuance
Engineering Division
The building permit shall not be issued until the frontage improvement design has been approved by the City. See Civil Permit PRCCP20221725.
Side Sewer Sample Tee Resolved Prior to Issuance
Engineering Division
Prior to issuance a utility permit must be issued to install the required sewer lateral sampling tee can be inconjuction with the installation of the RPBA. See Civil Permit PRCCP20221725. LL 01/17/2023
Miscellaneous Condition Resolved Prior to Issuance
Engineering Division
Prior to issuance a utility permit must be issued to install the required RPBA can be inconjuction with the installation of the sewer sampling tee. See Civil Permit PRCCP20221725. LL 01/17/2023
Miscellaneous Condition Resolved Prior to Occupancy
Engineering Division
All work associated with the installation of the frontage improvements and the RPBA must be complete and a final approval granted. See Civil Permit PRCCP20221725. LL 11/09/2022
Engineering Commercial Standard Conditions Open Standard Conditions
Development & Permitting Services
Development Engineering standard commercial conditions: ** All work associated with the installation of the frontage improvements must be complete and a final approval granted ** ** All work associated with the installation of the sewer sampling tee must be complete and a final approval granted ** **All work associated with the installation of the RPBA must be complete and a final approval granted ** - Stormwater control of roof downspouts required. Attached to the site plan is a typical infiltration system you may choose to follow. - The builder/owner shall be responsible for keeping the existing right-of-way free of debris and dirt. Any violation of PMC chapter 21.14 pertaining to clearing, filling and grading, erosion and sediment control, and storm water discharges shall be prosecuted to the fullest extent of the law.- Any addition/expansion to the footprint of the building including decks and porches not originally shown on the approved set of plans must obtain proper permits prior to construction. - The applicant is responsible to call the utility notification center at 1-800-424-5555 before beginning any excavation. Call before you dig, it's the law. - No work shall be done in or on the public right of way without a licensed and bonded contractor first obtaining a right of way permit. - Any code requirement that may have been overlooked in this plan review does not imply that the requirements have been waived.
Miscellaneous Condition Resolved Prior to Issuance
Engineering Division
Prior to issuance the sewer lateral inspection provided to Jeff Hill and Antwan Rhymes must be approved. Please ask Jamie Carter to approve this condition while/if I am out of the office. LL 12/20/2023

Related Permit & Planning Applications

Reference Number Status Type
PRCTI20221698 Closed Commercial - Tenant Improvement/Remodel
PRCCP20221725 Closed Civil Construction Permit
PRHM20231549 Closed Hydraulic Modeling
PRFS20231656 Closed Fire Sprinklers
PRFA20231782 Closed Fire Alarms
PRFA20231783 Closed Fire Alarms
PRROW20240592 Closed Right-of-Way Permit

Documents & Images

Date Uploaded File Type Name
11/03/2022 Receipt Receipt for transaction:2022-002203
01/11/2023 Receipt Receipt for transaction:2023-000048
03/30/2023 Receipt Receipt for transaction:2023-000526
04/26/2023 Plans CONSTRUCTION PLAN SET Drawing Set (Stamped)
04/26/2023 Other WSEC Mechanical Compliance Summary (Stamped)
04/26/2023 Other WSEC Mechanical Requirements List (Stamped)
04/26/2023 Other WSEC Project Lighting Form (Stamped)
04/26/2023 Other WSEC Project Lighting Requirements List (Stamped)
04/26/2023 Other WESC Building Mechanical load (Stamped)
04/26/2023 Form PLUMBING FIXTURE WORKSHEET Plumbing fixture worksheet (Stamped)
04/26/2023 Other TRAFFIC SCOPING WORKSHEET Trip Generation and Traffic Impact Fee Estimate - FINAL 03-27-2023 (Stamped)
04/27/2023 Receipt Receipt for transaction: 2023-000720
04/27/2023 Receipt Receipt for transaction: 2023-000720
05/24/2023 Letter Permit Job Card
05/24/2023 Permit Permit - Detailed
10/05/2023 Letter Permit Expiration Notice
11/20/2023 Plans REVISION FORM
11/20/2023 Receipt Receipt for transaction:2023-002210
12/04/2023 Letter Permit Review Correction Letter
12/15/2023 Form Revisions to Existing Residential or Commercial Applications_PRCTI20221714
12/15/2023 Form Permit Revision Correction Response #1 - CHC Garage Sewer
12/15/2023 Form Transmittal 23-12-15
12/20/2023 Receipt Receipt for transaction:2023-002367
12/20/2023 Report Inspection Report (Energy (Insulation) Inspection)
12/29/2023 Plans CONSTRUCTION PLAN SET REVISION - RESUB (Stamped)
02/09/2024 Report Inspection Report (Mechanical Rough In Inspection)
02/22/2024 Receipt Receipt for transaction:2024-000324
03/08/2024 Plans PLAN FOR REV (2) (Stamped)
03/11/2024 Report Inspection Report (Frame Inspection)
03/13/2024 Report Inspection Report (Wallboard / Drywall Inspection)
03/14/2024 Report Inspection Report (Wallboard / Drywall Inspection)
03/18/2024 Report Inspection Report (Plumbing Below Slab Inspection)
03/19/2024 Report Inspection Report (Frame Inspection)
03/21/2024 Report Inspection Report (Energy (Insulation) Inspection)
03/21/2024 Report Inspection Report (Mechanical Rough In Inspection)
03/21/2024 Report Inspection Report (Frame Inspection)
03/22/2024 Report Inspection Report (Wallboard / Drywall Inspection)
03/28/2024 Report Inspection Report (Energy (Insulation) Inspection)
03/28/2024 Report Inspection Report (Frame Inspection)
04/02/2024 Report Inspection Report (Energy (Insulation) Inspection)
04/08/2024 Report Inspection Report (Wallboard / Drywall Inspection)
04/25/2024 Report Inspection Report (Gas Test Inspection)
05/04/2024 Report Inspection Report (Plumbing Rough In Inspection)
05/23/2024 Report Inspection Report (Wallboard / Drywall Inspection)
06/11/2024 Report Inspection Report (Wallboard / Drywall Inspection)
06/21/2024 Report Inspection Report (Mechanical Rough In Inspection)
06/25/2024 Report Inspection Report (Mechanical Rough In Inspection)
06/28/2024 Report Inspection Report (Shear Wall Inspection)
06/28/2024 Report Inspection Report (Refrigeration Line Test Inspection)
06/28/2024 Report Inspection Report (Mechanical Rough In Inspection)
11/01/2024 Receipt Receipt for transaction:2024-002279
11/15/2024 Plans CONSTRUCTION PLAN SET - REV (3) (Stamped)
01/23/2025 Report Inspection Report (Building Final Inspection)
01/24/2025 Other Certificate of Occupancy


Should you need assistance, please contact the Permit Center at (253) 864-4165 option 1.